Questions.pdf
PDF 8 KB Posted
- Attached to
- INTERSECTION IMPROVEMENT Federal contract opportunity
- Solicitation number
- W911S7-16-B-0025
About this file
Questions and answers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911S7-16-B-0025_Bid_Abstract.pdf | ||
| W911S7-16-B-0025_-_0001_Intersection_Improvement.pdf | ||
| Drawings_to_Questions.pdf | ||
| DBA_Wage_Determination_MO160019 _19_Aug_2016.pdf | ||
| 7899_c2v8.pdf | ||
| 7899_s1v8.pdf | ||
| 7899_c1v8.pdf | ||
| W911S716B0025.pdf | ||
| 7899_s2v8.pdf | ||
| 7899_c7v8.pdf | ||
| 7899_c5v8.pdf | ||
| 7899_c3v8.pdf | ||
| 7899_coverv8.pdf | ||
| 7899_s3v8.pdf | ||
| 7899_c4v8.pdf | ||
| W911S716B0025_SOW_Final.pdf | ||
| 7899_c6v8.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911S7-16-B-0025 Intersection Improvement Questions
1. Will the asphalt need to be milled down to the concrete on the roadway like has been previously done on Missouri Ave.?
1A. Yes, after evaluation of the road on a different contract it's been determined that the full depth asphalt removal is necessary.
2. Can the working hours be adjusted on Missouri Ave to 09:00-04:00 the next morning on the
Southbound Lanes and 19:00-15:00 the next day on the Northbound Lanes as has been done effectively this summer on a similar project?
2A. Yes, the work hours can be adjusted as long as they don't interfere with the traffic peak hours.
3. Do you want the concrete splash pads to match the new pads that have been installed in the
Gate St. to First St. Median Project this summer?
3A. Yes, they should be the same.