About this file

Abrasive Blasting Machine

View the file

Other files for this federal contract opportunity

Other files attached to New Tube Abrasive Blasting Machine, newest first.
File Type Posted
W911PT-18-C-0024_Award.pdf PDF
W911PT-18-R-0016_Amendment_0003.pdf PDF
W911PT-18-R-0016_Amendment_002_26_JUN_2018.pdf PDF
W911PT-18-R-0016_Amendment_001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W911PT-18-R-0016 04-May-2018

b. TELEPHONE NUMBER

586-282-8663

8. OFFER DUE DATE/LOCAL TIME

01:00 PM 04 Jun 2018

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911PT9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

GERALD BRODERSON

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

ARMY CONTRACTING COMMAND-WARREN (WVA)

ATTN: CCTA-HDW/BLDG 10

1 BUFFINGTON STREET

WATERVLIET NY 12189-4000

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

333517

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF86

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

34-17-3426 Rev. C

Section SF 30 - BLOCK 14 CONTINUATION PAGE

NOTICE TO OFFERORS

1. This solicitation, is for the procurement of one new Tube Abrasive Blasting Machine for Watervliet Arsenal (WVA) in Watervliet, NY.

2. This solicitation will result in a Firm-Fixed Price contract and will be evaluated on a Lowest Price and Technically Acceptable basis.

3. FOB Point is Destination IAW 52.247-34.

4. Specification #34-17-3426 defines all requirements for this action and can be found herein.

5. Offerors shall reference item 6 (Instructions to Offerors) in Specification #34-17-3426 for additional guidance relative to the structure of its technical proposal.

6. Deliveries will be based on months after Receipt of Order. Actual delivery time for one new tube abrasive balasting machine is anticipated at18 months after date of award (ADA).

Subsequent quantities are estimated to be delivered at a rate of 1 each per 30 calendar days thereafter.

7. The evaluation will be in accordance with FAR 52.212-2, "Evaluation - Commercial Items" , a two-step approach. The Government will award a contract resulting from this solicitation to the responsible offeror whose offer is the lowest price and technically acceptable. Technical acceptance will be evaluated based on the offeror's responses to Attachment 0001 - Comply Sheet for specification #34-17-3426 - New Tube Abrasive Blasting Machine WVA.xls, which will be included with the solicitation.

8. PROPOSAL EVALUATION METHOD

Total Evaluated Price. The offeror shall input pricing for CLINS 0001 and 0002 in the solicitation and sum the two CLIN prices on the pricing page for a Total Evaluated Price. The offeror with the lowest Total Evaluated Price will proceed to an evaluation of the other factors.

Proposals will be evaluated as follows:

STEP 1 - Each proposal will be evaluated to determine the Total Evaluated Price. The Government will identify the proposal with the lowest Total Evaluated Price.

STEP 2 The proposal with the lowest Total Evaluated Price will be evaluated against the Technical – Compliance to Specification factor (See Attachment 001 Compliance sheet for SPEC #34-17-3426) Provided that the proposal is determined to be Technically Acceptable under the Technical –Compliance to Specification Factor and the offeror is determined responsible per FAR 9.104, the proposal will be selected for award.

If the proposal is determined to be Technically Unacceptable under the Technical – Compliance to Specification Factor, the Proposal will not be eligible for award, and the Government will return to Step 1, to begin the process with the next lowest total evaluated priced proposal.

9. A responsive proposal to this solicitation will contain the following:

a. Fully completed Attachment 0001 – Compliance to Specification Spreadsheet

b. Fully completed solicitation (SF 1449) with pricing and all appropriate fill-ins completed

10. QUESTIONS: Questions pertaining to this solicitation should be directed IN WRITING – NO PHONE CALLS WILL BE ACCEPTED to the Contract Specialist identified on the cover page of this solicitation. Questions will be answered using a Question and Answer (Q&A) form that will be posted on FBO before closing. For technical assistance in doing business with the Government, and doing business electronically, please visit the Procurement Technical Assistance Center (PTAC) website at <http://www.aptacus.org/> to locate a regional center.

11. Rejection of Offers

11.1 Offerors must carefully read understand, and provide all the information requested in the Notice to Offerors.

11.1.1 The proposal fails to meaningfully respond to requirements specified in the Notice to Offerors of this solicitation. Examples of failure to meaningfully respond include:

11.1.1.1 A proposal merely offers to perform work according to the solicitation terms or fails to present more than a statement indication its capability to comply with the solicitation terms and does not provide an elaboration as specified in the Notice to Offerors section of this solicitation;

11.1.1.2 A proposal fails to provide any of the data and information required by the Notice to Offerors;

11.1.1.3 A proposal provides some data but omits significant material data and information required by the Notice to Offerors;

11.1.1.4 A proposal merely repeats the contract PWS without elaboration.

11.1.2 The proposal takes exception to the attachments, exhibits, enclosures, or other solicitation terms and conditions.

11.1.3 The proposal is unbalanced as to price. An unbalanced offer is one which is (a) based on prices significantly high or low for one given period versus another period; or (b) the price of one or more contract line item is significantly over or understated as indicated by the application of price analysis techniques. There must be a direct relationship between the effort expended and its cost or price for each year and each CLIN. The PCO may reject a proposal which is deemed unbalanced.

11.1.4 The proposal offers a product or service that does not meet all stated material requirements of the solicitation.

11. 1. 5 The proposal is not submitted to the Government via the Federal Business Opportunities (FBO) system.

12. Award without Discussions. This RFP includes FAR 52.212-1, Instructions to Offerors Commercial Items, which advises Offerors that the Government intends to make award without conducting discussions. Where award will be made with discussions, exchanges with Offerors are limited to Clarifications as defined in FAR 15.306.

Therefore, the Offerors initial proposal should contain the Offerors best terms with respect to the price and non-price factors. However, under FAR52.212-1, the Government reserves the right to hold discussion if necessary.

13. Electronic Contracting

(a) All Army Contracting Command – Warren solicitations will be publicized on the Federal Business Opportunities website (<https://www.fbo.gov>). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

(b) As of 10 August 2015, unless directed to do otherwise in this solicitation, vendors are required to submit a quote or proposal via the Federal Business Opportunities (FBO) system.

Proposals or quotes submitted after this date using any other mechanism, including the Army Single Face to Industry Bid Response System (ASFI BRS) will be rejected.

(c) Requirements for the online FBO bid submission:

1. Vendors must log into the FBO System to be able to submit electronic responses for opportunities.

2. Vendors must be registered in the System for Award Management (SAM) at <www.sam.gov> (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).

3. Once logged into the FBO System, vendors will be asked to enter basic information and directed to upload one or more files containing the proposal/quote and any additional information as outlined in the solicitation.

4. FBO will send an email to vendor’s registered email address confirming the electronic submission.

5. For additional information on submitting electronic bid responses via the FBO system see the FBO Vendor Guide – Section 4.3.1 “Submitting an Electronic Response” (<https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf>).

6. Note to offerors:

(a) Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

(b) It is the responsibility of the Offeror to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure (in this case, received through FBO) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

(c) Solicitations may remain posted on the FBO after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses.

(d) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Government’s intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

14. ALL OR NONE-COMMERCIAL ITEM ACQUISITION

(a) This provision serves as an addendum that modifies paragraph (h) of FAR 52.212-1, entitled INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS. Paragraph (h) is modified to say that the proposal or quote must offer to provide the total quantity of the items in this solicitation.

(b) Only one award will be made as a result of this solicitation. Offers submitted for less than the total quantities of all the items in this solicitation will NOT be considered for award.

14. WVA INFORMATION NOTICE OF WVA INFORMATION/REQUIREMENTS

(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:

(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN

THE REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID,

PLEASE ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.

(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO

THE DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD.

FAILURE TO COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY

RESULT IN TERMINATION OF THE ORDER OR REQUIRE CONSIDERATION IF THE

GOVERNMENT ELECTS TO EXTEND DELIVERY. (NOTE: Nonavailability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid. They are not acceptable excuses for failing to meet the delivery after award).

(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE

JUST AS IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-

CONFORMING PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED

COSTS TO THE ARSENAL.

(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR

CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT

AWARDS.

NOTICE: Throughout this document we may use the terms “we” and “you”, the term “we” means the government of the United States of America, and the term “you” means the contractor.

(b) WVA INFORMATION FOR CONTRACTORS:

“WVA Information for Contractors” document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available.”

POC - CONTRACT SPECIALIST/BUYER: Gerald Broderson________

TELEPHONE NUMBER: 586-282-8663_

E-MAIL ADDRESS: gerald.r.brodeson.civ@mail.mil

CONTRACTOR DUNS NUMBER/CAGE CODE/FAX NUMBER:

Please provide the following information for your company.

VENDOR NAME: _________________________

VENDOR POC: __________________________

POC PHONE: ____________________________

E-MAIL ADDRESS (see note below): __________________________

DUNS NUMBER _______________________

CAGE CODE (if known) __________________

TAX ID NUMBER ________________________

VENDOR FAX NUMBER ________________

NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you. If we experience difficulties with e-mail, it will be data faxed.

(c) AWCF BULK FUND ____ DOES __X__ DOES NOT APPLY

(d) POSTERS:

(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards.

Orders subject to these Acts require contractors to post WH Publication 1313, “Employee Rights on Government Contracts”.

(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, “Employee Rights under the Davis Bacon” and the Office of Federal Contract Compliance poster on “Equal Employment Opportunity is the Law.”

(3) These posters can be accessed electronically at http://www.dol.gov .

(4) Hard copies of the posters will be made available upon request to the contracting officer.

(e) PAYMENTS:

Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://wawf.eb.mil/ using the “my invoice” system. You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.

(f) RELEASE OF INFORMATION:

The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor’s responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.usapa.army.mil/pdffiles/r360_1.pdf

CLAUSES INCORPORATED BY FULL TEXT

52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

Lowest Price

Technical - Compliance to Specification (Offeror must complete Attachment 0001).

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

(End of provision)

Section SF 1449 - CONTINUATION SHEET

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 New Tube Abrasive Blasting Machine

FFP

The new machine covered by this specification shall be a new tube abrasive blasting machine. Pre-drawing requirements under specification #34-17-3426.

FOB: Destination

PSC CD: 3695

NET AMT

Personnel Training

FFP

FFP

See Item 3.1.14 of the specification #34-17-3426 for training personnel requirements.

FOB: Destination

Contract Data Requirements List

FFP

Contract Data Requirements List (CDRL) CDRLs A001 through A016 are to be NOT SEPERATELY PRICED. Only CLINs 1001 and 1002 will make up the total price.

SPECIFICATION

Specification for a New Tube Abrasive Blasting Machine

Spec. # 34-17-3426

Manufacturing Engineering Work Group Watervliet Arsenal

Watervliet, New York 12189 5/03/2018

Department of the Army

TACOM

1 Scope: This specification describes the requirements for the turn-key installation of a front loading, continuous pressure, roll blasting cabinet capable of processing tubes that range 8 to 16 inches in outside diameter and 10 to 40 feet in length. The turn-key installation shall include all inter-machine wiring and airlines. The maximum workpiece weight will be 8,000 lbs. The machine shall be similar in design and function to the Watervliet Arsenal’s existing Tube Abrasive Blasting Machine, WV 12797, with one exception being the ability to accommodate a longer, heavier workpiece. The machine’s capabilities shall be equal to or better than WV 12797.

2 Applicable Standards and Publications: All work performed and procedures followed in association with this project shall meet or exceed all applicable and current OSHA, local, state, and federal government codes and laws relative to fire, safety, environmental, and electrical issues. The quality of all work performed and material provided shall meet or exceed the latest applicable industry standards and engineering practices for this type of equipment and its intended function. In all instances material, quality, and workmanship shall meet or exceed OEM specifications.

3 Requirements: All requirements are mandatory from the standpoint of intended function.

Wherever a specific requirement would force an offeror to depart from their standard practice or configuration, the Arsenal will accept, for evaluation, alternative offers for achieving the intended function. Any such alternative offers must be accompanied by sufficient technical information to allow the evaluator to reach a definite conclusion that the alternative is equal to or better than that specified.

3.1 General Requirements

3.1.1 Design and Engineering. The machine shall be designed and engineered in accordance with the latest standards recognized or adopted by the Association for Manufacturing Technology (formerly the National Machine Tool Builders Association). The design and engineering shall incorporate only concepts, systems, materials and new components which have been proven in prior use. Modifications to manufacturer’s standard designs to achieve requirements specified herein are not permissible if they result in deviations from good design practice.

3.1.2 Materials. Materials incorporated in the construction of the machine shall be of sound and uniform quality, free from defects and shall conform in specification, heat treatment and suitability to the standards recognized or adopted by the Association for Manufacturing Technology for this type and class of equipment.

3.1.3 Construction. All parts of the machine shall be new and unused and shall be constructed so as to be capable of withstanding all forces encountered during operation to its maximum rated capacity. The structure and assembly of the machine and its components shall be sufficiently rigid that workpiece finish and accuracy are not impaired by machine vibrations.

3.1.4 Workmanship. Workmanship throughout the machine and its equipment shall be of good quality and in conformance to the manufacturer's engineering drawings and to standards recognized or adopted by the Association for Manufacturing Technology / National Machine Tool Builders Association.

3.1.5 Castings and Forgings. All castings and forgings shall be free of defects, scale, and mismatching. Weldments, if used, shall be braced, ribbed and gusseted to obtain strength equal to or better than the strength of castings, and shall be properly stressed relieved.

3.1.6 Maintainability. All parts subject to wear, distortion or failure and all parts which require periodic adjustment shall be readily and safely accessible for repair, replacement or adjustment as applicable. Instructions for maintenance and adjustments shall be clear, concise and definite in application.

3.1.7 Interchangeability. All parts bearing the same part number shall be functionally interchangeable. Insofar as practical, the machine shall utilize the same parts as the Watervliet Arsenal’s existing Tube Abrasive Blasting Machine, WV 12797.

3.1.8 Applicable Power Source. The power source to which the machine will be connected furnishes a nominal 480 volts, 3 phase, 60 Hz AC. However, the machine shall be tolerant enough of line fluctuations to operate normally at source voltages ranging from 432 to 504 volts.

3.1.8.1 Conversion Equipment. If DC or reduced voltage AC is required to meet any specified requirement, the necessary conversion or transformation equipment shall be furnished with the machine by the contractor. All transformers must meet NEMA TP 1-2002 energy efficiency requirements.

3.1.8.2 Cabinet Enclosure for Electronic Equipment. All separate electrical hardware / circuitry are to be housed in a NEMA rated enclosure/cabinet. Should forced ventilation be necessary to maintain the interior of the enclosure at a temperature to ensure good product reliability, filtered air shall be forced into the cabinet to maintain an over pressure condition in the cabinet. The cabinet shall not inhibit operator access to the controls and/or adjustments.

3.1.8.3 Interconnecting Wiring. All wiring shall comply with accepted Joint Industry Code (JIC), National Machine Tool Builders Association (NMTBA), and National Fire Protection Association (NFPA) Standards.

3.1.8.4 Motors. All motors provided shall be of the optimum type and horsepower rating to meet intended application and usage based on accepted engineering practice. All motors shall be equipped with thermal overload protection. All motors shall be housed in enclosures of the appropriate NEMA type for the class and severity of service. Each motor shall bear an identification plate containing, as a minimum, the identity of the manufacturer, the model, serial number, input voltage, amperage, horsepower, phase, frequency and frame or mounting. All AC unidirectional motor housings shall bear a directional arrow to indicate proper rotation direction when correctly wired. All AC motors rated at 25 hp or greater shall be equipped with a "soft start" mechanism which provides for reduced voltage starting. All polyphase AC motors rated at 1 Hp or greater shall be tested per IEEE Standard 112-Method B and must meet Premium Efficiency requirements per NEMA MG 1-2006 Table 12-12 or IE3 (IEC 60034-30:2008). All motors are to be permanently lubricated and sealed unless the contractor can substantiate that this feature cannot be offered by two (2) or more major motor manufacturers.

3.1.8.5 Operator Control Voltage. All electrical controls meant for use by the operator of the machine shall carry a maximum of 120 volts AC @ 60 Hz.

3.1.9 Safety and Environmental Features. The contractor shall review the environmental requirements documented in Enclosure D and comply as applicable.

3.1.9.1 Protection of Machine Operator. Protection of the machine operator and other personnel shall be accomplished in accordance with all pertinent state, federal, local laws and regulations.

3.1.9.2 Protection of the Machine. The machine shall be fully equipped with the devices necessary to prevent self-damage in the event of malfunction and/or ordinary operator negligence insofar as practical. The system shall be equipped with the necessary protective devices required to prevent electrical/electronic damage to the system because of over-travel, power failure, and the resultant start and stop due to power failure.

3.1.9.3 Noise Levels. Noise levels at a distance not exceeding one meter from the nearest point on the machine shall, under no circumstances, exceed a maximum of 85 A-dba when measured by a properly calibrated sound level meter set for “A” weighting and slow response. Any shields, baffles, enclosures or other devices required to bring the machine into conformance with this noise level requirement shall be furnished by the contractor. Any such devices shall not interfere with the proper operation of the machine and shall be designed to preserve the visibility needed for safe operation and ease of maintenance.

3.1.9.4 Ozone Depleting Substances. Section 326 of Public Law 102-484 precludes the Dept. of Defense from awarding any contract that directly or indirectly requires the use of a class I ozone-depleting substance within the Government specification or standards set forth in the contract. Enclosure B is a list of the restricted Class I CFC's and Halons. All shall be replaced by new functionally equivalent substances or systems that are approved for use by the Environmental Protection Agency (EPA) and have an "Ozone-Depletion-Potential" (ODP) rating of zero. Safety Data sheets (SDS) shall be submitted for approval to Watervliet Arsenal at the time of the submission of proposal

Definition: Ozone-Depletion-Potential (ODP). The relative capacity of a substance, per unit weight, for destroying the earth's stratospheric ozone layer, in comparison with CFC-11, CFC-12 and CFC- 114, each having been assigned an ODP of 1.00.

Note: Offerors are responsible to obtain and adhere to the most current list of prohibited substances as of the date of the submission of bids or proposals.

3.1.9.5 Asbestos and Mercury Free Certification. All materials utilized in the system shall be certified as asbestos and mercury free unless substitute materials do not exist.

This certification shall be provided prior to machine delivery (IAW CDRL A001).

3.1.9.6 Lead-Free and Chromium-Free Paint Certification. All paints and primers applied to the system shall be certified as lead and chromium-free. Lead based paint is paint that contains more than nine thousandths of one percent (0.009%) lead by weight. This certification shall be provided prior to machine delivery (IAW CDRL A002).

3.1.9.7 PCB-Free Certification. To the extent that the machine may have been charged with lubrication and/or hydraulic fluids at the contractor's plant for preliminary acceptance inspection, these fluids shall not contain Polychlorinated Biphenyl’s (PCB’s). The machine and their equipment shall be certified as PCB-free prior to being shipped (IAW CDRL A003).

3.1.10 Identification Plate. A corrosion-resistant metal plate shall be securely attached to the machine in a visible location in the vicinity of the operator's workstation. This plate shall bear, as a minimum, the information called for as follows, with space at the bottom for one additional line of information to be applied by the government.

Nomenclature Manufacturer's name Model Manufacturer's Serial Number Power Input (voltage, phase, frequency, and total amps) Government Contract Number Date of Manufacture

NOTE: Information required by clause 252.211-7003 – ITEM UNIQUE IDENTIFICATION AND VALUATION shall also be included on this Identification Plate.

3.1.11 Lubrication. The machine shall be equipped to provide sufficient lubrication to every moving part where lubrication is essential to prevent damage. If the machine requires periodic, additional lubrication over the life of the machine, a corrosion resistant metal lubrication plate (or plates) shall be permanently fastened to the machine and shall clearly indicate the type and viscosity of lubricant and the service interval for all automatic and manual lubrication reservoirs and fittings. The plate shall include a simple diagram which depicts the physical location of all lubrication points on the machine structure. The contractor is requested to choose required lubricants, fluids, and oils from Enclosure A.

3.1.12 Painting. All exterior machine surfaces shall be painted except where bright metal, aluminum, granite, or other critical surfaces are required for machine function or to otherwise adhere to the requirements of this specification. Paint shall be chromium-free and lead-free.

Quality and manner of application shall be such as to afford protection throughout the normal life of the machine. Danger areas shall be painted red and caution areas shall be painted yellow in accordance with OSHA Standard 1910.144. Appropriate warning signs, tags or emblems will be affixed to respective areas of the machine in accordance with OSHA Standard 1910.145.

3.1.13 Technical Data. All data shall be in the English language and shall be furnished in accordance with the quantities, formats and delivery dates below. All data shall be packaged and delivered separately from the machine itself marked to the attention of the Technical POC.

Please note any AutoCAD drawings provided shall be saved as AutoCAD 2015 files.

a. Foundation Drawings, Standard or Special (see note): Shall be complete in all construction detail to permit pricing and construction by a general contractor and shall be furnished 225 days prior to scheduled delivery of the machine. All drawings shall be dimensioned in English units. One electronic copy on CD in AutoCAD .dwg or .dxf format shall be provided 225 days prior to scheduled delivery of the machine. When drawings are finalized the contractor shall certify the accuracy of the drawings by providing a stamped and signed hard copy of the drawings to the Watervliet Contracting Officer (IAW CDRL A004).

NOTE: Typical floor thickness at Watervliet is 8”-10”. A special foundation is one which exceeds thickness, load bearing capability and vibration insulation of Watervliet Arsenal's standard monolithic concrete flooring of 1,000 pounds per square foot load rating and/or one which requires a specific thickness, specifically-shaped excavations for coolant housings, chip conveyors, electrical circuits and conductors, etc.

b. Machine and Equipment Floor Plan: One digitized machine and equipment floor plan in AutoCAD .dwg or .dxf format shall be provided on a CD. This plan shall depict the complete machine space envelope including all ancillary equipment and the dimensioned bolt-hole pattern of the hold-down bolts for the machine. This AutoCAD drawing(s) shall also contain information that indicates the type, magnitude, and connection points of all plant utilities (electrical power including the full load amperage requirements, air, water, etc.) required to operate the machine. This data shall be furnished 60 days prior to scheduled delivery of the machine (IAW CDRL A005). Also, if a foundation is required for the offered machine then this drawing shall also clearly depict the outline of the foundation and provide locating dimensions from a fixed point on the machine to at least one corner of the foundation. When drawings are finalized the contractor shall certify the accuracy of the drawings by providing a stamped and signed hard copy of the drawings to the Watervliet Contracting Officer.

c. Catalog of Standard Tooling and Accessories shall be furnished 30 days after award of contract. For offers of foreign built machine tools (i.e., machines built outside the United States, its possessions or Canada), the catalog shall set forth U.S. domestic sources of supply (IAW CDRL A015) (one electronic copy on CD).

d. Non-Standard (special) Tooling and Accessories. To the extent that this specification requires the development of unique tooling and/or accessories not generally available commercially, a set of drawings and specifications sufficiently complete to permit manufacture of such tooling and accessories shall be furnished at the time of machine delivery. Dimensional information shall be in English units (IAWCDRL A006) One electronic copy on CD in AutoCAD .dwg or .dxf format shall be provided prior to machine delivery.

e. Installation Instructions and Drawings containing all necessary information to install the equipment. This shall include a drawing containing the certified dimensioned locations of all equipment mounting/holddown holes. To be furnished 60 days prior to scheduled delivery of the machine (IAWCDRL A007). One electronic copy on CD in AutoCAD .dwg or .dxf format shall be provided prior to machine delivery.

f. Lubrication Diagram or Instruction. To be delivered at time of machine delivery (if required (IAWCDRL A008). One electronic copy on CD in AutoCAD .dwg or .dxf format shall be provided.

g. Operating Instructions. These instructions shall be in the English language and be provided in separate manuals from other technical data provided. Instructions must include all updates for hardware and software. To be delivered upon machine delivery (IAW CDRL A009).

Three hardcopies and one electronic copy on CD shall be provided.

h. Maintenance and Troubleshooting Instructions for all machine systems. This material shall also include the machine’s mechanical assembly drawings. To be delivered at time of machine delivery (IAW CDRL A010) Two hardcopies and one electronic copy on CD in AutoCAD .dwg or .dxf format of the machine’s mechanical assembly drawings.

i. Electrical and hydraulic schematics To be considered acceptable, these schematics must clearly portray all as-built electrical and hydraulic ties to their respective main systems. Two hardcopies and one electronic copy on CD in AutoCAD .dwg or .dxf format. Final as-built drawings to be furnished not later than 30 days after final acceptance of the machine-(IAW

CDRL A011).

NOTE : If during installation and testing, the actual electrical and/or hydraulic systems are configured differently than depicted on the schematics, receipt of the revised "As-Built" schematics shall be a condition of final acceptance.

j. Repair Parts Catalog. This catalog shall encompass every replaceable part in the machine and shall include appropriate identification and ordering data. Items which can normally be purchased locally may be indicated provided they are sufficiently described. The repair parts catalog shall include illustrations which clearly locate parts within larger sub-assemblies. To be furnished not later than 30 days prior to delivery of the machine-(IAW CDRLA012). (one electronic copy on CD)

k. Programming Manuals. Programming manuals for all languages and functionality on the machine shall be supplied in the English language and be of the latest revision. These manuals shall include, or be supplemented by, a clear summary of the control functions actually implemented and usable on the system offered or specified. These manuals shall be delivered at machine delivery (IAW CDRL A013) and include one hardcopy and one electronic copy on

CD.

l. Software Documentation. The offeror shall provide copies of all system software and/or ladder logic developed to control and interface with the machine, controller, and computer hardware and include one electronic copy on CD. To be delivered to the technical POC 30 days after final acceptance of the machine (IAW CDRL A014).

3.1.14 Training Required. The contractor shall be responsible for providing training of WVA personnel normally lasting one week. The type and extent of training shall depend upon whether the contractor's machine is equipped with numerical control. All instructions and materials, oral or written, shall be in English. "On-Site" means "At WVA " and "Off-Site" means "a location within the U.S. away from WVA as determined and arranged for by the contractor".

The quality of the training shall be such that at the conclusion of the specified training time, each individual within their assigned category shall be capable of repairing, operating or programming the machine to its productive capacity. Training shall be in accordance with the applicable areas of the following schedule:

Type of training Number of persons When required Training location

Operator training 4 After delivery On site

Maintenance training 4 After delivery On site

Note: For all training, the associated technical data (see 3.1.13) shall be on hand at the time of instruction and its use and interpretation shall be covered during the training. A training schedule showing the hours of training for each person under their assigned category, shall be sent in with proposals for review.

3.1.15 Pneumatic Requirements. If air is needed for any machine operation or function, the machine shall be fully equipped with all necessary piping, valving, regulators, etc., fully installed to the point of connection to which the Arsenal will connect shop air. Available shop air at the Arsenal is 85 psi and if higher or lower pressure is needed at the machine, the machine shall be fully equipped with the devices needed to modify the 85 psi supply pressure. The machine shall also be equipped with devices to remove the normal moisture and other contaminants usually present in shop air supplies. Normal moisture is defined as that moisture produced when air at a relative humidity of 75% has been compressed to 85 psig. If an air compressor is required, it shall be sized and provided by the contractor. The air compressor may be quoted as an option as the Arsenal may place the machine near an existing air compressor.

With input from the contractor, the Arsenal will determine whether an existing air compressor can be used or whether to exercise an option for a new air compressor. All necessary airlines from the compressor (new or existing) to the machine shall be supplied and installed by the contractor. Airlines shall be hard piped and not utilize hose. Airlines shall not lay on the floor as to pose a tripping hazard.

3.1.16 Special Tools. If any element of machine operation or maintenance requires the use of specially designed tools, these tools shall be provided with the machine and shall become the property of the Government.

3.1.17 Site Conditions. The machine covered by this specification will be installed in a general machine shop space where there is currently no environmental conditioning.

Temperatures will range from 60 °F (15 °C) to 95 °F (35 °C) and relative humidity will range from 20% or less to 95%. On any given day the temperature in the machine shop may change as much as 4 °F per hour. These are the conditions under which the machine is expected to perform as specified, and the contractor shall be responsible for supplying whatever is required to meet the specified performance. The only permissible exception is positioning accuracy for numerically controlled machines.

3.1.18 Heat Exchange Equipment. Heat exchange equipment shall be furnished with the machine wherever it is needed to keep operating temperatures within design or specified limits. Any heat exchange equipment using water as the heat exchange medium shall be fully recirculating and shall not require the continuing input and discharge of Arsenal water supply.

Waste water systems of any type are not acceptable.

3.1.19 Machine Installation, Startup and Testing.

3.1.19.1 Work to be Performed by the Arsenal. Upon receipt of the required installation and foundation drawings (see 3.1.13), Watervliet Arsenal will identify an intended installation site prior to delivery of the machine. After placement of the machine by the contractor/riggers, Watervliet Arsenal will run utilities to first points of connection. However, if the installation instructions supplied by the contractor are incomplete or insufficiently detailed, installation work will stop and the contractor will be required to dispatch a service engineer.

Installation will resume upon their arrival and continue under their guidance.

NOTE: If installation instructions, foundation drawings and electrical and hydraulic schematics are not delivered at or before the times specified (see 3.1.13), the Government reserves the right to forestall delivery and/or final acceptance testing of the machine by an amount of time equal to the delay in receipt of instructions, drawings or schematics.

3.1.19.2 Work to be Performed by the Contractor. This project is classified as a turn-key with the contractor being responsible for all costs and work associated with the installation unless otherwise stated. The Contractor shall be solely responsible for all costs associated with skidding and shipment, rigging, and installation at WVA. Once an installation site is identified by Watervliet personnel and if required, a foundation is constructed, the contractor or their designated third party shall install the machine. Contractor personnel shall arrange for rigging services to off load the machine and contractor personnel shall be on-site at Watervliet when the machine arrives and is off loaded to supervise the placement of the machine on the installation site by the rigging service. Outside rigging services should be advised that only certified grade 8 chains are permitted to be used at the Arsenal and that all rigging slings must be tagged and certified for the weights being lifted. In most cases no Arsenal forklift services and/or Arsenal personnel will be available for the installation. Only propane powered forklifts are permitted and must also be equipped with a roll cage. Operators of forklifts shall have and be able to produce valid forklift licenses. Arsenal overhead pendant cranes (within load capacities) can be used by the contractor/rigging service for the installation. The contractor shall provide written certification to the WVA representative that all contractor/rigger personnel are qualified, through either formal training or experience per OSHA, to operate pendant controlled overhead cranes. Contractor personnel shall also adhere to the WVA requirements to wear OSHA approved non-tinted safety glasses with side shields and safety shoes while in the manufacturing shop areas. The contractor shall ensure they bring all equipment/material necessary for the installation of the machine(s). Watervliet does not have the resources to provide such material. Crane capacity within each building is limited (2, 5, 10 or 15 tons) and therefore if not adequate then the contractor will need to provide alternate means necessary for the installation. Specific building crane capacities where the equipment is to be installed should be verified with the WVA technical POC.

Once the machine is positioned and rough leveled by the contractor, WVA personnel will run utilities to the machine. Watervliet must be provided with sufficient time to accomplish these connections. The contractor, through their own service personnel shall be fully responsible for the startup and testing of the machine, conduct any acceptance tests specified in sections 3 & 4 and perform the required on-site training. The contractor and the service personnel shall remain until the machine activation and testing have been successfully completed. Under no circumstances should the contractor plan on gratuitous Arsenal assistance for diagnosis, troubleshooting or repair of the equipment during activation and testing. Should such activity prove necessary, it shall be the contractor's responsibility to provide the appropriate labor and materials. If the contractor chooses to request Arsenal assistance in lieu of providing their own resources, the request will be reviewed by the Technical POC who shall reserve the right to impose a charge for the assistance. Approvals, even on a charge basis, should not be taken for granted since there is no guarantee that appropriate Arsenal personnel will be readily available.

In such cases, the Arsenal will not be held responsible for delays in acceptance of the equipment resulting from non-availability of Arsenal personnel or Arsenal-furnished equipment.

IMPORTANT: Under normal circumstances the contractor will be allowed to work as long as is desired during normal work days. Contractor work outside Watervliet’s normal work days cannot be guaranteed. Watervliet is on a condensed work schedule. Normal work hours/days for this schedule are four 9-hour workdays (Friday off) one week and four 9-hour days, one 8-hour day (Friday) the following week. Contractor work on the Friday off and weekends cannot be guaranteed. Contractor’s classified as foreign nationals may further restrict work hours and days available.

If the contractor requests Watervliet Arsenal to ship misc. material via UPS, FedEx or by other similar carrier then the contractor shall provide their carrier account number for this purpose.

3.2 Machine Specific Requirements: The new continuous pressure tube abrasive blasting machine shall be capable of blasting the outer diameter of cylindrical tapered tubes between 10 and 40 feet in length. Workpieces may weigh up to15,000 lbs and measure up to 16” in outer diameter. The machine shall be capable of being loaded by overhead crane. The machine shall rotate a workpiece as it is blasted with 60 grit aluminum oxide blast media. The machine shall be capable of manual blasting operation as well as automatic blasting of programmed zones.

Offered machine must meet or exceed the following characteristics. The vendor shall review and ensure the requirements in the following paragraphs are appropriate for the machine being ordered. If there are conflicting options designated or if other options are required the vendor shall immediately notify the technical POC for clarification.

3.2.1 Concept Drawing: The machine shall be similar in design and function to the Watervliet Arsenal’s existing Tube Abrasive Blasting Machine, WV 12797, with one exception being the ability to accommodate a longer, heavier workpiece. The machine’s capabilities shall be equal to or better than WV 12797. With their proposal, the contractor shall submit a concept drawing depicting the main machine features required by this specification. A top, side, and front view shall be provided.