Amendment 0002 to revise specifications and drawings, add the bidder inquiry report, and extend the proposal due date from 14 August 2019, 2:00PM Alaska Time, to 16 August 2019, 2:00PM Alaska Time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B.08.03_Amendment_0003.pdf | ||
| Mod_0001.pdf | ||
| JBE047_J&As_Redacted.pdf | ||
| JBE047_Drawings_2019-05-17.pdf | ||
| JBE047_Specifications_1Jul19.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JBE047
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE/LOCATION: JBE047 POL Operations Facility, Joint Base Elmendorf/Richardson (Elmendorf), Alaska.
The purpose of this Amendment is to revise specifications and draw ings, as outlined on the attached summary of changes page, provide the bidder inquiry report, and extend the proposal due date from 14 August 2019, 2:00PM Alaska Time, to 16 August 2019, 2:00PM Alaska Time.
All other terms and conditions outlined in the Solicitation remain the same.
POC for this Amendment is Ron Jackson, 907 753-5596.
1. CONTRACT ID CODE PAGE OF PAGES
1 153
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB19R0020
X 9B. DATED (SEE ITEM 11)
01-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Aug-2019
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
Amendment 0002 (AM#02) 08 August 2019
Summary of Changes
a. The following drawings are substituted for the superseded documents/sections:
D-101 - Building 11673 Site and Utility Demolition Plan
C-501 - Civil Details 1
C-505 - Civil Details 5
A-102 - First Floor Reflected Ceiling Plan
A-201 - West and South Exterior Elevations
A-302 - Building Longitudinal Section
A-311 - Typical Exterior Wall Section
A-313 - Wall Sections
A-501 - Exterior Details
A-502 - Exterior Details
A-503 - Exterior Details
A-701 - Interior Details
S-101 - Structural Foundation Plan
S-202 - Canopy Type A Roof Framing Plan
S-110 - Structural Concrete Shear Wall Elevations
S-111 - Structural Concrete Shear Wall Elevations 2
S-502 - Structural Foundation Details 2
S-504 - Structural Roof Framing Details 2
E-101 - Electrical Site Plan
E-105 - Grounding Plan
E-502 - Communication Details
E-504 - Power Details 1
b. The following drawings are added:
NONE
c. The following revised documents/sections are substituted for the superseded documents/sections:
The identifier “AM#02…” appears before and "…AM#02" after new and/or revised materials.
00 22 11 - Proposal Submission Requirements, Evaluation Criteria and Basis of Award One Step - Best Value. Only the pages revised are provided for this section.
02 41 00 - Demolition
07 27 10.00 10 - Building Air Barrier System
09 06 00 - Schedules for Finishes
09 29 00 - Gypsum Board
26 36 23.00 20 - Automatic Transfer Switches
27 10 00 - Building Telecommunications Cabling System
31 00 00 - Earthwork
d. The following sections are added:
NONE
e. The following sections are deleted:
22 07 19.00 40 - Plumbing Piping Insulation
23 25 00 - Chemical Treatment of Water for Mechanical Systems
27 05 29.00 - Protective Distribution System (PDS) for SIPRNET Communication Systems
28 08 10 - Electronic Security System Acceptance Testing
f. Other:
Bidder Inquiry Report
The proposal due date is extended from 14 August 2019, 2:00PM Alaska Time, to 16 August 2019, 2:00PM Alaska Time.
ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME
(End of Summary of Changes)
Section 00 22 11 W911KB-19-R-0020
Section 00 22 11 Page 4
5.1.2 Provide a one-page consolidated list of the Specialized Experience projects to include a matrix that identifies the projects and the firms that worked on each one (teaming). Identify if the offeror was the prime on the contract or a subcontractor. Include the completion date and dollar amount executed on the project by the firm establishing the specialized experience.
5.1.3 Provide a supplemental narrative, not to exceed two (2) pages, to address any of the following that are applicable. The information shall be limited to projects that are well underway (at least 50% completed) or that have been completed and turned over no longer than six (6) years preceding the date of this solicitation.
a. Offerors who submit experience information of a parent, sister or other affiliated company shall describe what involvement such company will have on the instant acquisition and demonstrate a firm commitment that the affiliated firm will participate meaningfully in the performance of the contract. The narrative shall clearly and specifically indicate how the resources of the parent, sister, predecessor or other affiliated company – its workforce, management, facilities, or other resources – will be provided or relied upon for contract performance. The Government may discount experience of a parent, sister, predecessor or other affiliated company unless the prime contractor clearly provides, in its proposal, evidence of a binding teaming agreement or other contractual agreement which creates legal responsibility on the part of the parent, sister, predecessor or other affiliated company. If there is no contractual arrangement between the prime contractor and the parent, sister, predecessor or other affiliated company, provide a
Meaningful Relationship Commitment Letter including the following:
1. A statement of commitment as to the performance and utilization of the identified entity’s resources on this project.
2. Signatures of both the Offeror and Meaningful Relationship Entity.
b. AM#02… Provide a list of subcontractors and describe any previous teaming experience between the prime contractor and subcontractors identified under Tab C. Provide a matrix that identifies specific projects and teaming. …AM#02
c. If submitting projects performed under a prior business arrangement (joint venture, for example) for Factor
1, Specialized Experience, address why that experience is relevant to the experience of the firm submitting the offer.
Clearly identify the role and responsibilities of each joint venture partner.
5.2 Evaluation Criteria:
5.2.1 The Government will evaluate the extent of recent, relevant experience of the prime contractor as relevant to their role proposed on this project. Experience on the similar projects identified on the project experience sheets (Attachment
2) will receive more consideration than experience provided in the supplemental narrative. The Government may place greater importance on projects performed as a prime contractor than as a subcontractor, depending upon overall role and relevancy considerations. Federal Government project experience will not be rated inherently more important than non-
Federal Government project experience. In assessing relevancy of Specialized Experience, the relevancy ratings included at the end of this section will be utilized.
5.2.2 The Offeror must submit the requested information to demonstrate a record of recent, related experience for construction of the facility type, which may include similar state or local government or private counterparts. Recent experience includes projects well underway (at least 50% completed) or those completed and turned over within six (6) years of the proposal issue date for this RFP for construction experience. Joint Venture partners shall each demonstrate
Section 00 22 11 W911KB-19-R-0020
Section 00 22 11 Page 10 field overhead costs through the proposed contract duration are inclusive in the offered price for the contract.
9.3.2 If deemed necessary, the supplemental price breakdown information will be used to assist the Government in performing the price evaluations described above.
10.0 VOLUME 2, TAB B - REQUIRED PRE-AWARD INFORMATION
10.1 Submission Requirements:
10.1.1 Submit this information for the Contracting Officer’s determination of Offeror responsibility, which includes, but is not limited to the following:
(a) Joint Venture agreement or Limited Liability Company Certificate of Organization, Articles of Organization and Operating Agreement, if applicable.
(b) A copy of the Offeror’s current AM#02… HUBZone 8(a) …AM#02 certification from the Small Business
Administration (SBA).
(c) A list of present commitments, including the dollar value thereof, and name of the organization under which the work is being performed. Include names and telephone numbers of personnel within each organization who are familiar with the prospective contractor’s performance.
(d) A certified statement listing of each contract awarded within the preceding three (3) month period exceeding
$1,000,000.00 in value with a brief description of the contract. If the prospective contractor is a joint venture, each joint venture member will be required to submit the above defined certification
(e) Competed Representations and Certifications included by full text in Section 00 45 00. Representations and certifications shall also be completed in the System for Award Management (SAM) at www.sam.gov.
(f) Additional information required for responsibility determination:
(1) Proof of Financial Ability (Most recent financial statement covering assets and liabilities)
(2) Number of years the firm has been in business
(3) Name, address and telephone number of firm’s bonding company
(4) Information showing offeror’s bondability for this project. Submit a letter from the prime contractor’s bonding company indicating the offeror’s ability to obtain performance and payment bonds in the amount of their proposal price.
(5) Name, address and telephone numbers of two credit/trade references.
10.1.2 Evaluation Criteria:
In addition to the other proposal information, the Contracting Officer shall use this information in making an affirmative responsibility determination for award to the Successful Offeror, in accordance with FAR Part 9.
11.0 EVALUATION PROCEDURES
POL Operations Facility, JBER, Alaska JBE047
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SF1442 SOLICITATION, OFFER, AND AWARD
Proposal Sched PROPOSAL SCHEDULE FOR JBE047 REPLACE OPERATIONS
FACILITY JBER-ELMENDORF, ALASKA
00 21 00 INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
00 22 11 AM#02...PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION
CRITERIA AND BASIS OF AWARD ONE STEP - BEST VALUE
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 CONTRACT CLAUSES
00 73 00.00 29 SPECIAL CONTRACT REQUIREMENTS
00 73 46 BUILDING AND HEAVY CONSTRUCTION PROJECTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 19 30.00 29 SPECIAL ITEMS
01 19 30.00 29 Attach JBER SPECIAL ITEMS 01 19 30.00 29 Attach SAMPLE LETTER 01 19 30.00 29 Attach BASE ACCESS PROGRAM 01 19 30.00 29 Attach OUSD MEMO NDAA TELECOM PROHIBITION
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 00 Attach ENG FORM 4025-R 01 33 00 Attach SUBMITTAL REGISTER
01 33 29 SUSTAINABILITY REPORTING
01 33 29 Attach AIR FORCE SUSTAINABILITY REQUIREMENTS SCORESHEET
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 36 00.00 29 RADIOACTIVE MATERIALS PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 29 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20.01 29 ENVIRONMENTAL PROTECTION
01 57 34.00 29 STORM WATER POLLUTION PREVENTION MEASURES
01 58 00 PROJECT IDENTIFICATION
01 74 19.01 29 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00 COMMISSIONING
01 91 00 Attach COMMISSIONING PLAN
DIVISION 02 - EXISTING CONDITIONS
02 41 00 AM#02...DEMOLITION
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING
PCBs AND MERCURY
PROJECT TABLE OF CONTENTS Page 2
DIVISION 03 – CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 11 19.00 10 INSULATING CONCRETE FORMING
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 35 43.13 POLISHED CONCRETE FINISHING
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 51 33 METAL ALTERNATING TREAD DEVICES
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 10 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 19 00 WATER REPELLENTS
07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS
07 27 10.00 10 AM#02...BUILDING AIR BARRIER SYSTEM
07 41 63 FABRICATED ROOF PANEL ASSEMBLIES
07 42 13 METAL WALL PANELS
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 06 00 AM#02...SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 AM#02...GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
PROJECT TABLE OF CONTENTS Page 3
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 11 - EQUIPMENT
11 31 13 ELECTRIC KITCHEN EQUIPMENT
11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 24 13 ROLLER WINDOW SHADES
12 31 00 MANUFACTURED METAL CASEWORK
12 36 00 COUNTERTOPS
12 48 13 FLOOR GRATES
DIVISION 21 - FIRE SUPPRESSION
13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
22 07 19.00 40 AM#02...SECTION DELETED
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST
SYSTEMS
23 01 30.41 HVAC SYSTEM CLEANING
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEM
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL
23 11 25 FACILITY GAS PIPING
23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 25 00 AM#02...SECTION DELETED
23 31 13.00 40 METAL DUCTS
23 36 00.00 40 AIR TERMINAL UNITS
23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS
PROJECT TABLE OF CONTENTS Page 4
23 41 13.00 40 PANEL FILTERS
23 52 00 HEATING BOILERS
23 72 00.00 10 ENERGY RECOVERY SYSTEMS
23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
23 82 16.00 40 AIR COILS
23 82 23.00 40 UNIT VENTILATORS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 05 19.10 10 INSULATED WIRE AND CABLE
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 05 70.00 40 HIGH VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 08 00 APPARATUS INSPECTION AND TESTING
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 12 19.00 40 PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE
TRANSFORMERS
26 18 23.00 40 MEDIUM-VOLTAGE SURGE ARRESTERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 PANELBOARDS
26 27 14.00 20 ELECTRICITY METERING
26 36 23.00 20 AM#02...AUTOMATIC TRANSFER SWITCHES
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 53 00.00 40 EXIT SIGNS
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 05 29.00 AM#02...SECTION DELETED
27 10 00 AM#02...BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
28 08 10 AM#02...SECTION DELETED
DIVISION 31 - EARTHWORK
31 00 00 AM#02...EARTHWORK
31 05 19 GEOTEXTILE
PROJECT TABLE OF CONTENTS Page 5
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 16 13 CONCRETE SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13.53 CHAIN-LINK FENCES AND GATES
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
Page Intentionally Left Blank
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Demolition Plan
1.2.2 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Existing Construction Limits and Protection
1.3.2 Utility Service
1.3.3 Facilities
1.4 BURNING
1.5 AVAILABILITY OF WORK AREAS
1.6 SUBMITTALS
1.7 QUALITY ASSURANCE
1.7.1 Dust and Debris Control
1.8 PROTECTION
1.8.1 Traffic Control Signs
1.8.2 Protection of Personnel
1.9 FOREIGN OBJECT DAMAGE (FOD)
1.10 RELOCATIONS
1.11 EXISTING CONDITIONS
PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Chain Link Fencing
3.1.4 Paving and Slabs
3.1.5 Structural Steel
3.1.6 Miscellaneous Metal
3.1.7 Carpentry
3.1.8 Acoustic Ceiling Tile
3.1.9 Cylinders and Canisters
3.1.10 Locksets on Swinging Doors
3.1.11 Mechanical Equipment and Fixtures
3.1.11.1 Piping
3.1.11.2 Ducts
3.1.11.3 Fixtures, Motors and Machines
3.1.12 Electrical Equipment and Fixtures
SECTION 02 41 00 Page 1
3.1.12.1 Fixtures
3.1.12.2 Electrical Devices
3.1.12.3 Wiring Ducts or Troughs
3.1.12.4 Conduit and Miscellaneous Items
3.2 CONCURRENT EARTH-MOVING OPERATIONS
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
3.3.2 Disposal of Ozone Depleting Substance (ODS)
3.3.2.1 Special Instructions
3.3.2.2 Fire Suppression Containers
3.3.3 Transportation Guidance
3.3.4 Unsalvageable and Non-Recyclable Material
3.4 CLEANUP
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
3.5.2 Burning on Government Property
3.5.3 Removal to Spoil Areas on Government Property
3.5.4 Removal from Government Property
-- End of Section Table of Contents --
SECTION 02 41 00 Page 2
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI Guideline K (2009) Guideline for Containers for Recovered Non-Flammable Fluorocarbon Refrigerants
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/ UserWeb/aviationengineering/HazInfo/
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures
MIL-STD-129 (2014; Rev R) Military Marking for Shipment and Storage
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and Lighting
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 82 Protection of Stratospheric Ozone
SECTION 02 41 00 Page 3
49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels
1.2 PROJECT DESCRIPTION
1.2.1 Demolition Plan
Prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, and a detailed description of methods and equipment to be used for each operation and of the sequence of operations.
Coordinate with Waste Management Plan. Include statements affirming Contractor inspection of the existing roof deck and its suitability to perform as a safe working platform or if inspection reveals a safety hazard to workers, state provisions for securing the safety of the workers throughout the performance of the work. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.
1.2.2 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site. The work includes demolition and removal of resulting rubbish and debris.
Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
Construct and maintain shoring, bracing, and supports as required.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.3.2 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition operations. Prior to start of work, utilities serving each area of removal will be shut off by the Government and disconnected and sealed by the Contractor.
1.3.3 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide
SECTION 02 41 00 Page 4 approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.5 AVAILABILITY OF WORK AREAS
Verify locations and availability of work areas and schedule with the Contracting Officer.
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan Existing Conditions
SD-07 Certificates
Notification
SD-11 Closeout Submittals
Receipts
1.7 QUALITY ASSURANCE
Submit timely notification of demolitionprojects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M.
Notify the Regional Office of the United States Environmental Protection Agency (USEPA), State's environmental protection agency, local air pollution control district/agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6 .
Comply with the Environmental Protection Agency requirements specified.
Use of explosives will not be permitted.
1.7.1 Dust and Debris Control
Prevent the spread of dust and debris to occupied portions of the building, on airfield pavements, and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.
SECTION 02 41 00 Page 5
1.8 PROTECTION
1.8.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.
Provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet, but less than 200 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over 200 ft above ground level provide obstruction lighting in accordance with FAA AC 70/7460-1 . Light construction and installation shall comply with FAA AC 70/7460-1 . Lights shall be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.
1.8.2 Protection of Personnel
Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.9 FOREIGN OBJECT DAMAGE (FOD)
Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts.
Remove barricade when no longer required.
1.10 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.11 EXISTING CONDITIONS
Before beginning any demolition, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting
SECTION 02 41 00 Page 6 electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with specification Section 31 00 00 EARTHWORK for excavating, backfilling, and compacting procedures for soils used as backfill material to fill foundations, basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.
b. Fill material shall conform to the definition of unclassified material as defined in specification Section 31 00 00 EARTHWORK.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
a. Remove existing structures to limits indicated on the drawings.
b. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.
Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.
c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
AM#02... d. Salvage requirements: In accordance with Section 01 33 29 Sustainability Reporting, 60% of construction waste must be diverted from general landfill disposal and recyled. At Contractor's option, the items identified in Paragraphs 3.1.3 through 3.1.8 may be recycled and included in the required percentage for the project... AM#02
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
SECTION 02 41 00 Page 7
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities, as indicated on the drawings and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to an approved location in accordance with instructions of the Contracting Officer.
3.1.3 Chain Link Fencing
Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Remove gates as whole units. Cut chain link fabric to 25 foot lengths and store in rolls off the ground.
3.1.4 Paving and Slabs
Remove asphalt pavement to limits and depths as indicated on the drawings.
Provide neat sawcuts at limits of pavement removal as indicated. Pavement and slabs shall be removed from the Installation at Contractor's expense.
3.1.5 Structural Steel
AM#02...DELETED TEXT. Salvage for recycle structural steel, steel joists, girders, angles, plates, columns and shapes. AM#02...DELETED TEXT.
Transport structural steel shapes to a AM#02...DELETED TEXT recycling facility.
3.1.6 Miscellaneous Metal
Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items. AM#02...DELETED TEXT. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. Scrap metal shall become the Contractor's property.
Recycle scrap metal as part of demolition and deconstruction operations.
AM#02...DELETED TEXT. Transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.
3.1.7 Carpentry
Salvage for recycle lumber, millwork items, and finished boards, and sort by type and size. Remove windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories. AM#02...
Transport to a recycling facility... AM#02
3.1.8 Acoustic Ceiling Tile
Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, priority shall be given to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material.
3.1.9 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of
SECTION 02 41 00 Page 8 in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.10 Locksets on Swinging Doors
Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal.
3.1.11 Mechanical Equipment and Fixtures
Disconnect and dispose of all mechanical equipment and fixtures. No equipment or fixtures are to be salvaged.
3.1.11.1 Piping
Disconnect and dispose of all piping and associated valves, unions, flanges and other appurtenances. No piping or related appurtenances are to be salvaged.
3.1.11.2 Ducts
Classify removed duct work as scrap metal.
3.1.11.3 Fixtures, Motors and Machines
Remove and dispose of all fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. No fixtures, motors or machines are to be salvaged.
3.1.12 Electrical Equipment and Fixtures
Remove and dispose of all motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Remove and dispose of all wiring systems and components. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.12.1 Fixtures
Remove and dispose of all electrical fixtures.
3.1.12.2 Electrical Devices
Remove and dispose of all switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items.
3.1.12.3 Wiring Ducts or Troughs
Remove and dispose of all wiring ducts, troughs, plug-in, and disconnecting devices.
3.1.12.4 Conduit and Miscellaneous Items
Remove and dispose of all conduit, supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
SECTION 02 41 00 Page 9
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
All materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Disposal of Ozone Depleting Substance (ODS)
Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS shall be removed from Government property and disposed of in accordance with 40 CFR 82 .
Products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) shall be disposed of in accordance with 40 CFR 82 . Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia.
3.3.2.1 Special Instructions
No more than one type of ODS is permitted in each container. A warning/hazardous label shall be applied to the containers in accordance with Department of Transportation regulations. All cylinders including but not limited to fire extinguishers, spheres, or canisters containing an ODS shall have a tag with the following information:
a. Activity name and unit identification code
b. Activity point of contact and phone number
c. Type of ODS and pounds of ODS contained
d. Date of shipment
e. National stock number (for information, call (804) 279-4525).
3.3.2.2 Fire Suppression Containers
Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used
SECTION 02 41 00 Page 10 to cover exposed actuation mechanisms and discharge ports on these special cylinders.
3.3.3 Transportation Guidance
Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .
3.3.4 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable combustible material off the site.
3.4 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan.
Storage of removed materials on the project site is prohibited.
3.5.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property..
3.5.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.
3.5.4 Removal from Government Property
Transport waste materials removed from demolished structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.
-- End of Section --
SECTION 02 41 00 Page 11
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 07 27 10.00 10
BUILDING AIR BARRIER SYSTEM
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 DEFINITIONS
1.3.1 Air Barrier Accessory
1.3.2 Air Barrier Assembly
1.3.3 Air Barrier Component
1.3.4 Air Barrier Envelope
1.3.5 Air Barrier Material
1.3.6 Air Barrier System
1.3.7 Air Leakage Rate
1.3.8 Air Leakage
1.3.9 Air Permeance
1.3.10 Environmental Separator
1.4 PREPARATORY PHASE OR PRECONSTRUCTION CONFERENCE
1.5 SUBMITTALS
PART 2 PRODUCTS
2.1 VAPOR RETARDER
2.2 PRESSURE SENSITIVE TAPE
2.3 Weather Barriers
2.3.1 Building Wrap
2.3.1.1 Water-Vapor Permeance
2.3.2 Air Permeance
2.3.3 Allowable UV Exposure Time
2.3.4 Flame Propagation Test
2.4 Building-Wrap Tape
PART 3 EXECUTION
3.1 QUALITY CONTROL
3.1.1 Documentation and Reporting
3.1.2 Quality Control Testing And Inspection
3.2 Installation of Vapor Retarder
3.3 Weather barrier installation
3.4 REPAIR AND PROTECTION
SECTION 07 27 10.00 10 Page 1
SECTION 07 27 10.00 10
BUILDING AIR BARRIER SYSTEM
PART 1 GENERAL
1.1 SUMMARY
This Section specifies the construction and quality control of the installation of an air barrier system. Construct the air barrier system indicated, taking responsibility for the means, methods, and workmanship of the installation of the air barrier system. The air barrier must be contiguous and connected across all surfaces of the enclosed air barrier envelope indicated. The maximum leakage requirements of individual air barrier components and materials are specified in the other specification sections covering these item ds.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
AM#02...
ASTM D3833/D3833M (1996; R 2011) Water Vapor Transmission of Pressure-Sensitive Tapes
ASTM D4397 (2016) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM D4541 (2017) Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM E84 (2019a) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E96/E96M (2016) Standard Test Methods for Water Vapor Transmission of Materials...AM#02
1.3 DEFINITIONS
The following terms as they apply to this section.
1.3.1 Air Barrier Accessory
Products designated to maintain air tightness between air barrier materials, air barrier assemblies and air barrier components, to fasten them to the structure of the building, or both (e.g., sealants, tapes, backer rods, transition membranes, fasteners, strapping, primers).
SECTION 07 27 10.00 10 Page 2
1.3.2 Air Barrier Assembly
The combination of air barrier materials and air barrier accessories that are designated and designed within the environmental separator to act as a continuous barrier to the movement of air through the environmental separator.
1.3.3 Air Barrier Component
Pre-manufactured elements such as windows, doors, dampers and service elements that are installed in the environmental separator.
1.3.4 Air Barrier Envelope
The combination of air barrier assemblies and air barrier components, connected by air barrier accessories that are designed to provide a continuous barrier to the movement of air through an environmental separator. There may be more than one air barrier envelope in a single building. Also known as Air Barrier System.
1.3.5 Air Barrier Material
A building material that is designed and constructed to provide the primary resistance to airflow through an air barrier assembly.
1.3.6 Air Barrier System
Same as AIR BARRIER ENVELOPE.
1.3.7 Air Leakage Rate
The rate of airflow (CFM) driven through a unit surface area (sq.ft.) of an assembly or system by a unit static pressure difference (Pa) across the assembly. (example: 0.25 CFM/sq.ft. @ 75 Pa).
1.3.8 Air Leakage
The total airflow (CFM) driven through the air barrier system by a unit static pressure difference (Pa) across the air barrier envelope. (example:
6500 CFM @ 75 Pa).
1.3.9 Air Permeance
The rate of airflow (CFM) through a unit area (sq.ft.) of a material driven by unit static pressure difference (Pa) across the material (example: 0.004 CFM/sq.ft. @ 75 Pa).
1.3.10 Environmental Separator
The parts of a building that separate the controlled interior environment from the uncontrolled exterior environment, or that separate spaces within a building that have dissimilar environments. Also known as the Control Layer.
1.4 PREPARATORY PHASE OR PRECONSTRUCTION CONFERENCE
Organize pre-construction conferences between the air barrier inspector and the sub-contractors involved in the construction of or penetration of
SECTION 07 27 10.00 10 Page 3 the air barrier system to discuss where the work of each sub-contractor begins and ends, the sequence of installation, and each sub-contractor's responsibility to ensure airtight joints, junctures, penetrations and transitions between materials. Discuss the products, and assemblies of products specified in the different sections to be installed by the different sub-contractors.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
AM#02... SD-03 Product Data
Weather Barriers
Vapor Retarder
Pressure Sensitive Tape...AM#02
SD-04 Samples
SD-06 Test Reports
Testing and Inspection; G
SD-07 Certificates
PART 2 PRODUCTS
AM#02... 2.1 VAPOR RETARDER
6 mil thick polyethylene sheeting conforming to ASTM D4397 and having a water vapor permeance of .01 perm or less when tested in accordance with
ASTM E96/E96M.
2.2 PRESSURE SENSITIVE TAPE
As recommended by the vapor retarder manufacturer and having a water vapor permeance rating of one perm or less when tested in accordance with
ASTM D3833/D3833M.
2.3 Weather Barriers
2.3.1 Building Wrap
ASTM E1677, Type I air barrier with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, when tested according to ASTM E84; UV stabilized; and acceptable to authorities having jurisdiction.
2.3.1.1 Water-Vapor Permeance
Not less than 20 perms per ASTM E96/E96M, Desiccant Method (Procedure A).
SECTION 07 27 10.00 10 Page 4
2.3.2 Air Permeance
Not more than 0.004 cfm/sq. ft. at 0.3-inch wg when tested according to
ASTM E 2178.
2.3.3 Allowable UV Exposure Time
Not less than three months.
2.3.4 Flame Propagation Test
Materials and construction shall be as tested according to NFPA 285.
2.4 Building-Wrap Tape
Pressure-sensitive plastic tape recommended by building-wrap manufacturer for sealing joints and penetrations in building wrap...AM#02.
PART 3 EXECUTION
3.1 QUALITY CONTROL
3.1.1 Documentation and Reporting
Document the entire installation process on daily job site reports. These reports include information on the Installer, substrates, substrate preparation, products used, ambient and substrate temperature, the location of the air barrier installation, the results of the quality control procedures, and testing results.
3.1.2 Quality Control Testing And Inspection
Conduct the following tests and inspections as applicable in the presence of the Contracting Officer during installation of the air barrier system, and submit quality control reports as indicated below.
a. Provide a Daily Report of Observations with a copy to the Contracting Officer.
b. Inspect to assure continuity of the air barrier system throughout the building enclosure and that all gaps are covered, the covering is structurally sound, and all penetrations are sealed allowing for no infiltration or exfiltration through the air barrier system.
c. Inspect to assure structural support of the air barrier system to withstand design air…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.