A.07.24_Solicitation_Amendment.pdf

PDF 257 KB Posted

Attached to
Tanana River Area Soil Disposal Federal contract opportunity
Solicitation number
W911KB-17-R-0064
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

Solicitation Amendment

View the file

Other files for this federal contract opportunity

Other files attached to Tanana River Area Soil Disposal, newest first.
File Type Posted
A.07.24_Solicitation_Amendment2.pdf PDF
QandA.pdf PDF
A.07.23_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911KB17R0064

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project Titled: Tanana River OB/OD Area, Ft Wainw right, Alaska has been amended to reflect Q and A from ProjNet.

All other terms and conditions of this solicitation remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

1 32

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jul-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB17R0064

X 9B. DATED (SEE ITEM 11)

23-Jun-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jul-2017

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

PROPOSAL SCHEDULE

PROPOSAL SCHEDULE

Characterization, Transportation, and Disposal of Soil, OB/OD River Site, Fort Wainwright, AK June 9, 2017

Item Task Description Quantity Unit Unit Price Amount

BASE ITEMS

0001 Task 1 Planning Documents 1 Job $

0002 Task 2 Sample Collection and Analysis

1 Job $

0003 Task 3 Transportation and Disposal of Hazardous Soil

0004 Task 4 Reporting 1 Job $

0005 Task 5 Contractor Manpower

Reporting

0006 Task 6 Project Management 1 Job $

SUBTOTAL ITEMS 1-6 $

OPTIONAL ITEMS

0007 Task 3a (Optional) Transportation and Disposal of Additional Hazardous Soil (If exercised, this optional task will be exercised in increments of 10 tons, up to 460 times, not to exceed a total of 4600 tons.)

460 10 Ton

0008 Task 3b (Optional) Transportation and Disposal of Non- Hazardous Soil

1 375

0009 Task 3c (Optional) Transportation and Disposal of Additional Non-Hazardous Soil (If exercised, this optional task will be exercised in increments of 10 tons, up to 420 times, not to exceed a total of 4200 tons.)

420 10

0010 Task 3d (Optional) Transportation and Treatment of Soil 1 375

0011 Task 3e (Optional) Transportation and Treatment of Additional Soil (If exercised, this optional task will be exercised in increments of 10 tons, up to 420 times, not to exceed a total of 4200 tons.)

420 10

0012 Task 3f (Optional) Stockpile

Removal Confirmation Sampling (If exercised, this optional task will be exercised in increments of 1 sample, up to 7 times, for a maximum of 7 samples.)

1 each $ $

SUBTOTAL OPTIONAL

ITEMS 7-12

TOTAL BASE AND

OPTIONS

Options can be award at anythime at the convenience of the government during the period of preformance of this contract.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT

Characterization, Transportation, and Disposal of Soil Small Arms Complex OB/OD River Site, Fort Wainwright, Alaska

9 June 2017 Revised 14 July 2017

1.0 INTRODUCTION

The objective of this performance work statement (PWS) is to characterize, transport, and dispose of excavated soils at the Small Arms Complex Open Burn/Open Detonation (OB/OD) River Site (Table 1), Fort Wainwright, Alaska in accordance with the “Off-Site Rule”, 40 CFR 300.440. The soils were generated during the Time Critical Removal Action (TCRA) at the OB/OD River Site during the 2015 and 2016 field seasons. Additional soil will be generated during the 2017 field season and are included in this scope of work.

The Contractor shall furnish all labor, management, facilities, supplies, equipment, transportation, material, and do all things necessary for, or incidental to, performance of the work as set forth below. The Contractor shall furnish to the Government, reports and other data together with supporting material developed during the period of performance. During the progression of the work, the Contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness, and safe progress of the work.

Table 1 – Source Area Tracking Numbers

Source Area AEDB-R Number HQAES ADEC File Number ADEC Hazard ID Site Status

Open Burn/Open Detonation River Site

FTWW-068 02871.1045 108.38.126 26311 Open

AEDB-R = Army Environmental Database - Restoration HQAES = Headquarters Army Environmental System

2.0 SITE HISTORY

The site is located along the northern bank of the Tanana River within the firing fans from the Small Arms Range Complex (see Figure 1 in FES, 2017). The 5,053 acre Small Arms Range Complex is still in use and is part of the Fort Wainwright Range Complex - Tanana Flats Training Area, which encompasses over 622,000 acres. The Small Arms Range Complex is located directly to the south of the Fort Wainwright cantonment area. The entire 622,000 acre training area is designated as a Dud-Impact Area which means there is a potential to encounter unexploded ordnance (UXO) anywhere within this boundary. The Fort Wainwright Range Complex - Tanana Flats Training Area is an active range. There are no plans for any changes to the current land use in the immediate or distant future. Access to the OB/OD River Site is restricted based on the use of the Small Arms Range Complex and will require coordination with Fort Wainwright Range Control Officer.

On June 27, 2013 significant quantities of munitions debris (MD) were observed by Jacobs Engineering Group Inc. (Jacobs) during a site visit to the OB/OD River Site with personnel from Fort Wainwright Range Control, U.S. Army, and others. The site visit also identified a trench having a fuel odor. The U.S. Army initiated a TCRA in February 2015 by performing a geophysical evaluation of the site using an Electromagnetic (EM) time domain metal detector and ground penetrating radar (GPR). Based on the survey an area of approximately 0.5 acres was found to contain near surface and sub-surface metallic anomalies. In June of 2015 vegetation was removed from the site following a magnetometer assisted surface sweep conducted by UXO personnel. A gravel road and gravel pad were constructed to access the site and facilitate field activities.

The TCRA was performed by the Environmental and Munitions Design Center, Baltimore District, U.S. Army Corps of Engineers (USACE-Baltimore), in 2015 and 2016. Excavation began in August 2015 and continued through September 2016 with breaks for winter conditions (October 2015 through April 2016) and elevated water levels in the Tanana River (July 2016 through August 2016). In March 2016 excavation was conducted within the river channel to access sediment and MD once frozen conditions allowed access to this material. Activities resumed in May 2016 and were completed in September 2016 once water levels in the Tanana River had subsided. Excavated soil and sediment was screened by UXO technicians to identify and remove munitions and explosives of concern (MEC), material documented as an explosive hazard (MDEH), MD, and small arms ammunition (SAA).

During the field effort UXO technicians manually screened the excavation spoils for MEC, MDEH, MD and SAA. The spoils were stockpiled on site and were mechanically screened a second time. A trommel was used to process the excavated soil and sediments and separate residual metallic debris (primarily MD and SAA) from the soil. Soil from one stockpile (DU-10) was not mechanically screened and was composed of soil remaining at the bottom of the two trenches after the majority of the metal was removed. After it was screened, processed soil was stockpiled onsite and all MEC, MDEH, and SAA was transferred to Army Explosive Ordnance Disposal (EOD) unit for proper disposal. MD and other metallic debris determined to be material documented as safe (MDAS) was recycled. Approximately 2,000 cubic yards (cy) of soil and sediment was excavated and screened to remove MEC, MDEH, MD, and SAA. During the TCRA approximately 600,000 pounds of metal debris was sent off post for recycling, 8,375 small arms items will be sent to Tooele Army Ammunition Depot for destruction, and 336 MEC/MDEH were removed from the OB/OD River Site and transferred to EOD for disposal.

Four soil stockpiles remain at the OB/OD River Site. The stockpiles are designated Decision Unit (DU) -7 through DU-10, in accordance with the Post TCRA Soil Sampling Report (FES, 2017).

Soil samples were collected as Multi-Increment (MI) samples as well as discrete samples. MI samples were analyzed for explosives (EPA Method 8330B), metals (EPA Methods 6010C, 6020A, and 7471B), perchlorate (EPA Method 6850), white phosphorous (EPA Method 7580), and pH (EPA Method SM9045D). Toxicity Characteristic Leaching Procedure (TCLP) analysis of RCRA metals (EPA Methods 1311, 6010C, 7470A) and select explosives compounds (2,4- Dinitrotoluene [DNT] and Nitrobenzene, by EPA methods 1311 and 8330B) was performed on MI samples to determine disposal requirements. Discrete samples were analyzed for Volatile Organic Compounds (VOC’s, by EPA method 8260C-LL), gasoline range organics (GRO, by method AK101), diesel range organics (DRO, by method AK102), and semi-volatile organic compounds (SVOC, by EPA method 8270D-LL). Laboratory results are presented in the Post TCRA Soil Sampling Report (FES, 2017). In general, the discrete samples are consistent with and bracket the MI sample results. While the data has been determined to be of sufficient quality for use several results were qualified as estimates and a few were rejected based on missed sample holding times. This primarily affects the TCLP explosives analysis. In addition DU-8 was not fully characterized as the bottom three feet of stockpiled material was not included in the MI analysis. DU-9 exceeded the TCLP criteria for lead and is considered hazardous.

A fifth stockpile will be created in 2017 from soil remaining in the trenches that exceeded 18 AAC

75.341 soil cleanup levels. Soil confirmation samples collected in September 2016 indicate that DRO, 2,4-DNT, 2,6-DNT, Naphthalene, and Nitroglycerin remain above cleanup levels in and around the disposal trenches. USACE-Baltimore will conduct the excavation and any required screening of this material as it is stockpiled. Based on the confirmatory geophysical surveys this material should be free of MEC, MDEH, MD, and SAA.

Table 2 identifies the stockpile ID, stockpile volume, source of material, contaminants that exceeded Alaska Department of Environmental Conservation (ADEC) cleanup levels (ADEC, 2016), and TCLP exceedances from the MI samples. This information will be provided to the contractor for informational purposes as part of the government furnished material (GFM).

Ultimately, the contractor shall perform whatever waste characterization is required leading to disposal and/or treatment in accordance with all Federal, State, and Local regulations.

Table 2 Stockpile

ID

Volume

(yd3) Source ADEC Cleanup Level

Exceedances

TCLP

Exceedance DU-7 850 May-July

Stockpile

2,4-DNT, 2,6-DNT,

Hexachlorobenzene, Naphthalene, Nitroglycerin, Arsenic3, Copper, and Mercury

None

DU-8 1 350 River Sediment Stockpile

2,4-DNT, 2,6-DNT,

Nitroglycerin, and Arsenic3

None

DU-9 2 550 2015

Stockpile

1,3-Dinitrobenzene, 2,4-DNT, 2,6-DNT, DRO, Hexachlorobenzene, Naphthalene, Nitroglycerin, n- Nitrosodiphenylamine and/or Diphenylamine4, Antimony, Arsenic3, Copper, Lead, and Mercury

Lead

DU-10 250 September Stockpile

2,4-DNT, 2,6-DNT,

Nitroglycerin, 2,4,6-TNT, Arsenic3, Copper, and Lead

None

DU-11 1,000 2017

Stockpile

DRO, 2,4-DNT, 2,6-DNT,

Naphthalene, and Nitroglycerin5

TBD

DNT = dinitrotoluene TNT = trinitrotoluene TBD = To Be Determined

Notes:

1. Stockpile DU-8 was not fully characterized the bottom three feet were not included in the MI sample.

2. Stockpile DU-9 has already been determined to be Hazardous Waste based on TCLP Lead exceedance.

3. Arsenic levels are consistent with background and not considered a contaminant at the OB/OD River Site.

4. SVOC compounds n-Nitrosodiphenylamine co-elutes with Diphenylamine.

5. ADEC cleanup level exceedances are based on the results of soil confirmation samples collected following excavation activities in 2016. Characterization of this stockpile is required.

3.0 OBJECTIVE

The objective of this PWS is to characterize, containerize, transport, dispose, and potentially treat previously excavated soils at the site. The soils were, or will be, generated during the TCRA at the OB/OD Tanana River Site during the 2015, 2016, and 2017 field seasons. The disposal of the five soil piles will complete the TCRA at the OB/OD River Site.

4.0 DETAILED DESCRIPTION OF TASKS

The Contractor shall be responsible for performing the work in the base tasks listed as described below. All work performed by the Contractor shall be designed and implemented in a manner which complements earlier and ongoing environmental investigations at Fort Wainwright.

All work shall be in compliance with applicable State, Federal, and Army regulations and guidance, which includes the Resource Conservation and Recovery Act (RCRA), the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), the Superfund Amendments and Re-authorization Act (SARA), the National Contingency Plan (NCP), the Ft Wainwright Federal Facility Agreement (FFA), and State of Alaska regulations. All work shall be performed in cooperation with the State of Alaska, EPA, the United States Army Corps of Engineers (USACE), the Fort Wainwright Directorate of Public Work Environmental Division (DPW), and in accordance with this PWS. Work at the OB/OD River Site shall require coordination with DPW Environmental Division and the Range Control Officer within 30 days of contract award to avoid periods of active use of the Small Arms Range Complex.

The contractor shall assume that work will be performed on weekends and during the evening to accommodate scheduled range activities.

Task 1 – Planning Documents

Work Plan The Contractor shall prepare a detailed and comprehensive work plan (WP) to include all of the tasks to be performed under this PWS. The WP shall describe in detail the quality assurance, quality control, and other technical activities that shall be implemented to ensure that quality data are collected to support project data quality objectives (DQOs).

The Contractor shall provide draft DQOs for approval prior to completion of the pre-draft work plans. If the contractor has an existing Fort Wainwright “Post-Wide Plan” they may revise and/or reference that document, where appropriate, for use on this project. The Contractor may prepare a separate WP for the definable features of work described in Tasks 2 and 3.

A pre-draft, draft, draft final, and final version of this WP shall be required. The pre-draft WP shall be submitted within 60 days of contract award. The pre-draft document shall be provided in electronic format only and the for expedited Government Army review. will provide review comments within 30 days. The Contractor shall revise the WP as necessary and submit a draft within 15 days of receipt and resolution of Army review comments. The draft WP will be provided in electronic format; EPA and ADEC will provide review comments within 30 days of receipt.

The Contractor shall revise the WP as necessary and submit a draft-final within 15 days of receipt and resolution of EPA and ADEC review comments. The draft-final WP shall be submitted electronically (in PDF format) and may need to be submitted as a red-line document to show revisions based on regulatory comments. Upon Army and regulatory approval, a final document shall be submitted both electronically and as hard copies. The final WP shall include electronic copies inclusive of all appendices on CD-ROM. A total of 5 hard copies of the Final document shall be provided. The WP must be approved by the Army, EPA, and ADEC prior to the commencement of the fieldwork. All work will be conducted according to the approved WP. All deviations from the Work Plan must be approved by the USACE Contracting Officer (KO) prior to execution. The WP(s) shall include the Sampling and Analysis Plan, Accident Prevention plan, and Waste Management Plan described below as appropriate.

Sampling and Analysis Plan The Contractor shall develop a Sampling and Analysis Plan (SAP). The SAP shall be prepared in accordance with 18 AAC 75, Department of Defense – Quality Systems Manual (most recent version), ADEC Field Sampling Guidance, ADEC Site Characterization Work Plan and Reporting Guidance, and contain the following elements:

• Field Sampling Plan (FSP): The FSP shall contain sufficient information for field personnel to understand sampling and field measurement requirements. The FSP shall provide a comprehensive description of all onsite activities and necessary supporting information, including: sample locations, sampling procedures, summaries of analyses to be performed, protocols for instrument and equipment operation and use, shipment of samples for offsite analyses, data documentation, and reporting requirements.

• Quality Assurance Project Plan (QAPP): The QAPP shall meet the requirements of the Uniform Federal Policy for Quality Assurance Project Plan (UFP-QAPP) Manual (EPA 2005). The QAPP shall contain sufficient information for field and laboratory personnel to understand the requirements for sample handling, quality control, analytical methods, data review/validation, and data reporting. Appropriate Detection Limits (DLs), Limits of Quantitation (LOQs), and recovery control limits shall be specified and rationale provided.

The QAPP shall also detail how the Contractor intends to meet the data quality objectives and to ensure the accuracy, precision, representativeness, completeness, defensibility, and comparability of the data. The QAPP shall address all levels of the investigation with enough detail to become an audit guide for field and laboratory work. Chain of Custody forms shall be sent by the laboratory to USACE within 24 hours of sample receipt (receipt.cooler@usace.army.mil). The analytical data generated during this project shall be compliant with 18 AAC 75 and the Department of Defense Quality Systems Manual (QSM) definitive data requirements.

Accident Prevention Plan The Contractor shall develop and follow an Accident Prevention Plan (APP) for all field activities associated with this contract and for all persons performing work under this contract. The APP shall be developed and maintained in compliance with the most recent requirements of the USACE Safety and Health Requirements EM 385-1-1 and OSHA standard 29 CFR 1910 and all applicable Federal, State, and local safety and occupational health laws and regulations.

The APP shall include the Site Safety and Health Plan (SSHP) required by EM 385-1-1. Matters of interpretation of standards shall be submitted to the appropriate administrative agency for resolution before starting work. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply.

Waste Management Plan The Contractor shall prepare a plan detailing the manner in which wastes will be managed both onsite and offsite.

The plan shall propose facilities to be used for treatment, storage, and/or disposal; shall identify whether transfer facilities are to be used; and how the wastes will be tracked to ultimate disposal and comply with EPA’s “Off-Site Rule”, 40 CFR 300.440. For any identified RCRA waste, the Contractor shall use RCRA Subtitle C permitted facilities that meet the requirements of 40 CFR 264 or facilities operating under interim status that meet the requirements of 40 CFR 265. Offsite treatment, storage, and/or disposal facilities (TSDFs) with significant RCRA violations or compliance problems (such as facilities known to be releasing hazardous constituents into groundwater, surface water, soil, or air) shall not be used. Facilities receiving hazardous waste must be permitted in accordance with 40 CFR 270, operating under interim status in accordance with 40 CFR 265 requirements, or must be permitted by an authorized state program. The Contractor shall provide the names, physical addresses, telephone numbers, and EPA identification numbers of TSDFs and transporters. This information shall be contained in the Waste Management Plan for approval prior to waste disposal. The EPA RCRA ID Number for this project will be provided by the Government after contract award. The Contractor shall notify the Ft. Wainwright Hazardous Waste Manager immediately if other waste codes will need to be used or if changes in generator status are needed.

The Contractor shall prepare properly completed manifests and provide them to the USACE PM for review in Anchorage, Alaska. The USACE PM will then forward to the Fort Wainwright Hazardous Waste Manager who will review and sign the manifests as the generator. The Contractor shall allow the Government seven calendar days for review and signature of the manifests. The Contractor shall be responsible for signing any Canadian manifests required for transport.

Task 2 – Sample Collection and Analysis

The contractor shall be responsible for collecting waste characterization samples from four of the five soil stockpiles (DU-7, DU-8, DU-10, and DU-11) located at the OB/OD River Site (see Section 2). DU-11 will be a new stockpile that will be generated from additional excavation that will take place in early summer 2017. This DU will be an estimated 1,500 tons. DU-11 has not been characterized but confirmation samples collected following excavation activities in 2016 indicate that DRO, 2,4-DNT, 2,6-DNT, Naphthalene, and Nitroglycerin remain above ADEC cleanup levels. Sample results will be used to determine the appropriate method of disposal (hazardous vs. non-hazardous) or treatment for these soils. Samples shall be collected in accordance with standard sampling protocols in accordance with the WP and EPA/ADEC guidelines. Samples shall be analyzed with the most current EPA and/or ADEC analytical methods. Analytical methods listed below may be substituted for other methods as long as the laboratory is ELAP certified for the substituted method and the Contracting Officer Representative (COR) concurs.

Multi-Increment Characterization Samples The Contractor shall collect one representative MI sample from each of the four stockpiles (DU7, DU8, DU10, and DU-11). One of the stockpiles will require triplicate analysis (3 MI samples) to determine the 95% upper confidence level (UCL) for soil contaminants. Laboratory analysis for all four stockpiles shall include TCLP Explosives (EPA Methods 1311-8330B). Laboratory analysis for DU-8 shall also include DRO (by AK Method 102), VOCs (EPA Method 8260C), and SVOC’s (EPA Method 8270D). Laboratory analysis for DU-11 shall also include DRO (by AK Method 102), explosives (EPA Method 8330B), and SVOC’s (EPA Method 8270D). Additional analysis may be required by the soil disposal facility. The contractor shall submit MI characterization samples to the laboratory on an expedited turn-around time (7 days). MI Stockpile sampling may require a small excavator to assist in collection of representative samples.

The contractor shall be responsible for all of the associated waste characterization for disposal of all hazardous and non-hazardous waste in accordance w/all local, state, and federal regulations. This data will supplement the existing data provided to the contractor as part of the GFM. All laboratories utilized under this contract must be certified by ADEC and the Environmental Laboratory Accreditation Program (ELAP). Analytical data requirements are described in Section 4 of this PWS. Analytical reports, including QA/QC data, shall be furnished in an electronic SEDD 5.2 Stage 2a and a level IV PDF format for each sample delivery group submitted.

Task 3 - Transportation and Disposal of Hazardous Soil (DU-9)

The Contractor shall provide all equipment, transportation documentation, and labor to load, transport, and dispose approximately 750 tons of contaminated hazardous soil from soil stockpile DU-9. This DU failed TCLP analysis for lead and is assumed to be a hazardous waste (FES, 2017).

The contractor shall be responsible for performing any additional chemical analysis required to dispose of this soil in accordance with all Federal, State, and local requirements at an EPA-approved disposal facility. The disposal of the soil at DU 9 must be completed (i.e. removed from the site and in route to the disposal facility) by October 31, 2017.

Optional Task 3a – Transportation and Disposal of Additional Hazardous Soil

The Contractor shall provide all equipment, transportation documentation, and labor to load, transport, and dispose of an additional 10 tons of contaminated hazardous soil from any of the four remaining soil stockpiles (DU-7, DU-8, DU-10, and DU-11). This optional task can be awarded up to 460 times. The contractor shall be responsible for performing any additional chemical analysis required to dispose of this soil in accordance with all Federal, State, and local requirements at an EPA-approved disposal facility

Optional Task 3b – Transportation and Disposal of Non-Hazardous Soil

The Contractor shall provide all equipment, transportation documentation, and labor to load, transport, and dispose 375 tons of contaminated non-hazardous soil from any of the four remaining soil stockpiles (DU-7, DU-8, DU-10, and DU-11). Preliminary characterization results (FES, 2017) indicate elevated levels of select metals and explosive compounds (copper, lead, mercury, 2,4-dinitrotoluene, 2,6-dinitrotoluene, nitroglycerin, etc.), above ADEC soil cleanup levels. Preliminary results indicate that the other four stockpiles (DU-7, DU-8, DU-10, and DU-11) will not be hazardous. However that determination may change based on further characterization. The contractor should be prepared to dispose of all stockpiled soil as hazardous, if this occurs Optional Task 3a above will be executed.

Contaminated soils shall be transported to an EPA-approved disposal facility in accordance with all Federal, State, and Local requirements.

Optional Task 3c – Transportation and Disposal of Additional Non-Hazardous Soil

The Contractor shall provide all equipment, transportation documentation, and labor to load, transport, and dispose of an additional 10 tons of contaminated non-hazardous soil, as described above. This optional task can be awarded up to 420 times.

Optional Task 3d - Transportation and Treatment of Soil

The contractor shall provide all equipment, transportation documentation, and labor to load 375 tons of contaminated soil for transportation from the site to Organic Incineration Technology (OIT), Incorporated in North Pole, AK for thermal treatment. The soil treatment option will require approval by ADEC and EPA. The contractor shall be responsible for providing OIT any required analytical sampling results as required by their operating permit. The contractor shall arrange for transportation of the soil to and from OIT’s facility. After treatment all soil is to be returned to the FTW Small Arms Range Complex from which it was removed. The material shall be placed on the range at the location(s) directed by the Fort Wainwright Range Control Officer.

Optional Task 3e – Transportation and Treatment of Additional Soil

The Contractor shall provide all equipment, transportation documentation, and labor to load for transportation from the site to OIT, an additional 10 tons of contaminated soil, as described in Optional Task 3d. This optional task can be awarded up to 420 times.

Optional Task 3f – Stockpile Removal Confirmation Sampling

In the event that deteriorated stockpile liner is observed, or other indication that a release has occurred from the stockpiles, the Contractor shall perform Stockpile Removal Confirmation Sampling. The Contractor shall collect one representative MI sample from beneath each of the five stockpiles (which have indications of a release) once they have been removed to confirm that contaminants did not leach beneath the stockpile liner. One of the stockpile footprint samples will require triplicate analysis (3 samples) to determine the 95% upper confidence level (UCL) for soil contaminants. The contractor shall submit stockpile confirmation samples to the laboratory using standard turn-around times. Laboratory analysis should include DRO (Method AK102). The contractor shall provide a unit cost for each MI sample. This option may be awarded up to seven

(7) times. The first stockpile confirmation sample collected will require three (3) samples to provide triplicate analysis. Each of the remaining stockpiles where confirmation sampling is required would require one (1) MI sample.

Task 4 - Reporting

The Contractor shall submit a report that summarizes all activities completed under this PWS, including soil transport and disposal, characterization, laboratory analytical data, and any other activities. The report will include the following:

• A detailed description of site activities,

• A photographic log that details site activities,

• Maps with sample locations and results,

• Tables with sample results,

• All waste manifests,

• Analytical results and ADEC Laboratory Data Review Checklist, and

• All field notes and other supporting field documentation including survey data, waste characterization data and disposal certificates, etc. (as Appendices).

A pre-draft, draft, draft final, and final of this document shall be required. The pre-draft document shall be provided in electronic format only within 90 days of receipt of the stockpile confirmation laboratory data and waste manifests.

The Government will provide review comments within 30 days. The contractor shall revise the document as necessary and submit a draft within 15 days of receipt and resolution of Army review comments. The draft document will be provided in electronic format, EPA and ADEC will provide review comments within 30 days of receipt. The Contractor shall revise the document as necessary and submit a draft final within 15 days of receipt and resolution of EPA and ADEC review comments. The draft final report shall be submitted electronically (in PDF and native Microsoft formats) and may need to be submitted as a red-line document to show revisions based on regulatory comment. Upon Army and regulatory approval the final document shall be submitted both electronically and as hard copies. The final report shall include electronic copies inclusive of all appendices and the analytical data deliverable (as discussed in Section 4) on CD-ROM. A total of 5 hard copies of the Final document shall be provided.

Task 5 – Contractor Manpower Reporting

The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for environmental investigations and support at various sites on Ft Wainwright, Alaska via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at: http://www.ecmra.mil/

Task 6 – Project Management

This task includes coordination of client meetings, financial management, contract management for the length of the contract, and closeout activities.

Post-Award Coordination Meeting Within ten (10) days of award of this contract, the Contractor shall attend a Post Award Coordination Meeting with the Army to discuss, at a minimum: the scope; work to be conducted; the project schedule; and any Contractor questions. The Contractor shall prepare meeting minutes and submit them for Army review within 10 days of the http://www.ecmra.mil/ http://www.ecmra.mil/ meeting. Upon Army approval, minutes shall be signed by both the Contractor and the USACE PM, and shall become part of the Contract File.

Monthly Status Report and Conference Calls The Contractor shall participate in monthly conference calls with the Army for the duration of the project. The Contractor shall provide monthly status reports to the COR and USACE PM five days prior to the meeting. The purpose of these calls is to discuss the current status of the projects and address contract deficiencies that may require corrective actions.

Progress Meetings The USACE PM, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the COR will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding contractor issues. For costing purposes, the Contractor shall assume these meetings will occur quarterly for the period of performance of the task order.

5.0 ANALYTICAL DATA REQUIREMENTS

The Contractor shall develop a data management system for both field and laboratory data to ensure that data collected are of adequate quality and quantity to support their intended use. To support this specification, the following are required:

• Any laboratory contracted for this work must be approved under the ADEC and ELAP programs.

• Any laboratory contracted for this work must adhere to QSM requirements (Version 5.1)

• Contractor must request a USACE Project Number prior to finalizing the WP or the report.

• The WP must contain a table that specifies laboratory detection limit (DL), limit of detection (LOD), limit of quantification (LOQ), lower control limit (LCL), upper control limit (UCL), and ADEC and/or TCLP cleanup limits for each analyte/matrix of interest. The WP must clearly denote and discuss any analyte where the cleanup level is greater than the laboratory LOD.

In addition, any collected data shall be reviewed and validated at an appropriate quality control level in a manner consistent with: (1) ADEC Technical Memo 06-002 Environmental Laboratory Data and Quality Assurance Requirements, and (2) the most recent version of the Department of Defense Quality Systems Manual for Environmental Laboratories (DoD QSM) to determine whether it is appropriate for its intended use.

Laboratory deliverables will consist of a PDF of the laboratory data consistent with QSM Stage 4 reporting requirements and SEDD Version 5.2 Stage 2A electronic data. In addition, the Contractor shall provide a completed and detailed ADEC Laboratory Data Review Checklist for each sample delivery group (SDG), and a Chemical Data Report (CDR) summarizing the findings in the checklists in the report. The CDR, at a minimum, will describe the following parameters for all analytical results with respect to the impact that any discrepancies have on the quality and usability of the data: precision, accuracy, representativeness, comparability, completeness, and sensitivity.

6.0 ON-SITE COORDINATION

The Fort Wainwright point of contact is Kristina Smith (907-361-9687) of the Public Works Environmental Office.

Where Contractor activities are likely to require coordination with various Fort Wainwright tenants or private sector customers, the Contractor shall notify Fort Wainwright sufficiently ahead of time to allow for the coordination activities to take place. Work at the OB/OD River Site shall require coordination with DPW Environmental Division and the Range Control Officer within 30 days of contract award to avoid periods of active use of the Small Arms Range Complex. The contractor shall assume that work will be performed on weekends and during the evening to accommodate scheduled range activities.

7.0 PERIOD OF PERFORMANCE

The requirements of the Base Period of Performance for this PWS shall be complete by 1 August 2018.

8.0 AUTHORITY AND POINTS OF CONTACT

The USACE Contracting Officer (KO) is the only person with the authority to act as agent of the Government under this contract. Only the KO has authority to:

(1) Direct or negotiate any changes in the Statement of Objectives or specifications;

(2) Modify or extend the period of performance;

(3) Change the delivery schedule; or

(4) Otherwise change any terms and conditions of this contract.

The USACE KO is the only person authorized to make or approve any changes in any of the requirements of this contract. In the event the Contractor makes any changes at the direction of any person other than the USACE KO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

The Government will conduct periodic inspections of the Contractor’s work to determine compliance with the requirements of this contract. The USACE KO will notify the Contractor of any work that is determined to be noncompliant with the contract requirements. The Contractor shall take immediate corrective action after receipt of such notice. The USACE KO may issue an order stopping all or part of the work until satisfactory corrective actions have been taken.

Points of Contact:

U.S. Army Corps of Engineers

Project Manager:

Mr. Robert Glascott

CEPOA-PM-ESP-IIS

P.O. Box 6898

JBER, AK 99506-6898

P: 907-753-5661 F: 907-753-5659 Email: robert.a.glascott@usace.army.mil

Contracting Officer:

Mr. Aldone Graham

CEPOA-CT-SP

P.O. Box 6898

JBER, AK 99506-6898

P: 907-753-2528 F: 907-753-2544 Email: aldone.r.graham@usace.army.mil

9.0 GENERAL REQUIREMENTS

All reports and data generated under this contract are the property of the government and distribution by the Contractor to any source, unless previously authorized by the USACE Contracting Officer, is prohibited. The Contractor shall not make available to the news media or publicly disclose any data generated or reviewed under this contract. When approached by the news media, the Contractor shall refer them to the Contracting Officer for response. Project reports and data generated under this contract shall become the property of the government and distribution to any other source by the Contractor is prohibited.

10.0 REFERENCES

1. ADEC, 2016, 18 AAC 75, November.

2. Fairbanks Environmental Services (FES), 2017. Post TCRA Soil Sampling Report, Draft, February.

END OF PWS

mailto:robert.a.glascott@usace.army.mil

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

Tanana River OB/OD Area Soil Disposal, Ft Wainwright, Alaska

1.1 GENERAL DESCRIPTION OF WORK

1.2 GOVERNMENT SECURITY REQUIREMENTS

1.3 OFFEROR'S QUESTIONS AND COMMENTS

1.4 SMALL BUSINESS SIZE STANDARD/NAICS CODE

1.5 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

1.6 ACCURACY IN PROPOSALS

1.7 PROPOSAL SUBMISSION REQUIREMENTS

1.8 BIDDER INQUIRIES

1.1. GENERAL DESCRIPTION OF WORK

The objective of this award is to characterize, containerize, transport, dispose, and potentially treat previously excavated soils at the site. The soils were, or will be, generated during the TCRA at the OB/OD Tanana River Site during the 2015, 2016, and 2017 field seasons. The disposal of the five soil piles will complete the TCRA at the OB/OD River Site

1.2. GOVERNMENT SECURITY REQUIREMENTS

The Offeror must ensure that ALL mail sent to the Alaska District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc.

ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at 2204 3rd St, Joint Base Elmendorf- Richardson (JBER), AK 99506, if it does not contain a return mailing address. There will be no exceptions.

1.3. OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to proposal procedures or project specifications see 1.8. Bidder Inquiry section below.

1.4. SMALL BUSINESS SIZE STANDARD/NAICS CODE

NAICS code 562910

Size Standard: 750 Employees

1.5. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

1.6. ACCURACY IN PROPOSAL

The proposal must set forth full, accurate, and complete information as required by this RFP, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

1.7. PROPOSAL SUBMISSION REQUIREMENTS

Please submit your proposal via email to the Contract Specialist at christopher.taylor@usace.army.mil and the Contracting Officer at Timothy.L.Clapp@usace.army.mil Three ring binders should be at 2204 3rd Street JBER, Alaska 99506 before proposal close date.

Please provide the following:

• Cover Letter

• Any Assumptions Made for Tasks in the Performance Work Statement

• Detailed Cost Spreadsheets for Each Task

• Backup Information for Subcontractor Pricing and Equipment Supply Costs

1.8. BIDDER INQUIRIES

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) July 7, 2017. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing. All timely questions and approved answers will be made available through ProjNet.

Approved answers to all timely questions will also be posted in an amendment to the solicitation in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are finalized.

In the event of a conflict between the bidder inquiry responses and the solicitation, the solicitation shall govern.

The Bidder Inquiry Key is: 3R684V-75IYTV The Solicitation Number is : W911KB-17-R-0064 Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

mailto:christopher.taylor@usace.army.mil mailto:Timothy.L.Clapp@usace.army.mil

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

SECTION M - EVALUATION FACTORS FOR AWARD

PROPOSAL EVALUATION CRITERIA

SELECTION PROCEDURES

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA AND BASIS OF AWARD ONE

STEP - - TRADEOFF PROCESS

1.0 OVERVIEW

2.0 BASIS FOR AWARD

3.0 GENERAL INSTRUCTIONS

4.0 PROPOSAL INFORMATION AND RELATED EVALUATION FACTORS

5.0 VOLUME 1 – TAB A - FACTOR 1: TECHNICAL APPROACH

6.0 VOLUME 1 – TAB B - FACTOR 2: KEY PERSONNEL

7.0 VOLUME 1 – TAB C – FACTOR 3: PAST PERFORMANCE

8.0 VOLUME 2 – TAB A – FACTOR 4: STANDARD FORM 33, PROPOSAL DATA SHEET, AND

CONTRACT LINE ITEM SCHEDULE

9.0 VOLUME 2 -- TAB B – REQUIRED PRE-AWARD INFORMATION

10.0 EVALUATION PROCEDURES

ATTACHMENTS

1 - PROPOSAL DATA SHEET

2 - COMPANY SPECIALIZED EXPERIENCE

3 - KEY PERSONNEL RESUME FORMAT

4 - PAST PERFORMANCE QUESTIONNAIRE

1.0 OVERVIEW

1.1. Interested firms (here after referred to as Offerors) shall submit proposals demonstrating their capability to successfully execute the construction services contract resulting from this solicitation.

1.2 This is a Trade-Off source selection for the Characterization, Transportation, and Disposal of Soil Small Arms Complex OB/OD River Site, Fort Wainwright, Alaska. The Government will evaluate proposals in accordance with the criteria described herein, and award a firm fixed price IDIQ contract to the responsible offeror, whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government utilizing procedures in accordance FAR PART 15.101-1 – Tradeoff Process.

2.0 BASIS FOR AWARD

2.1 The Contracting Officer will award a firm fixed price contract to the responsible Offeror whose proposal the Source Selection Authority has determined conforms to the solicitation, is fair and reasonable, and offers the “best value” to the Government. Exchanges may occur (see FAR

PART 15.306.

2.2 After listing proposal strengths, weaknesses and deficiencies, the Government will assign an adjective rating of Outstanding, Good, Acceptable, Marginal, or Unacceptable to technical factors one and two which reflects the Government's confidence in each offeror's ability, as demonstrated in its proposal, to perform the requirements stated in the RFP. The adjectival ratings shall be assigned, using the following criteria, which incorporate a proposal risk assessment:

Outstanding: Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.

Good: Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.

Acceptable: Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Marginal: Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

Unacceptable: Proposal does not meet requirements and contains one or more deficiencies. Proposal is un-awardable.

2.3 There are three aspects to the past performance evaluation: recency, relevancy (including context of data), and quality (including general trends in contractor performance and source of information

2.3.1 Recency. The first is to evaluate the recency of the offeror’s past performance. Recency is generally expressed as a time period during which past performance references are considered relevant,…