Solicitation Amendment 03

View the file

Other files for this federal contract opportunity

Other files attached to JBE030 Truck Offload Facility, newest first.
File Type Posted
SF_30.pdf PDF
AM_01.pdf PDF
A.07.23_Final_Solicitation_to_issue.pdf PDF
DWGS-JBE030-RTA-Halfsize.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION: JBE030, Construct Truck Off-Load Facility

a. This amendment provides changes to the solicitation as indicated on the continuation pages of this document.

b. PROPOSAL DUE DATE IS CHANGED FROM 17 March 2017 TO 21 March 2017 at 2:00 PM ADT. Proposals shall be submitted in accordance w ith Section 00 21 00, paragraph 1.10, Proposal Submittals.

c. YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Mar-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB-17-R-0029

X 9B. DATED (SEE ITEM 11)

30-Jan-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Mar-2017

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. The following drawings are substituted for the superseded documents/sections:

E-101, E-604, E-001, E-102

b. The following revised documents/sections are substituted for the superseded documents/sections. The identifier “AM 03” appears before and after new and/or revised materials, except as noted below.

SECTION 00 11 01 – CLIN SCHEDULE

NOTE: Revisions within the following documents do not contain the above referenced identifiers:

SECTION 00 11 00 - STANDARD FORM (SF) 1442, BLOCK 13

- PROPOSAL DUE DATE IS CHANGED TO: 21 March 2017 at 1400 hours ALASKA TIME.

Proposals shall be submitted in accordance with Section 00 21 00, paragraph 1.10, Proposal Submittals.

c. The following sections are deleted:

NONE

d. The following documents are added:

e. The following revisions are incorporated:

f. Other:

(End of Summary of Changes)

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.

W911KB-17-R-0029

PROPOSAL SCHEDULE

CONSTRUCT TRUCK OFF-LOAD FACILITY

JBER-ELMENDORF, ALASKA

BASE ITEMS

Item No.

Description Estimated Quantity

Unit Unit Price Amount

0001 Construct Truck off-load facility fuel systems, eyewash station, Complete

1 Job $_________ $_________

0002 Construct site work and utilities, Complete 1 Job $_________ $_________

0003 Procurement of ATG System (SRM Funded)

1 Each $_________ $_________

Total of Base Items 0001 thru 0003 $_________

OPTION ITEMS

Item No.

Description Estimated Quantity

Unit Unit Price Amount

0004 Construct Canopy (Identified in Project Drawings as Bid Option 1), Complete

1 Job $_________ $_________

0005 Remove, Sample stockpile 10 Cubic Yards of POL Contaminated Soil including Construction of Holding Cells, Complete*

10 Each $_________ $_________

AM

03…

Construct light poles in the truck offload area, Complete

6 Each $_________

…AM03

Total of Option Items 0004 thru AM 03… 0006 … AM 03 $_________

Total of Base and Optional Items 0001 thru AM 03… 0006

…AM 03

W911KB-17-R-0029

* Work on CLIN 0005 shall be the cost for work identified in Section 02 61 13 “Excavation and Handling of Contaminated Material” and Section 01 57 20.01 29 “Environmental Protection” that is additional to the requirements of the normal project excavation and the field screening identified on sheet G-002. For CLIN 0005, the Contractor shall keep a record of the amount of contaminated soil being excavated. Upon completion, if the amount of contaminated soil excavated is less than 6 cubic yards the Government will not receive a credit based upon the unit price noted in CLIN 0005. If the amount of contaminated soil excavated and stockpiled of is more than 15 cubic yards the Government will pay for the additional cubic yards at the same unit price noted in CLIN 0005. SEE FAR CLAUSE 52.211-18, VARIATION IN ESTIMATED

QUANTITY.

EVALUATION OF OFFERS.

1. AWARD: Award will be made in accordance with Section 00 22 11 - EVALUATION

FACTORS FOR AWARD.

2. INCOMPLETE OFFERS: Failure to submit an offer on all items in the schedule constitutes an incomplete offer. Incomplete offers may be rejected. Lump sum or unit prices must be shown for each item within the schedule.

3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

4. SPECIAL CONDITION: If a modification to an offer based on unit prices is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.

AM 03…5. Either Optional Line Item 0004 OR Optional Line Item 0006 will be exercised at the time of award. …AM03

-- END OF PROPOSAL SCHEDULE --