RFI Q and A update .docx
DOCX document 15 KB Posted
- Attached to
- Under Belly Interim-Solution (UBIS) Request For Information (RFI) Federal contract opportunity
- Solicitation number
- W56HZV-21-R-0093
About this file
This document contains a Request for Information (RFI) from the U.S. Army regarding the Under Belly Interim Solution (UBIS) for the Bradley Fighting Vehicle system. The RFI provides details on the required 2,000 ton plate forming press, including material size of 140 inches long and 1.2 inches thick of MIL-DTL-12560 class 4A. Responses to the RFI are due by March 8, 2021 and should be submitted to Matthew Kainz via email. The RFI also seeks information on offerors' ability to provide manufacturers' specification sheets and purchasing/rental agreements for the press. This will result in a firm-fixed-price contract awarded by the Department of the Army Materiel Command TACOM Life Cycle Management Command for 300 UBIS kits with an option for 300 additional kits to be exercised incrementally.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| UBIS Section L and M .doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Q & A
What specific type of 2,000 ton press is the USG requesting for this program? (i.e. brake press, stamping press, compression molding press, etc.).
-Plate forming Press
What is the specific need for this 2,000 ton press in the production process of the UBIS kits?(i.e. approximate size of component requiring this type of press).
- Material size: 140" long, 1.2" thick -Material type: MIL-DTL-12560, class 4A -Press tonnage of 2000 tons minimum
Reference L.4.1 Volume I: Past Performance Factor. Is the Government willing to accept OTA topic awards as past performance?
-Yes, if there is a SOW tied to an agreement that says they are tasked with performing that work for a customer, the USG would consider it.
Will this be a FFP or CPFF contract?
-This will be a FFP contract
Will there be established quantities for quoting or a ceiling to quote to with established price break quantities? We recommend established quantities in order to deliver the best value to the government customer and reduce the risk built into the cost of ambiguous quantities.
-Yes, 300 kit base quantity with an option for 300 additional kits. However, the option may be exercised incrementally.
Will delivery occur within CONUS or will the contractor be required to deliver to OCONUS locations?
-CONUS
Is the GOV willing and able to register this contract with the Department of State to reduce import/export fees?
-The Contracting Officer will consider the request, and if the agency determines to register the contract that will be stated in the solicitation.
What quality requirements should we anticipate?
-See section 2.4 of the solicitation.