Statement of Work Part 1.pdf

PDF 2 MB Posted

Attached to
Building Repairs Federal contract opportunity
Solicitation number
W50S8E21B0001
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Building Repairs, newest first.
File Type Posted
Statement of Work Part 2.pdf PDF
Sources Sought Information Form.pdf PDF
Sources_Sought_Info_Req_Form.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: Base Repair Projects

Project #: WKVB212116

22 JUNE 2021

NY Air National Guard

106th Rescue Wing

Francis S. Gabreski Airport (ANG)

150 Old Riverhead Road

Westhampton Beach, N.Y. 11978-1201

1.0 GENERAL SCOPE OF WORK: The Contractor shall provide all engineering, supervision, labor, parts, equipment, tools, and supplies required to repair specified base concrete, Bldg 370 roof, Bldg 250 and Bldg 254 siding and to install Bldg 424 80amp exterior panel. The contractor shall provide all personnel and quality control necessary to perform contents of contract to government satisfaction as defined in this statement of work (SOW).

1.1 PERIOD OF PERFORMANCE: The Period of Performance shall be 60 days from the

Notice to Proceed.

1.2 ACRONYMS AND DEFINITIONS:

1.2.1 Acronyms:

BCE Base Civil Engineer

CLIN Contract Line Item Number

CO Contracting Officer

COR Contracting Officer’s Representative

CQC Contractor Quality Control

FAR Federal Acquisition Regulation

FPCON Force Protection Condition

HM Hazardous Material

HMPT Hazardous Material Pharmacy Team

SDS Safety Data Sheet

ODS Ozone Depleting Substances

OPSEC Operations Security

OSHA Occupational Health and Safety Administration

QA Quality Assurance

QC Quality Control

SOW Statement of Work

106CES Title Project WKVB212116 Base Repair Projects

1.2.2 Definitions:

1.2.2.1 Base Civil Engineer – Final authority on the Installation for all issues related to Real Property management.

1.2.2.2 Competent Person – a person designated in writing, who, through training, knowledge, and experience is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

1.2.2.3 Contractor – A supplier or vendor awarded a contract to provide a specific product or service to the Government. The term used in this contract refers to the Prime contractor.

1.2.2.4 Contracting Officer – Individual with authority to negotiate and sign contracts on behalf of the Government.

1.2.2.5 Contracting Officer’s Representative – Individual delegated authority to act on behalf of the Contracting Officer with regard to specific contracts and contracting authority.

1.2.2.6 Defective Work – Any work performed by the Contractor that does not meet the Government’s satisfaction in accordance with the project specifications.

1.2.2.7 Definable Feature of Work – A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment.

1.2.2.8 Deliverable – Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

1.2.2.9 Government – Refers to the United States Government and the United

States Air Force as represented by the 106th Rescue Wing and New

York Air National Guard.

1.2.2.10 Hazardous Material – Any substances that are a risk to health, safety, property or the environment. For this contract, hazardous materials include, but are not limited to, any substances that are a healthy or physical hazard, regulated in its disposal by the U.S. Environmental

Protection Agency, hazardous as defined by U.S. Department of

Transportation regulations, covered under the Emergency Planning and

Community Right-to-Know Act tracking requirement, covered under the

Occupational Safety and Health Administration hazard communication standard, or are classified as a Class I or II Ozone Depleting Substance.

1.2.2.11 Installation – The Government property under the control of the 106th

Rescue Wing and the New York Air National Guard.

1.2.2.12 Key Personnel – Any member of the Contractor team that needs to be specifically identified to the Government, including but not limited to, supervision and Contractor administrative staff, Competent Persons, Qualified Persons, subcontractor points of contact, etc.

1.2.2.13 Notice to Proceed – Written notification from the Contracting Officer to proceed with construction activities.

1.2.2.14 Operations Security – Actions that prevent sensitive information from falling into adversaries’ control.

1.2.2.15 Period of Performance – Contractual timeline required for the

Contractor to fulfill the requirements of the contract to the satisfaction of the Government.

1.2.2.16 Physical Security – Actions that prevent the loss or damage of

Government property.

1.2.2.17 Qualified Person – a person designated in writing, who by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

1.2.2.18 Quality Control – All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

1.2.2.19 Real Property – Lands, buildings, structures, utilities systems, improvements, and appurtenances thereto. Includes equipment attached to and made part of buildings and structures but not movable equipment.

1.2.2.20 Subcontractor – One that enters into a contract with the Prime contractor. The Government does not have privity of contract with the subcontractor.

1.2.2.21 Submittal – written and/or physical information provided by the Prime contractor for Government review and acceptance.

2 GENERAL REQUIREMENTS

2.0 Contractor Installation Access: The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security

Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy.

Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

2.0.1 Construction hours for the installation are from 0730 – 1700 hours (7:30 am –

5:00 pm), Monday through Friday. Any request for a deviation from these posted work hours needs to be submitted, in writing, to the CO at least two weeks before the requested schedule change. Any requests for changing the working hours is purely at the convenience of the Government and rejected requests do not exonerate the Contractor from the contract requirements.

2.0.2 Unscheduled gate closures by the Security Forces may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. The Contractor is responsible for requesting compensation for any lost time through the CO for approval. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations.

Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

2.0.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The

Government reserves the right to direct the removal of an employee from

Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

2.0.4 The Contractor is responsible for ensuring proper documentation is received for personnel passes in time to avoid any delay in project start of performance. Any additional time required for obtaining badges and passes as required for access to the installation will not necessarily be grounds for additional time granted to complete the project, if passes are delayed due to Contractor actions. All traffic will enter through the Main Gate. All personnel working on the installation must be on the contractor request access sheet in excel format and submitted to the

COR at least one week (7 days) prior to requested visit date. All must pass the

Security Forces screening process. The Government reserves the right to deny access to any person, with no consequence to the contract. All contractor personnel shall prominently display the visitor’s badge at all times while on the installation.

2.1 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days without explicit written approval from the CO:

New Year’s Day: January 1st

Martin Luther King, Jr.’s Birthday

President’s Day

Memorial Day

Independence Day: July 4th

Labor Day

Columbus Day

Veteran’s Day: November 11th

Thanksgiving Day

Christmas Day: December 25th

2.2 Physical Security: The contractor shall safeguard all Government property on and around the work site. At the close of each work period, ensure that Government and

Contractor property is secured. The Government is not responsible for lost or missing items resulting from Contractor failure to secure materials.

2.3 OPSEC Requirements: The contractor shall safeguard all Government information and prevent the unauthorized release of protected information. The Contractor will be responsible for failing to protect sensitive information obtained or released as a result of this contract.

2.4 Contractor Manpower Reporting: The Contractor Manpower Reporting requirement is mandated by the Department of the Air Force and requires the reporting of the dollar value of labor hours for the performance of and awarded service. The Contractor

Manpower Reporting website is https://www.ecmra.mil. The Contractor shall be responsible for submitting information necessary to meet this requirement through the listed website.

2.5 Project Supervision: The Contractor shall have at least one qualified Project

Superintendent capable of reading, writing, and conversing fluently in the English language, on the work site at all times during the performance of contract work. In addition, a QC and Safety representative must also be fluent in English and on the work site at all times during work. The CO can remove any supervisor at any time during the project if the Government determines him or her unfit for duty, at no expense to the

Government.

2.5.1 Project Superintendent Qualifications: The Contractor shall submit qualifications, in resume format, of the proposed Project Superintendent and any alternates for Government approval. The Project Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule control on the project. The superintendent is required to attend all project-related meetings as directed by the CO. If more than one superintendent is required for various phases, the Contractor must submit qualifications for each proposed superintendent. The individual(s) must be capable of interpreting schedules and construction drawings. The CO may request proof of qualifications at any time if the performance of a superintendent is in question.

2.5.2 Quality Control Systems Manager: The Contractor shall submit qualifications, in resume format, of the proposed QC System Manager and any alternates for

Government approval. The QC System Manager is primarily responsible for the

CQC program and ensuring finished products meet the contract specifications.

The QC System Manager is required to attend all project-related meetings as directed by the CO. The CO may request proof of qualifications at any time if the performance of a QC System Manager is in question.

2.5.3 Safety and Health Manager: The Contractor shall submit qualifications, in resume format, of the proposed Safety and Health Manager and any alternates for

Government approval. The Safety and Health Manager is primarily responsible for ensuring that the Contractor and all subcontractors are in compliance with all applicable safety and health regulations. The Safety and Health Manager is https://www.ecmra.mil/ required to attend all project-related meetings as directed by the CO. The CO may request proof of qualifications at any time if the performance of a Safety and

Health Manager is in question.

2.6 Quality Control: The Contractor shall establish and maintain an effective QC program that consists of plans, procedures, and organization necessary to identify, prevent, and ensure non-recurrence of defective work. The QC system covers all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence.

The Project Superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context, the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The Project Superintendent and QC staff must maintain a physical presence at the site at all times during progress of the work and are responsible for all construction and related activities at the site, except as otherwise acceptable to the

Contracting Officer.

2.6.1 There is no separate payment associated with providing and maintaining an effective QC program. All associated costs should be included in the overall pricing schedule.

2.6.2 Contractor Quality Control Plan: Submit no later than 3 business days prior to the Pre-Construction Meeting to the CO. Construction will be permitted to begin only after acceptance of the CQC Plan by the Government. Acceptance of the

CQC Plan is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the

Contractor to make changes in the CQC Plan and operations, including removal of personnel, as necessary, to obtain the quality specified. Any proposed changes to the CQC Plan made after acceptance must be approved by the CO. The

Contractor shall keep the CQC Plan onsite and be readily accessible by the

Government as requested.

The CQC Plan should cover all construction operations, both on and offsite, including work performed by subcontractors and include:

A description of the quality control organization, including a chart showing lines of authority and individuals responsible for ensuring quality on each section of work accomplished.

The name, qualifications, duties, responsibilities, and authorities of the CQC

System Manager and each person assigned a CQC function.

A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System

Manager, including authority to stop work which is not in compliance with the

Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the

Contracting Officer.

Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents.

Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test.

Procedures for tracking construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

A list of definable features of work. Although each section of the specifications can be considered as a design feature of work, there are frequently more than one definable feature of work under a particular section.

2.6.3 Quality Control Program Organization: The minimum requirements for a

CQC Plan area Safety and Health Manager and a CQC System Manager, but should be sufficient to ensure safety and quality compliance. One person may perform functions as both the Safety and Health Manager and CQC System

Manager with written approval from the CO. Unless written approval is granted by the Contracting Officer, the CQC System Manager and/or Safety and Health

Manager shall not be the same person as the Project Superintendent. There should be sufficient personnel designated as CQC staff to ensure at least one member is always onsite during work.

2.7 Testing Reports and Samples: If required within the technical specifications of this contract, perform specified testing to verify that control measures are adequate to provide a product that conforms to contract requirements. Upon request, furnish to the

Government duplicate samples of test specimens for possible testing by the Government.

All testing should be accomplished by an outside laboratory approved by the CO. If outside testing is required per contract, submit qualifications and certifications of the laboratory for CO approval. The Government reserves the right to check both onsite and offsite testing equipment for compliance with the contract specifications at no additional cost to the Government.

2.8 Project Schedule: The Contractor shall submit a Project Schedule, pursuant to FAR

Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required and the scheduling of construction is the responsibility of the Contractor. It is the

Contractor’s responsibility to incorporate work accomplished by subcontractors and delivery schedules from supplies into the master Project Schedule. Use the Critical Path

Method (CPM) of network calculation to generate all Project Schedules. Prepare each

Project Schedule using the Precedence Diagram Method (PDM). Construction will only be allowed to start after a Project Schedule has been approved. Submit, no later than 3 business days prior to the Pre-Construction Meeting to the CO.

2.8.1 Basis for Payment and Cost Loading: The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN. Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the CO. Failure to meet the requirements of this specification may result in the disapproval of schedule submittals and subsequent reject of payment requests until compliance is met.

2.8.2 Detailed Requirements: Develop the project schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Include any design, permitting, and procurement activities and lead times into the master project schedule for approval. The Government will reject any project schedule that does not have sufficient detail to allow for

Government review. Activity loading should follow logical sequencing of activities from start to finish.

2.8.3 Schedule Computer Software: The scheduling software used by the Contractor may be of any brand but must be capable of meeting all requirements of this specification. The software must be capable of either printing in Adobe Acrobat© format or exportable to Microsoft Project© format. The Government intends to use Microsoft Project© as its scheduling software.

2.8.4 Project Schedule Updates: For projects with a Period of Performance longer than 45 days, the Contractor will submit, at a minimum, updated Project

Schedules at every progress meeting with the Government. The updated schedule shall show completed activities and remaining activities and timelines. The CO can request an updated schedule from the Contractor at any time and the

Contractor has 3 business days to submit the current updated schedule as requested.

2.9 Submittals: The Contractor is required to provide written documentation on all submittals for Government review. The CO may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Submittals requiring

Government approval are to be schedule and made prior to the acquisition of the material or equipment covered thereby. The Contractor must maintain a submittal register showing items of equipment and materials for when submittals are required by the specifications. The CQC System Manager and/or Designer or Record shall approve all items prior to submittal and stamp/sign and date indicating approval.

2.9.1 Pre-Construction Submittals: Submittals which are required prior to start of construction. The exact submittals may vary depending on the size and complexity of the technical specifications. These include, but are not limited to:

Certificates of insurance

Surety bonds

List of proposed subcontractors

List of proposed products & product data

List of key personnel

Construction project schedule – AF3064

Submittal register

Quality Control plan

Health and safety plan

Environmental protection plan

Waste management plan

2.9.2 Certifications: If specialized work or materials are required per the technical specifications, the Contractor shall submit all necessary certifications or permits to the CO for approval.

2.9.3 Operations and Maintenance Data and Manuals: Submit Operation and

Maintenance (O&M) Data for the provided equipment, product, or system, defining the importance of system interactions, troubleshooting, and long-term preventive operation and maintenance. Compile, prepare, and aggregate O&M data to include clarifying and updating the original sequences of operation to as-built conditions. Organize and present information in sufficient detail to clearly explain O&M requirements at the system, equipment, component, and subassembly level. Include an index preceding each submittal. Documents must be fully legible and must be consistent with the manufacturer’s standard brochures, schematics, printed instructions, general operating procedures, and safety precautions.

2.9.4 As-builts: As-built drawings are developed and maintained by the Contractor and depict actual conditions, including deviations from the Contract Documents.

Maintain the as-builts throughout construction as “red-lined” hard copies on site.

At the end of construction and prior to acceptance, the Contractor shall provide final as-builts to the Government in both digital and hard copy formats. Digital as-builts should be submitted in the “.dwg”, “.xml”, and “.pdf” formats compatible with AutoCAD©, ArcGIS©, and Adobe©, respectively. Hard copy as-builts shall be a binder of all drawings submitted on 24”x36” sheets of white paper. The Contractor shall provide 2 copies of all hard copy as-builts to the

2.9.5 Warranty Plan: Develop a warranty management plan which contains information relevant to the clause Warranty of Construction and submit to the

Government as part of the Pre-Final Inspection. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. Warranty information made available during the construction phase must be submitted to the

Contracting Officer for approval prior to each monthly pay estimate. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of project acceptance and continue for the full product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contractor, CO, and the BCE. Include within the warranty management plan, but not limited to, the following:

Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the

Contractors, subcontractors, manufacturers or suppliers involved.

Furnish with each warranty, the name, address, and telephone number of each of the guarantor’s representatives nearest to the project location.

Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers, and for all commissioned systems such as fire protection and alarm systems, sprinkler systems, lightning protection systems, etc.

A list for each warranted equipment, item, feature of construction or system indicating:

(1) Name of item.

(2) Model and serial numbers.

(3) Location where installed.

(4) Name and phone numbers of manufacturers or suppliers.

(5) Names, addresses and telephone numbers of sources of spare parts.

(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

(7) Cross-reference to warranty certificates as applicable.

(8) Starting point and duration of warranty period.

(9) Summary of maintenance procedures required to continue the warranty in force.

(10) Cross-reference to specific pertinent Operation and Maintenance manuals.

(11) Organization, names and phone numbers of persons to call for warranty service.

(12) Typical response time and repair time expected for various warranted equipment.

The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.

Procedure and status of tagging of all equipment covered by extended warranties.

Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

2.9.6 Draft DD Form 1354, Transfer and Acceptance of Real Property: The

Government will provide a draft initial DD Form 1354 to the Contractor at the start of the project that has the appropriate Real Property Unique Identifies

(RPUIDs) and associated Category Codes that apply to this contract. The

Contractor will submit a draft complete DD Form 1354, to the Government for review and acceptance at the Red Zone Meeting that uses the appropriate division of the RPUIDs & Category Codes and represents the final constructed facility and associated costs. The Government shall return the draft DD Form 1354 to the

Contractor for any necessary corrections. The Contractor shall submit to the

Government a final, correct, and signed DD Form 1354 at final project acceptance.

2.10 Construction Meetings: The Contractor and Government shall hold Pre-Construction, Periodic Progress, and Red Zone meetings throughout the project.

2.10.1 Pre-Construction Meeting: Prior to issuance of a NTP, the Government will schedule a Pre-Construction Meeting (Pre-Con) to review project specifications and installation requirements with the Contractor. The Contractor must have the

Project Superintendent, CQC System Manager, and Safety and Health Manager, at a minimum, in attendance.

2.10.2 Periodic Progress Meetings: The Contractor is responsible for scheduling periodic schedule update meetings for the purpose of reviewing the schedule, quality, and overall progress. The Contractor shall coordinate with the CO and other Government personnel, as directed by the CO, to schedule periodic progress meetings at an interval agreed upon at the Pre-Con. At any time, either party may request a change to the progress meeting intervals for consideration. The

Contractor’s Project Superintendent or authorized representative must attend the progress meetings. The Contractor shall provide minutes from the meeting and submit to the CO within 2 business days for review.

2.10.3 Red Zone Meetings: The Contractor shall schedule an initial, and any necessary follow-up, Red Zone meetings when the project reaches 75% complete according to the most current project schedule. During the Red Zone meetings, the

Contractor and Government will discuss the closeout process and checklist, remaining milestones and deliverables, and align responsibility for actions necessary to ensure a smooth transfer and acceptance of real property. These Red

Zone meetings can be combined with progress meetings, if both parties agree, to increase efficiency and reduce additional meetings.

2.11 Standard Material & Workmanship: All materials and supplies shall be new and standard products regularly used for commercial construction of similar size, style and complexity. Workmanship shall be comparable to quality commercial construction, meet industry standards and comply with standards contained in this SOW. The CO and BCE representative shall review materials and inspect work for compliance with these standards. Defective work will be rejected at the discretion of the CO or COR.

2.12 Material & Equipment Storage: The Contractor shall stockpile and place materials and equipment only in areas specifically approved by the BCE. All materials stored on the installation are at the risk of the Contractor and not the responsibility of the Government.

It is the responsibility of the Contractor to secure all materials and equipment left on the work site.

2.13 Completion Inspections: The Contractor shall be responsible for conducting Punch-Out

Inspections, Pre-Final Inspections, and Final Acceptance Inspections.

2.13.1 Punch-Out Inspection: Conduct an inspection of the work near the end of the construction to identify any work that does not conform to the contract specifications or drawings. The CQC Systems Manager shall re-inspect the deficient work after corrections and ascertain that all deficiencies have been corrected. When the Punch-Out Inspection is complete and all noted deficiencies have been corrected, notify the CO that the facility is ready for the Government

Pre-Final Inspection.

2.13.2 Pre-Final Inspection: The Government will perform the Pre-Final Inspection to verify that the facility is complete and ready to be occupied. A Government Pre-

Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that the

Final Acceptance Inspection can be scheduled. Correct any items noted on the

Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work

2.13.3 Final Acceptance Inspection: The Contractor's QC personnel, plus the superintendent or other primary management person, and the COR is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from BCE organization and end-users. The final acceptance inspection will be formally scheduled by the CO based upon results of the Pre-Final Inspection. The Contractor will notify the CO at least 14 days prior to the Final Acceptance Inspection and include the

Contractor's assurance that all specific items previously identified to the

Contractor as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the Final

Acceptance Inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the CO to bill the

Contractor for the Government's additional inspection cost.

2.14 Safety: The Contractor personnel shall work in a safe manner in accordance with

Government and OSHA standards. Determination of what constitutes unsafe practices is at the discretion of Government personnel. Failure of the Contractor supervisors to ensure

Contractor personnel work safely and with the proper gear may require a stoppage of work and/or removal of the workers at no cost or delay charged to the Government. All

Contractor personnel shall have appropriate clothing and PPE worn at all times. At a minimum, this includes wearing work pants and shirts, work boots and yellow or orange bright reflective safety vests. Loose fitting clothing and open toed shoes are not allowed on the work site. Additionally, some tasks require additional protection: i.e., safety glasses, hearing protection, masks, etc. that shall be required for certain tasks. Safety harnesses shall be required for workers performing elevated work. Contractor shall provide a site safety plan for review.

2.14.1 Competent Persons: Unless otherwise directed in the specifications, it is the

Contractor’s responsibility to determine the need for Competent Persons based on the technical specifications and work required for this contract. The Contractor shall submit the qualifications, in resume format, for identified individuals and the specific tasks they are required for to the CO for approval.

2.14.2 Qualified Persons: Unless otherwise directed in the specifications, it is the

Contractor’s responsibility to determine the need for Qualified Persons based on the technical specifications and work required for this contract. The Contractor shall submit the qualifications, in resume format, for identified individuals and the specific tasks they are required for to the CO for approval.

2.15 Accident Prevention: The Contractor shall comply with the following safety requirements while performing work under this contract:

2.15.1 Use diligent care not to damage the facility or government assets in the project area while in performance of this contract. Damage caused by the Contractor will be repaired to pre-existing condition or better at no additional cost to the

2.15.2 The contractor shall maintain a clean and secured work area at all times. Free of trip hazards and debris generated by project actions and secured against accidental intrusions by non-project personnel.

2.15.3 The Contractor shall ensure that any open excavations are covered, secured, and clearly marked/identified at the end of each work day or when there are not

Contractor personnel onsite.

2.16 Traffic Control Devices: The Contractor shall be responsible for signaling, lighting and barricading the immediate work area as determined by the BCE.

2.17 Vehicles: All vehicles operated by the Contactor will obey all traffic signs and laws while operating on the installation.

2.18 Electrical extension cords: may be used on a temporary basis to provide power to tools and equipment. Do not overload extension cords. Any frayed or spliced extension cords are prohibited. Power supply will be the responsibility of the contractor.

2.19 Fire Prevention: The prevention of fire is imperative during construction projects. The

Contractor is responsible for enforcing fire safety in his work area. The Contractor shall have serviceable fire extinguishers readily available at all times if necessary.

Extinguishers shall be supplied by the Contractor. Any hot work will require a burn permit from the Fire Department.

2.19.1 Smoking is prohibited inside buildings and within 50 feet of flammable and combustible liquids. Contractor must designate authorized smoking areas and must provide flameproof canisters or receptacles to capture and safely dispose of discarded tobacco materials.

2.20 Work Clearance and Approval: Prior to starting work, the Contractor shall submit an

Air Force Form 103, “Base Civil Engineering Work Clearance Request”, to the BCE for approval. The AF Form 103 should include all of the information necessary to approve a permit for work on the installation. In addition to the required submittals for this contract, other examples of supporting documentation for an AF Form 103 include, but are not limited to:

2.20.1 Work Site Layout: The Contractor shall perform a physical survey of the actual site to verify locations of existing objects and buildings, as well as existing power cables, communication cables, water and sanitary sewer line conditions prior to the start of construction. The Contractor shall submit a list of items that will need to be moved to accommodate the construction. The Contractor shall identify the extent of the work site and proposed areas for material storage, administrative space, traffic routes, etc.

2.20.2 Utility Markout: Contractor shall thoroughly tone and markout all areas to be excavated greater than 4” to identify any possible obstructions to excavating throughout the project area. Most utilities on the installation are owned by the

Government and may not be marked out by the local utility companies. It is the

Contractor’s responsibility to appropriately identify any risk to utility lines and mitigate such risk appropriately. The Contractor is solely responsible for any damage caused to Government or Private utility lines during construction.

2.20.3 Connections to Water Distribution System: Contractor shall only connect to points approved by the BCE or CO using reduced pressure backflow prevention device. Certification that the reduced pressure backflow prevention device has a current inspection and is serviceable shall be provided to the BCE and/or CO.

The connection point shall be in a highly visible location and appropriately marked.

2.20.4 Barricades and Fencing: The Contractor shall furnish the materials, equipment, and labor to install and maintain temporary barricades to safeguard against non-project personnel accidental intrusions. The Contractor is required to provide all necessary barriers and temporary covering of exposed areas as well as furnish the materials, equipment, and labor to prevent accidental entry. The contractor is responsible to furnish and install silt fencing barricade systems around the work site and/or Base drainage structures as required.

2.20.5 Sanitary Facilities: The Contractor shall provide temporary, field-type sanitary facilities for personnel working the project and the facilities provided must be new or in “like-new” condition and free of graffiti. Units are required to be serviced on a weekly basis, at a minimum; and all units shall be equipped with hand wash stations. The Contractor is responsible for ensuring positive control over sanitary facilities and shall not allow them to become an eyesore or health concern for site nor installation personnel. The Contractor is responsible for any spill resulting from improper handling, use, or maintenance of sanitary facilities.

2.21 Inspection by Government Agents: The CO or BCE may inspect the job site and any work area at any time. Inspections by the Government do not in any way absolve the contractor from their obligation to provide materials and construction free from defects and in accordance with the required specifications and quality.

2.22 Permits: All required permitting (with both on- and off-base entities) is the responsibility of the Contractor. Any required permits from off-base entities must be vetted for concurrence through the BCE and/or CO prior to submittal.

2.23 Construction Debris: Disposal of all debris is the responsibility of the Contractor and the disposal shall be done in accordance with all applicable laws. Debris from the site shall be removed and transported in a manner that prevents spillage on streets and adjacent areas. The contractor shall submit waste/recycling manifests with descriptions of all rubbish/debris and recycled matter removed from the base, including weights and the final location of the rubbish/debris or recycled material. All dumpsters shall be fully covered and secured at the end of each work day while on Base. Extreme caution shall be taken to eliminate any source of Foreign Object Debris (FOD) when working on or near airfield pavements.

The Contractor shall be responsible for the covering of open bodied vehicles transporting any material likely to create air pollution or become debris while on base. All mud, dirt, debris, foreign objects, trash, or spills (including Sub-Contractors and suppliers) on a street or parking lot, used as access to the work site or staging area shall be cleaned off the same day. The Contractor is responsible for any damage caused by lack of positive control over debris.

2.24 Environmental Protection: The Contractor shall comply with all applicable federal and state laws regarding protection of the environment during construction.

2.24.1 Hazardous Materials Approval: In the event the Contractor brings any hazardous material (HM) on to the installation, the Contractor shall notify the CO and BCE and provide a list of each material and the quantity of material for all proposed HM on the Hazardous Material Identification Worksheet (HMIW) at monthly intervals. The Contractor HMIW will be provided to the Contractor at, or prior to, the Pre-Construction meeting if HM are required for the project. The

Contractor shall provide a safety data sheet (SDS) for each HM brought on the installation.

2.24.2 Hazardous Materials Use and Storage: The contractor shall establish HM storage and a daily distribution system when HM is to be used that must be approved by the CO and/or COR. All HM required to support the contract shall be reported to the Hazardous Material Pharmacy Team (HMPT) using the

Contractor HMIW, listing the order of quantities used. Additional HM needed by the Contractor shall be identified to the COR for approval by the HMPT. The contractor planning to use HM for the work shall register with the base HMPT prior to start of work in order to support the installation’s compliance with

Executive Order 12856, Federal Compliance with Right-to-Know Laws and

Pollution Prevention Requirements. The Contractor shall maintain Contractor

HMIW on the job site for inspection/verification. The COR will verify that the

HM identified to HMPT is the only HM in use on the jobsite. Prior to final contract closure, the Contractor will complete part 2 of the Contractor HMIW to be submitted to the HMPT for approval. The contractor shall accompany the

Government representatives on the project close-out inspection to ensure all used/unused HM is removed from the installation.

2.24.3 Hazardous Waste Control: The Contractor shall be responsible for maintaining the work site to prevent the spread of contamination, provide for the safety of all individuals in the vicinity of the work site areas, and prevent the release of any contaminants into the environment. Any tanks or drum containers used by the

Contractor on the installation to store HM, including petroleum products, shall be reviewed and approved by the CO and/or COR prior to use.

2.24.4 Accidental Spills: The Contractor shall immediately report to the CO and COR any issues or incidents which may indicate potential imminent risk to Government personnel or the environment. Following the notification, the Contractor shall be available to the CO for instructions regarding remediation of the release.

Contractor should be aware of “you spill, you dig” policies related to working on the installation and be prepared to respond to a release caused by the Contractor’s personnel. To report a release or spill, contact the CO, COR, and BCE as soon as possible. Report the following:

a. Your name, location, organization, and telephone number

b. Name and address of the party responsible for the incident

c. Date and time of the incident

d. Location of the incident

e. Source and cause of the release or spill

f. Types of material(s) released or spilled

g. Quantity of materials released or spilled

h. Danger or threat posed by the release or spill

i. Number and types of injuries (if any)

2.25 Codes and Standards: The Unified Facilities Criteria (UFC) found at the Whole

Building Design Guide website (https://www.wbdg.org) are the governing criteria for all construction on the installation. All work performed under this contract shall otherwise be in compliance with all highest standards, rules, codes, regulations, guidance and laws https://www.wbdg.org/ having any relevance to the project such as, but not limited to; NYANG, USAF, NYDEC the New York State (NYS) Fire Prevention and Building Code and USAF Health and

Safety standards as well as widely accepted industry standards, including but not limited to: American Institute of Architects, American Concrete Institute, American Institute of

Electrical Engineers, American Institute of Steel Construction, American National

Standards Institute, American Society of Heating, Refrigerating and Air-Conditioning

Engineers, American Society of Mechanical Engineers, American Society of Testing

Materials, National Bureau of Standards, National Electric Code, American Welding

Society, Brick Institute of America, Building Officials and Code Administrators, Federal

Aviation Administration, National Fire Protection Association, National Electric Code, Occupational Safety & Health Administration, Rubber Manufacturers Association, Underwriters Laboratories, the New York DOT standard specifications and the New

York Department of Environmental Conservation. The Contractor is responsible for identifying any conflicting requirements asap to the CO and COR for resolution.

3.0 TECHNICAL REQUIREMENTS

3.1 SCOPE OF WORK FOR BASE CONCRETE REPAIR:

The following is a list of the major tasks included for Base Concrete Repair:

Replace 7 concrete sidewalk flags on Moen Street o The contractor shall remove/fill RCA in each flag where needed and compact to a 90% minimum compaction rating. The contractor shall provide NYS DOT approved RCA if needed.

o The contractor shall form all flags in line with existing sidewalk, install expansion joints where new concrete flags will meet existing concrete and install reinforcement wire mesh. Each flag is approximately 4’X4’.

o The contractor shall install 4” of 4,000 PSI concrete in each flag. The concrete shall have a broom finish and have a smooth level transition to the existing sidewalk.

Building 424 walkway continuation (North Side) o The contractor shall lay out and excavate for an approximate 64’X

5’X4” walkway extension on the north side of Building 424 to extend to the airfield.

o The contractor shall provide NYS DOT approved RCA and fill excavated walkway at a minimum of 6” compacted. Compact to a

90% minimum compaction rating.

o The contractor shall install forms and reinforcement wire mesh.

o The contractor shall relief saw cut and install expansion joints where needed.

o The contractor shall install 4” of 4,000 PSI concrete. The concrete shall have a broom finish, be relief saw cut as needed and have a smooth level transition to the existing airfield and sidewalk.

Building 424 man gate walkway (South Side) o The contractor shall saw cut and remove existing concrete step at personnel gate o The contractor shall lay out and excavate for an approximate 15’X

5’X4” walkway extension on the south side of Building 424 to extend to the airfield.

o The contractor shall provide NYS DOT approved RCA and fill excavated walkway at a minimum of 6” compacted. Compact to a

90% minimum compaction rating.

o The contractor shall install forms and reinforcement wire mesh.

o The contractor shall relief saw cut and install expansion joints where needed.

o The contractor shall install 4” of 4,000 PSI concrete. The concrete shall have a broom finish, be relief saw cut as needed and have a smooth level transition to the existing airfield and sidewalk/ provide a step down if needed.

o The contractor shall notify Civil Engineering before completion and final acceptance.

-See the attached sheets at the end for site overview map for each.

3.2 SCOPE OF WORK FOR BLDG 370 ROOF REPAIR:

The following is a list of the major tasks included for Bldg 370 Roof Repair:

o The contractor shall coordinate with Civil Engineering for a site visit to inspect/confirm the exact work that needs to be done prior to work being started.

o The contractor shall clean and prepare all specified areas of both upper and the lower roof noted during the site visit to be repaired.

o The contractor shall prime all areas of the lower roof with single ply roof primer.

o The contract shall supply and install an approximate 20’x20’ patch on lower flat roof and strip perimeter of the patch with 6” of flashing sheet.

o The contractor is to supply and install approximately 100’ of flashing and approximately 20 linear feet of MBR Liquid flashing system with serum on bldg. 370s main hangar upper roof.

o The contractor shall ensure all materials used are to match or be equivalent to existing materials on all portions of Bldg. 370 o The contractor shall install all materials to manufacturer’s specifications.

3.3 SCOPE OF WORK FOR BLDG 250 AND BLDG 254 SIDING REPAIR:

The following is a list of the major tasks included in this SOW:

o The contractor shall coordinate with the Base Contracting Office/

Civil Engineering to inspect/confirm sites prior to work starting.

o The contractor shall supply and install scaffolding where need at bldg. 254 and 250 to meet all OSHA safety standards and to have mesh wrapping.

Bldg. 254 o The contactor shall grind off all of the exterior wall and peeling paint on bldg. 254.

o The contractor shall soft wash all areas to be get getting stucco o The…