Question and Answers for B108 Generator.pdf

PDF 309 KB Posted

Attached to
Replace Bldg. 108 Generator Federal contract opportunity
Solicitation number
W50S8D23R0008
Issued by
Department of the Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Replace Bldg. 108 Generator, newest first.
File Type Posted
B108 Generator.pdf PDF
4.jpg JPG image
1.jpg JPG image
6.jpg JPG image
2.jpg JPG image
9.jpg JPG image
7.jpg JPG image
10.jpg JPG image
3.jpg JPG image
8.jpg JPG image
5.jpg JPG image
Solicitation.pdf PDF
A-1 - Performance Work Statement.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Voltage Requirement: Could you please specify the voltage that the generator will require? Voltage 277/480 – KW Rating 150

2. Power Output: We would like to know the kilowatt (kW) rating of the generator.

Voltage 277/480 – KW Rating 150

3. Fuel Type: Are you specifically interested in a natural gas or diesel generator? Diesel

4. Enclosure Preference: Do you require an "Open skid" generator, i.e., without an enclosure? Open Skid

5. Could you kindly advise us of the Voltage (KW) rating of the existing generator? We encountered difficulty in discerning this information from the provided picture of the serial plate due to its lack of clarity. Voltage 277/480 – KW Rating 150

6. Are we permitted to offer an Equal brand generator as an alternative, or is it necessary for us to provide a generator of the same make and model? YES, as long as it is capable of handling the existing load

7. We will need the voltage and KW rating in order to bid this project. Voltage 277/480 – KW Rating 150

8. Can the existing conduits and wiring get reused for the new generator and transfer switch?

You may use the conduits, but the wiring should be replaced.

9. How long of a power interruption will be allowed to replace the transfer switch? One duty day 0700-1600

10. Has that fuel tank ever been tested or polished to know the condition of the inside, and would you be interested in an option for a base tank under the generator? We are not interested in this option.

11. Are any of the fire pumps electric? If so, can we have a picture of the electric motor tag to check with the sizing software if a present day 150kw will be able to handle the starting inrush load. Yes, Photo attached

12.

File details come from the government source that posted it. Updated .