Amended Q AND A - W50S6S20R0004.docx
DOCX document 19 KB Posted
- Attached to
- Airfield Sunshade Fabric Replacement Federal contract opportunity
- Solicitation number
- W50S6S20R0004
About this file
This document contains questions and answers regarding a solicitation for airfield sunshade fabric replacement. The solicitation seeks replacement of fabric for shelters that are approximately 20 years old and were last replaced in 2010. Offerors are responsible for removing existing fasteners and installing new fabric. A site visit is available and questions are due by specified dates in June 2020. Proposals must include a FOD plan and will be evaluated for appropriate material considering the purpose and climate. The requirement is set aside for small businesses and is issued by the Department of the Army Arizona Army National Guard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 W50S6S20R0004 - Amendment 0003.docx | DOCX document | |
| Reference Photos.pptx | PPTX presentation | |
| SF30 - W50S6S20R0004 - Amendment 0002.docx | DOCX document | |
| (Amended) Attachment 1 - Statement of Need .docx | DOCX document | |
| Q AND A - W50S6S20R0004.docx | DOCX document | |
| SF30 - Amendment 0001 - W50S6S20R0004.docx | DOCX document | |
| SF1449 - W50S6S20R0004.docx | DOCX document | |
| Attachment 1 - Statement of Need.docx | DOCX document | |
| Attachment 3- Past Performance Questionnaire blank.pdf | ||
| Attachment 2 - Reference_List Blank.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S6S20R0004 – Airfield Sunshade Fabric Replacement Amended Q&A 1.
Q. Are the original building/construction drawings available?
A. Original drawings are marked confidential and not available for distribution.
2.
Q. How many linear feet of structure will be accessible at one time?
A. A precise measurement of linear feet is not available. However, 4 spots per row, 8 spots total are anticipated to be available at one time.
3.
Q. Is night work an option?
A. Yes, with proper coordination and contracting officer approval. If the contractor desires to work after 3:30 p.m., weekends, or during federal holidays, the contractor must submit the request to the Contracting Officer at least 2 business days in advance. Each request will be considered on a case-by-case basis.
4.
Q. Is weekend work an option?
A. Limited weekend work may be available with proper coordination and contracting officer approval. If the contractor desires to work after 3:30 p.m., weekends, or during federal holidays, the contractor must submit the request to the Contracting Officer at least 2 business days in advance. Each request will be considered on a case-by-case basis
5.
Q. Vendor X will not be able to attend the pre-bid site visit. Does this preclude us from bidding?
A. No. However, per page 3 of the RFP ‘Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.’
6.
Q. Are there any pictures and/or drawings that show how the fabric is attached to the structure? Requested drawings/pictures would include underside of the canopy and topside, valley line, peak line, front or back.
A. Drawings are unavailable as indicated in response to question 1. Limited photos have been posted with Amendment 0003.
7.
Q. Sections 2 & 4 reference "manufacturer's instructions". Neither the manufacture name nor the manufacturer's instructions are included in SON. Are they available?
A. No, by providing specific instructions, competition would be limited to one specific product manufacturer. As such, instructions may vary depending on which manufacturer the vendor obtains the fabric from. Thus the offeror will be responsible to obtain/determine necessary installation techniques.
8.
Q. Does the material need to be Berry Act compliant / Does the Government require the fabric to be manufactured in the United States?
A. Yes, also see DFARS Clause 252.225-7012 Preference for Certain Domestic Commodities.
9.
Q. Does any type of sealed engineering need to be submitted with the bid?
A. No, sealed engineering is not required as there are to be no structural changes.
10.
Q. What is the age of the shelters/current membrane fabric?
A. Shelters are approximately 20 years old. Fabric was last replaced in 2010.
11.
Q. Does the Government want the same material? / A. While the current fabric has provided UV reduction properties, material with more rain resistance may be beneficial to the end user. Offerors should consider the purpose and climate within which to be installed, and propose a product they believe is appropriate at the best value.
12.
Q. Did the Government remove all of the self-drilling fasteners that held the fabric in place?
If not is it the Contractor's responsibility to remove all of the existing fasteners before installing the new fabric?
A. Unknown, contractor would be responsible to verify. It is the Contractor's responsibility to remove all of the existing fasteners before installing the new fabric
13.
Q. Can you define the minimum order the Government will purchase so we can provide the very best unit rates?
A. CLINS 0001, 0002, 0003 are anticipated in the base award.
14.
Q. What is the anticipated timing for rescreening the flight line canopies?
A. Please refer to paragraph 8 of the Statement of Need.
15-17 Added via Amendment 0003, due to inadvertent oversight:
15.
Q. Will it be required for the contractor to submit a FOD plan? If so what would this plan entail and if you could provide an example?
A. Yes, a FOD plan is required; no sample is available. Details can be requested through the MXG POC post contract award.
16.
Q. Are there any permits required by the contractor?
A. None are anticipated for the scope of work. If any are in question, please factor in to proposal and it can be verified prior to contract award.
17.
Q. Is there a number of [fabric] options/types the customer would like to see in particular?
A. Offerors should consider the purpose and climate within which to be installed, and propose product(s) they believe appropriate at the best value.
W50S6S20R0004 Q&A
File details come from the government source that posted it. Updated .