RESPONSE TO QUESTIONS BATCH 2.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| INTERESTED__VENDORS_LIST_18-R-1027.pdf | ||
| RESPONSE_QUESTIONS_FOR_18-R-1027_BATCH_3.pdf | ||
| FRANKLIN_LIGHTS_PICTURE.pdf | ||
| RESPONSE_QUESTIONS_FOR_18-R-1027_BATCH_1.pdf | ||
| W15QKN-18-R-1027-0001.pdf | ||
| FRANKLIN_LIGHTING_LIST_4_10_18.pdf | ||
| PA035_FRANKLIN_SITEMAP.PDF | ||
| W15QKN-18-R-1027_OFFIICAL_SOLICITATION.PDF | ||
| DRAFT_PA035-Franklin-A2-CSS_4501-SOW-Lighting_Upgrade.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS BATCH 2 W15QKN-18-R-1027
1. QUESTION: My question is on the lighting quantities – training center PDF file, it says quantity of existing lights. Is that the quantity of fixtures or is that lamps? Are all interior lamps for the rooms T8 4ft lamps? Is there any Can lighting?
RESPONSE: The quantity is listed as fixtures. All existing lamps are T8 4ft light bulbs. There are no can fixtures.
2. QUESTION: What is the mounting height of the parking lot pole heads? Metal halide lamps? 400W or
1000W? The wall packs on the sides of the buildings- how high? 400W Metal Halide?
RESPONSE: The existing exterior lights are metal halide and sodium vapor and mercury vapor combination. Building mounted lights are 8-10 feet high. The wattage varies from 250W to 400W for exterior lights. The pole lights are 40-50 feet high.
3. QUESTION: What types of fixtures are currently in place?
RESPONSE: The current fixtures are T8 32 watt fluorescent fixtures.
4. QUESTION: What are the ceiling heights in the facility? Can pictures be provided of these same areas?
USARC BUILDING_Assembly area USARC BUILDING_office areas OMS Building Unheated Storage
RESPONSE: Assembly area is 30 feet high. Office areas are 8 feet high. OMS building is 30 feet high.
Unheated storage building is 20 feet high outside the caging, and 8 feet high inside the caging. Please see attached pictures.
5. QUESTION: PWS PARAGRAPH: 11.3. Background Information:
Contractor/ Sub-contractor, directly performing services/install on this contract shall supply all lead individuals’ qualifications that will be performing work on site (Project Managers, Installers, and Technicians) at the time of proposal.
Contractor/ Sub-contractor shall be required to provide a minimum of 2 lead personnel currently holding valid DOD CAC credentials who will be directly performing the tasks under this contract. Card holders shall have a minimum of Level I OPSEC Training Certification as well as Level I Anti-Terrorism Awareness Training. All certifications and credentials must be and remain valid from the date of proposal through contract duration.
Are CAC Credentials a requirement to submit a bid for this project? If so, is there a way to get CAC credentials prior to the bid deadline? I.e. would the CO be able to sponsor potential bidders? It seems unlikely that any non-incumbent would be able to obtain CAC credentials in time for the bid deadline otherwise.
RESPONSE: CAC credentials are not required to submit a bid.