Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req No. 5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code) 9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print) 16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0001 2018DEC11
W15QKN
ARMY CONTRACTING COMMAND - NJ
PICATINNY ARSENAL, NJ 07806-5000
NICHOLAS HANKO
EMAIL: NICHOLAS.A.HANKO.CIV@MAIL.MIL
W15QKN-18-R-0065
2018OCT19
X
X 2019JAN07 03:00pm
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 18
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: NICHOLAS HANKO
Buyer Office Symbol/Telephone Number: ACC-NJ-SW/(973)724-3558
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
Mounted Machine-Gun Optic (MMO) Amendment 0001 to Request for Proposal (RFP) for Solicitation Number W15QKN-18-R-0065
Description:
Solicitation Number W15QKN-18-R-0065 was issued as a Request for Proposal (RFP) for the procurement of the Mounted Machine-gun Optic
(MMO) on October 19, 2018.
Amendment 0001 to the Mounted Machine-gun Optic (MMO) Request for Proposal (RFP) addresses the following items:
(1) Due to a delay in sending out the classified lens addendum, the time for proposal submission has been extended to 3:00 PM, Monday ________________________________________________
January 07, 2019 Eastern Standard Time._______________________________________
(2) Section C.5.2.3. shall be amended to: Contractor personnel shall have the appropriate level of investigation and/or security clearance for each site of performance of work. The Contractor shall observe and comply with all security provisions in effect at each selected site. All Contractor personnel that require access to classified information and/or material will be required to have a Secret clearance under this contract and must maintain the level of security clearance for the life of this contract. The Contractor will notify the COR the same day as an employee receives notice that they will be released, have been fired, or have had their security clearance revoked or suspended.
(3) Section L.3.1.C. shall be amended to: Volumes I, III, IV, V and VI of the Proposal has no page limit. (Please note: Volume II
(Technical) shall continue to have a maximum of 30 single sided page limit).
Please send all requests (see - sentence below) to Mr. Nicholas Hanko (email: nicholas.a.hanko.civ@mail.mil) and Dan Potempa (email:
daniel.l.potempa2.civ@mail.mil) or mail to same at the address listed below.
Please send all inquiries via email only. Contrary to FBO posting telephone numbers at the bottom of this announcement, NO TELEPHONE _____________
INQUIRIES WILL BE ACCEPTED.___________________________
Contracting Office Address:
ACC-New Jersey, Center for Contracting and Commerce, Building 9 Phipps Road, Picatinny Arsenal, NJ 07806-5000
Points of Contact: Nicholas Hanko, Daniel Potempa
*** END OF NARRATIVE A0004 ***
2 18
W15QKN-18-R-0065
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
STATEMENT OF WORK
Mounted Machine Gun Optic
M2/M2A1, M240 & Mk19 Weapon Platforms
(MMO)
C.1 SCOPE
C.1.1. Objective: The objective of this procurement is to obtain a Mounted Machine Gun Optic (MMO) which will provide a day view optic capability to mounted machine gunners on M2/M2A1, M240 and Mk19 weapon platforms. The device will allow for increased first burst probability of hit and decreased engagement times over the baseline configurations (iron sights and the M145 Machine Gun Optic (MGO)) while maintaining situational awareness.
C.1.2. This Statement of Work (SOW) is for the production of MMOs. The first delivery order is for the delivery of 35 MMOs per weapon platform in accordance with the Purchase Description (AR-PD-191) to be used in Government Lab and Live Fire Testing with a period of performance of 180 days from contract award. Under this effort, an MMO shall be produced that meets the requirements of the MMO Purchase
Description AR-PD-191.
C.1.3. Background
C.1.3.1. Description: The MMO is a weapon mounted day view optic with laser protection and a rubber or other non-slip coating. The MMO incorporates laser hardening In Accordance With (IAW) AR-PD-191. The MMO will enable a gunner firing from a vehicle mounted platform to acquire and effectively engage multiple targets out to 1,000 meters and 1,500 meters on the M2A1/M240 family and the Mk19, respectively, and to operate effectively throughout all operational environments.
C.1.3.2. Integral Components: Each MMO includes the following integral components per AR-PD-191:
a. Magnified optical assembly
b. Reflex or Unity Power (1X) Optic (Viewing Window) assembly
c. Housing (as required for design)
d. Battery compartment
e. A carrying strap
f. Eye lens cover(s)
g. Objective lens covers
h. Batteries
i. Lens Cleaning Material
j. Laser Filter Unit
C.2 APPLICABLE DOCUMENTS: The following documents are incorporated by reference. Where a document listed below refers to or incorporates one or more other documents that are not listed, the issues or version (including all changes and amendments) in effect on date of receipt of this SOW shall govern.
C.2.1. Military Specifications and Standards
-ISO 9001:2008 ISO Quality Management Systems
-MIL-PRF-49506 Logistics Management Information
-MIL-STD-882EDOD Standard Practice for System Safety
-MIL-HDBK-61A Configuration Management Guidance
-EIA-649-A National Consensus Standard for Configuraiton
C.2.2. Other Documents
-AR-PD-191 MMO Purchase Description
-Drawing 13010593:19200 Laser Filter Codes
-Security Classification Guide SCG for LFU Laser Protection Materiel
-AR-381-12 Threat Awareness and Reporting Program
(ARDEC drawings may be requested online at pica.Drawing.Request@conus.army.mil or from US Army ARDEC, ATTN: RDAR-EIS-PE, Picatinny, NJ
07806-5000.)
3 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
C.3 BASE CONTRACT STATEMENT OF WORK
C.3.1 Requirements: The Contractor shall manufacture and deliver 35 MMOs in accordance with AR-PD-191, but does not require adherence to the laser filter portion of the specification.
C.3.1.1 Deliverables
C.3.1.1.1 The Contractor shall deliver 35 MMOs IAW AR-PD-191, excluding the laser filter portion of the specification (3.6.9-3.6.11.3), 180 days After Contract Award (ACA) for Government Lab and Live Fire Testing, which shall be conducted by the Government.
C.3.1.1.2 Meetings and Reviews: The Contractor shall participate in the meetings listed below.
C.3.1.1.2.1 Start of Work Meeting: Within 15 days after award, a Start of Work Meeting shall be held via a teleconference, Virtual
Teleconference (VTC), or at the Contractor's facility.
C.3.1.1.2.2 IPT (Integrated Product Team) Teleconferences, as needed.
C.3.1.1.3 Data Deliverables
C.3.1.1.3.1 A Government Testing Safety Assessment Report (SAR) shall be submitted within 30 days after contract award (DI-SAFT-80102C, CDRL A002) which will evaluate the risks associated with testing a system at a government facility. This SAR will identify all safety features of the system, all related hazards associated with testing, and the mitigations (procedures, precautions, etc.) required to minimize risks and safety conduct testing. The SAR shall contain range safety data (i.e., Recommended Surface Danger Zone). The SAR shall contain results from the Contractor's safety assessments, hazard analyses, and testing. A Government Testing SAR shall be submitted for each unique configuration submitted to the Government.
C.3.2 Deliveries and Performance Period and Location
C.3.2.1 Notice Regarding Late Delivery: Late Deliveries will not be accepted for Base Contract (Govt. Lab and Live Fire Testing- QTY
35).
C.3.2.2 Period of Performance (PoP): The PoP for this effort shall be completed in 180 days.
C.3.2.3 Location of Performance: The location for the performance of the work will be at the Contractor's or the Subcontractor's facilities, to be decided after contract award.
C.4 FULL RATE PRODUCTION STATEMENT OF WORK, IF EXERCISED:
C.4.1 Requirements: The Contractor shall manufacture and deliver the respective weapon platform MMO in full accordance with AR-PD-191, to inlcude the laser filter portion of the specification, in an IDIQ contract with five - one year ordering periods in the quantities and on the respective dates listed in each delivery order. The Contractor shall warrant all material (e.g., MMO and parts) and workmanship (e.g., manufacture and repair) performed under this contract. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
C.4.1.1 Testing
C.4.1.1.1 FAT and Hardware: The Contractor shall perform a FAT on production representative hardware per AR-PD-191. The test shall utilize 12 MMOs. All successful First Article hardware shall be refurbished to "as new" condition and delivered to the Government with the test report, but shall not be considered a production unit under any other Line Item Number (LIN). The Contractor shall prepare and submit First Article Qualification Test Plan and Procedures and a FAT Report per Paragraph C.4.1.3.1 of this SOW.
C.4.1.1.2 LAT: The Contractor shall perform Conformance Inspection and Testing as specified in AR-PD-191. The Contractor shall submit an
Inspection and Test Plan (see Paragraph C.4.1.3.2) commensurate with standard Contractor format for Government review. Upon completion of the LAT, the Contractor shall submit a Final Inspection Record (see Paragraph C.4.1.3.3).
C.4.1.2 Configuration Management (CM) and Control. Upon contract award, the configuration of the MMO shall be identical to the submitted pre-production units. Any proposed changes must be submitted to the Government for review and Government authorization prior to implementation. Any changes not authorized shall be considered non-conforming, and shall not be accepted by the Government. All CM requirements shall apply and be passed on to all Subcontractors and vendors. All hardware, software, and firmware delivered under this contract are to be of single design. Such design is to be thoroughly documented and access to such documentation including copying thereof shall be granted to the Government.
C.4.1.2.1 The Contractor shall not make any design changes after the FAT is accepted without Government approval. Modifications from the baseline design shall be approved by the Government in advance and prior to implementation and thoroughly tested, documented, and tracked via Engineering Change Proposal (ECP), Request for Deviation (RFD) and Notice of Revision (NOR) (see Paragraph C.4.1.3.4). The
4 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Contractor shall maintain a separate and unique numbering system for this contract. ECPs, RFDs and NORs, regardless of origin (prime
Contractor or Subcontractor), shall be numbered sequentially and consistently. Test sample quantities for configuration change purposes shall be statistically relevant. Government approval of configuration change documentation shall not alleviate Contractor's obligation to meet AR-PD-191 and SOW requirements.
C.4.1.2.2 The Contractor shall track, record and report upon configuration changes to each fielded unit, the current approved configuration, and the configuration of each produced item by serial number (see Paragraph C.4.1.3.5).
C.4.1.2.3 The Contractor shall develop, submit to the Procuring Contracting Officer (PCO) for Government approval, and maintain, a configuration management plan (see Paragraph C.4.1.3.5).
C.4.1.3 Data Deliverables
C.4.1.1.3.1 Technical Data Package: Thirty days after contract award, the Contractor shall deliver digital Contractor format drawings and associated parts lists in accordance with MIL-DTL-31000C and Commercial Drawings and Associated Lists DI-SESS-81003 (CDRL A003) for configuration management oversight to include analysis of how component subsystems and components are integrated into the complete system, for Army provisioning and cataloging, for configuration audit, and for the development of maintenance activities. These drawings shall include interface drawings documenting all interface areas of the design, (e.g. all interfaces, an MMO top drawing specifying all components of the system including: all assemblies and individual piece parts, electronics units, wiring connector(s), maintenance drawings, major assembly drawings, complete parts lists, and all other equipment drawings). The Contractor shall arrange the drawings in a "drawing tree" to ensure that all the necessary drawings have been provided. The Contractor shall make available to the Government Inspector all drawings to which the product was manufactured for product inspection and acceptance.
C.4.1.1.3.2 The Contractor shall provide for a Physical Configuration Audit (PCA) for the MMO. The PCA will establish a product uniformity baseline for key characteristics of the product design. The Contractor shall determine the key characteristics of the design that are essential in order to meet performance requirements. The PCA will compare the Contractors design to the Technical Data provided by the Contractor. The PCA shall be witnessed by a Government Official and the report (DI-CMAN-81022, CDRL A004) shall be delivered no later than 45 days after the FAT report has been approved by the Government.
C.4.1.3.1 The Contractor shall submit First Article Qualification Test Plan and Procedures (DI-NDTI-81307, CDRL A005) for Government review and acceptance, which shall address all information necessary for accomplishing the FAT as required per AR-PD-191. The FAT Report
(DI-NDTI-81307, CDRL A006), which shall be submitted no later than 90 days ACA for Government review and approval, shall encompass the results of the FAT, and shall be in a similar format as the FAT Plan. The Government will review and approve or disapprove the FAT
Report within 45 days of submittal.
C.4.1.3.2 The Contractor shall submit an Inspection and Test Plan (DI-QCIC-81110, CDRL A007) in the format of the Contractor's choice, which will document the details of the Contractor's inspection system, test procedures and inspection procedures, which shall be in compliance with conformance inspection and lot acceptance testing portions of the contract.
C.4.1.3.3 The Contractor shall submit a Final Inspection Record (FIR) (DI-QCIC-81068, CDRL A008) in the Contractor's format. It should be organized to as to be compatible with assemblies, installation, and end item performance and acceptance. The FIR shall contain all examinations and tests that are performed on a single unit during its manufacture and final inspection. The FIR shall list each MMO characteristic or function to be inspected from Purchase Description. As a minimum, the FIR shall have blocks for the Contractor's inspector's initials indicating that each characteristic or function was inspected and either accepted or rejected, and another block for re-inspection and acceptance of any rejected characteristic or function. Final review and acceptability shall be indicated by a signature block containing the full name and title of the company official rendering approval. The FIR shall be updated to reflect all engineering and/or manufacturing changes that impact the FIR, during the entire contract period. The Contractor shall submit the completed and certified copy of the FIR to the Government Inspector with each item inspected and offered for acceptance by the
Government.
C.4.1.3.4 Configuration Change Data Deliverables: Configuration change documentation shall include the complete original drawings for the affected parts (highlighted to show items/areas to be changed), the complete proposed change drawings, and the next higher assembly drawings. Configuration change documentation shall include the results of both design verification testing and production representative testing to adequately demonstrate that the proposed changes meet all requirements. The Contractor shall maintain a record of all changes to the original design. The Contractor shall provide, at a minimum, a record of any changes, narrative reasons for each change, and any relevant data. Configuration changes shall be approved by the Government in advance and prior to implementation and tracked by ECPs (DI-CMAN-80639, CDRL A009), RFDs (DI-CMAN-80640, CDRLA009), and NORs (DI-CMAN-80642, CDRL A009).
C.4.1.3.5 The Contractor shall develop, submit to the PCO for Government approval, and provide upon Government request, a Configuration
Management (CM) Plan (DI-CMAN-80858, CDRL A010) in accordance with MIL-HDBK-61A and EIA-649-A. The CM Plan shall address all aspects of the contract effort, which shall ultimately lead to establishment, deviation, or modification of the system.
C.4.1.3.6 Provisioning Data (DI-ILSS-80134, CDRL A011).
C.4.1.3.6.1 A Statement of Prior Submission shall be furnished, in standard Contractor format to specifically identify any
5 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Provisioning/Logistics Support Analysis (LSA) data previously provided to a Government (U.S. or NATO). The Contractor shall provide a catalog of parts identifying all of the following: Nomenclature, Contractor and Government Entity Code (CAGE) of manufacturer, unit price, part number, whether totally interchangeable, National Stock Number (NSN), if any, and identity of next higher assembly.
C.4.1.3.6.2 The Contractor shall prepare a listing of spare and repair parts prices using MIL-PRF-49506 as guidance. The listing shall be furnished in standard Excel format.
C.4.1.3.7 Safety Data
C.4.1.3.7.1 The Contractor shall establish and execute a system safety program in accordance with MIL-STD-882E, Standard Practice for
System Safety. The Contractor shall develop, maintain and update as necessary a System Safety Program Plan (DI-SAFT-81626, CDRL A012) throughout the program and shall make this program plan available for Government review. The System Safety Program Plan shall define the planned safety activities for the system.
C.4.1.3.7.2 The Contractor shall report immediately (DI-SAFT-81563, CDRL A013) any major accident/incident (including fire) resulting in any one or more of the following: causing one or more fatalities, or one or more disabling injuries; damage of Government property exceeding $10,000; affecting planning or production schedules; degrading the safety of equipment under contract, such that personal injury or property damage may be involved; identifying a potential hazard requiring corrective action. The Contractor shall prepare a separate report for each incident.
C.4.1.3.7.3 A Comprehensive Safety Assessment Report (SAR) shall be provided within 45 days after contract award (DI-SAFT-80102, CDRL
A014). This SAR shall contain the safety methodology used to classify and rank hazards, the results of the analyses and tests performed to identify and assess hazards inherent to the system. It shall include a list of all hazards, specific safety recommendations or precautions, and hazardous materials information including identification, transportation and the disposal procedures. The conclusion of the SAR shall document any hazards that still exist with suggested mitigations and risk levels. The report shall contain sufficient
"safety case" evidence to support the conclusion and follow guidance specified in MIL-STD-822E.
C.4.1.4 Meetings and Reviews
C.4.1.4.1 Start of Work Meeting: Within 15 days after option award, a Start of Work Meeting shall be held via a teleconference, Virtual
Teleconference (VTC), or at the Contractor's facility.
C.4.1.4.2 Test Plan Review meeting: After completion of the FAT Procedures for Government Review and Acceptance and submittal to the
Government, (see Paragraphs C.4.1.1.1.1 and C.4.1.3.1), a test plan review meeting shall be held at the Contractors facility or via teleconference/VTC.
C.4.1.4.3 IPT Teleconferences, as needed.
C.4.2 Options (Production) Deliveries and Performance Period and Location:
C.4.2.1 Notice Regarding Late Delivery: The Contractor shall notify the Contracting Officer's Representative (COR), the Contract
Specialist, and PCO as soon as it becomes apparent to the Contractor that a scheduled delivery will be late. The Contractor shall include in the notification the rationale for late delivery. The new schedule and rationale will be reviewed by the COR and PCO.
Guidance and a determination of any equitable adjustment or consideration to the Government shall be provided to the Contractor.
C.4.2.2 PoP: The PoP of this effort shall be five years, if the full rate production option is exercised by the Government.
C.4.2.3 Location of Performance: The location for the performance of the work will be at the Contractor's or the Subcontractor's facilities, to be decided after contract award. The Contractor is not required to travel under this contract. However any travel that may occur shall be in accordance with the JTR.
C.5 GENERAL SOW
General Information applies to Base Award and, (if full rate production option is exercised), Production Quantities.
C.5.1 Notes/Guidance: Access to Government Data: To permit execution of assigned responsibilities, the Contractor shall be given full access to unclassified information and data pertaining to this effort upon signing of Non-Disclosure Agreement (NDA) and presentation of properly executed SF86 (Personnel Security Questionnaire) form. This will also include non-disclosure statements from other Contractors that do business with the US Government.
C.5.2 Security Requirements
C.5.2.1 The highest classification for this effort is SECRET. The Contractor will be required to obtain and maintain a Facility
Clearance with safeguarding from the Defense Security Service for the life of the contract. The Contractor will only receive classified material at the actual performance location(s) as identified in Block 8a of the DD254.
6 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
C.5.2.2 Information Disclosure: A Certificate of Non-Disclosure shall be signed by all contractor employees working under this effort and returned to the COR prior to award. The Contractor shall not release any information or data without the approval of the Government.
C.5.2.3 Personnel: Contractor personnel shall have the appropriate level of investigation and/or security clearance for each site of performance of work. The Contractor shall observe and comply with all security provisions in effect at each selected site. All
Contractor personnel that require access to classified information and/or material will be required to have a Secret clearance under this contract and must maintain the level of security clearance for the life of this contract. The Contractor will notify the COR the same day as an employee receives notice that they will be released, have been fired, or have had their security clearance revoked or suspended.
C.5.2.4 For Official Use Only Information (FOUO) and Controlled Unclassified Information (CUI): The Contractor shall be capable of accessing, handling, receiving, and storing UNCLASSIFIED documents, equipment, hardware, and test items, using the applicable standards of FOUO information. Defense Federal Acquisition Regulation Supplement (DFARS) 252.204-7012, "Safeguarding Covered Defense Information and Cyber Incident Reporting" applies to this effort. All Controlled Unclassified Information (documents designated as FOR OFFICIAL USE
ONLY and/or LIMITED DISTRIBUTION) shall be submitted and electronically transmitted by a controlled means via the United States Parcel
Service (USPS) mail, U.S. Army Aviation and Missile Research Development and Engineering Center Safe Access File Exchange (AMRDEC SAFE) website https: //safe.amrdec.army.mil/SAFE/ and/or an approved application that is Certified for Networthiness such as the Encryption
Wizard.
C.5.2.5 Receive Classified Material: In performance of the contract, the Contractor will be required to receive and store classified material and/or hardware up to the level of SECRET. The Contractor requires access to classified source material and or data up to and including the level of SECRET in support of this work effort, and is applicable to all performance locations under this agreement.
Receipt and storage of classified material shall be at the approved Contractor facility identified in Block 8a of the DD254. Classified computer systems will not be utilized in performance of this effort. (Note: No classified information will be transmitted electronically. All classified information/material will be hand carried or mailed registered through the USPS.)
C.5.2.6 Handling and destroying unclassified/limited distribution documents: Unclassified/limited distribution documents shall be handled using the same standard as "FOUO" material and will be destroyed by a method that will prevent disclosure of contents or reconstruction of the document. When local circumstances or experiences indicates that this destruction method is not sufficiently protective of unclassified limited information, local authorities may prescribe other methods, but must give due consideration to the additional expense balanced against the degree of sensitivity.
C.5.2.7 Export Control Laws/International Traffic in Arms Regulation: Information Subject to Export Control Laws/International Traffic in Arms Regulation (ITAR): Public Law 90-629, "Arms Export Control Act", as amended (22 U.S.C 2751 et. Seq.), requires that all unclassified technical data with military application may not be exported lawfully without an approval, authorization, or license under
EO 12470 or the Arms Export Control Act and that such data required an approval, authorization, or license for export under EO 12470 or
Arms Export Control Act. For purposes of making this determination, the Militarily Critical Technologies List (MCTL) shall be used as general guidance. All documents determined to contain export controlled technical data will be marked with the following notice:
WARNING: This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., App. 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD
Directive 5230.25).
C.5.2.8 Threat Awareness Reporting Program (For all contractors with security clearances): Per AR 381-12 Threat Awareness and Reporting
Program (TARP), Contractor employees must receive annual TARP training by a Counter Intelligence (CI) agent or other trainer as specified in 2-4b. This training shall be completed within 12 months after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, and then annually thereafter. The Contractor shall submit documentation of completion for each affected Contractor employee and Subcontractor employee to the COR (or to the PCO, if a COR is not assigned) within
14 calendar days after completion of training by all Contractor employees and Subcontractor personnel. Training can be executed by a local CI agent, online via the Army Learning Management System (ALMS) at https: //www.lms.army.mil (and search for TARP), or by contacting the 902nd military intelligence unit at usarmy.picatinny.902-migrp.list.308th-picatinny-fo@mail.mil.
C.5.2.9 Development of an OPSEC (Operation Security) Standing Operating Procedure (SOP)/Plan: The contractor shall develop an OPSEC
SOP/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC Officer, per AR 530-
1, Operations Security. This SOP/Plan will specify the project's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it. In addition, the contractor shall identify an individual who will be an
OPSEC Coordinator. The Contractor will ensure that this individual becomes OPSEC Level II certified per AR 530-1. ARDEC OPSEC POC e-mail: usarmy.pica.ardec.mbx.ardec-opsec@mail.mil.
C.5.2.10 OPSEC Training: Per AR 530-1 (or DoDM 5205.02-M), new Contractor employees, including Subcontractor employees, must complete initial OPSEC training within 30 calendar days of reporting for duty and must also complete annual OPSEC awareness training as provided by the appropriately designated OPSEC level II trained OPSEC Officer/Coordinator (DI-MGMT-80934). The COR or Agreements Officer
Representative (AOR) can request Armament Research, Development and Engineering Center (ARDEC) OPSEC training from ARDEC OPSEC Point of
Contact (POC) e-mail: usarmy.pica.ardec.mbx.ardec-opsec@mail.mil.
C.5.2.11 Public Release of Information: Per AR 530-1, Operations Security, an OPSEC review is required prior to all public releases.
7 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
All Government information intended for public release by a Contractor will undergo a government OPSEC review prior to release.
*** END OF NARRATIVE C0001 ***
8 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
L.1. PROPOSAL SUBMISSION
L.1.1 Introduction: This section contains general proposal submissions instructions, as well as specific proposal requirements for the
MMO with regards to submitting the written proposal.
L.1.2 General. The proposal shall be presented in sufficient detail to allow Government evaluation of response to the requirements of the RFP. The Government will not assume the Offeror possesses any capability, understanding, or commitment not specified in the proposal.
L.2 PROPOSAL INSTRUCTIONS
L.2.1 General:
L.2.1.1 Offerors shall provide information by addressing each Factor/Subfactor in the format and sequence identified in the solicitation. The Offerors must provide information in sufficient detail to allow the Government to make a best value assessment of the
Offeror's capability to support the proposed response to the evaluation criteria. Proposals that do not contain the information requested in the solicitation risk being determined Unacceptable by the Government. The Government will not assume the Offeror possesses any capability, understanding, or commitment not specified in the proposal.
L.2.1.2 The proposal must not merely repeat the solicitation requirements, but rather must provide convincing documentary evidence in support of conclusive statements of how contract requirements will be met.
L.2.1.3 The Government intends to award without discussions (see FAR 52.215-1). Proposals that do not contain the information requested in the solicitation risk being determined Unacceptable by the Government. The Government does not assume the duty to search for data to cure problems it finds in proposals. The burden of proving acceptability remains with the Offerors.
L.2.1.4 Alternate Proposals: Alternate proposals will not be accepted.
L.2.1.5 Proposals shall be valid through 180 days after receipt of proposal.
L.2.2. All questions concerning this procurement, either technical or contractual must be submitted in writing to the Contracting
Officer. No direct discussion between the technical representative and a prospective Offeror shall be conducted. Questions and proposals shall be submitted to the following point of contact:
Army Contracting Command New Jersey
ACC-NJ-SW, Bldg. 9, Mail Stop: 10B
ATTN: Nicholas Hanko, Telephone: (973)724-3558
Picatinny Arsenal, NJ 07806-5000
E-mail: nicholas.a.hanko.civ@mail.mil
Please note that electronic e-mail proposal submissions will not be accepted.
L.2.3 The MMO effort requires access to a secret specification for the laser filter. The classified laser filter information is restricted to U.S. Firms with foreign participation, if any, in accordance with Block 13 of attached form DD254. Offerors that do not meet the requirements cited in the attached DD254 cannot receive the secret laser filter information and will be returned without evaluation.
L.2.4 All portions of the Offeror's proposal shall be in unclassified terms. Failure to follow these instructions may result in a breach of security and appropriate Government action against the Offeror, and may result in immediate rejection of the proposal. The unclassified terms of unclassified Purchase Description and secret ARDEC Drawing 19200:13010593 LFU Codes: Lambda 1 through Lambda 9 and
OD1 through OD4 are provided for the Offeror's convenience to report and document in unclassified formats. There shall be no mention of specific wavelength bands, laser wavelengths, rejection levels, optical densities, specific tests lasers and/or laser makes and models.
Photopic and scotopic transmission curves shall not include any wavelength scale. Failure to follow these guidelines may result in a breach of security and appropriate Government action against the Offeror, and may result in immediate rejection of the proposal.
L.2.5 The proposal shall consist of the following:
L.2.5.1 Each proposal shall be submitted in the English language and consist of and include all of the following:
a. One signed and completed paper copy of the attached Standard Form 1449 (SF 1449) and continuation sheets signed by a person authorized to enter into the proposed contract on behalf of the Offeror. Acknowledgment of all amendments to the solicitation and all continuation sheets are to be filled in as directed, i.e., proposed prices in the Pricing Matrices, any fill-ins required, such as
Contract Data Requirements List: DD Form 1423 with Blocks 17 and 18 completed if required, and Certifications and Representations.
9 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Offerors are directed to thoroughly read the solicitation and fill in the required information in the appropriate solicitation clauses.
For any fill-ins that are not applicable, the Offeror must acknowledge by indicating "N/A". The proposal must also include computation for the use of Government-Owned Production and Research Property, if applicable.
b. See table below for specific paper and disc quantities required in proposal submission Original and four paper copies for a total of five paper copies, and five electronic CD/DVD copies of the proposal volumes I- VI (NOTE: Vol III is separate CD/DVD - do not include on same disc as other volumes. All other volumes may be combined in a single CD/DVD as long as five copies of each are provided.
), compiled using the Microsoft Office for Windows suite of applications, submitted on a single-write CD-ROM/DVD to prevent accidental erasure of the data therein, formatted for a MS Windows compatible computer. The Price Factor (Volume III) shall be contained on a separate CD/DVD from non-price Factors. Price breakdown will include MS Excel spreadsheets with formulae intact. If the Offeror provides electronically compressed files, all of the proposal files shall be compressed (zipped) into one file and the Offeror shall include the software used to compress and expand the proposal files, to include documentation. Process flows may be delivered in hard copy if not compatible with the above software. CD/DVD copy must mirror the submitted hard copies. If the CD/DVD copy and hard copy differ, the CD/DVD copy supplied for each Factor will be used for the evaluation. Each CD/DVD must be clearly marked with Offerors Name and Solicitation Number. Alternatively, files may be provided in Portable Document Format (.pdf).
c. Representations through System for Award Management: The purpose of electronic Representations and Certifications is to provide all
Offerors with a portal in which to submit Reps/Certs in a publicly accessible format, nullifying the requirement to submit identical information in response to each and every Federal contract solicitation. As a requirement under the instant solicitation, all Offerors must submit Reps/Certs data into the System for Award Management (S.A.M.) at https: //www.sam.gov/ or provide one electronic copy (on
CD/DVD) submitted as a .XPS file. Any Offeror that has previously submitted Reps/Certs data into SAM is reminded to update the data prior to submitting with the proposal. Alternatively files may be provided in .pdf format.
L.2.6 Each Large Business Offeror shall provide a Small Business Subcontracting Plan that contains all the elements required by FAR
52.219-9, alternate II. The small business Subcontracting plan shall be included in Volume V. This plan shall be incorporated into any resultant contract in reference to this RFP.
L.3 FORMAT FOR PROPOSALS
L.3.1 The Offeror's proposal will be submitted in severable volumes (combinable in the same CD/DVDs as provided in L.2.5.1.b.) based on the Factors as set forth below and all information specific to each Factor will be confined to that volume. Each proposal must include all volumes and shall be submitted by the closing date and time of the solicitation. Failure to provide any volume may result in the proposal being given an Unacceptable rating. Information provided shall be specific to each Factor.
a. Offerors are required to submit both electronic and paper copies of their offers as follows:
| Volume Number | Title | (Paper) | (Electronic) |
| Volume I | Cover Letter | 1 | 2 |
| Volume II | Technical Factor Proposal | 5 | 5 |
| Volume III | Price Factor Proposal | 2 | 2 |
| Volume IV | Past Performance Factor Proposal | 2 | 2 |
| Volume V | Small Business Participation Factor Proposal | 2 | 2 |
| Volume VI | Signed and completed copies of the attached Standard | 2 | 2 |
| | Form 33 (SF33) and continuation sheets signed by a | | |
| | person authorized to enter into the proposed contract | | |
| | on behladf of the Offeror. Continuation sheets to be | | |
| | filled in as directed (i.e., proposed costs in | | |
| | Section B, any fill-in required, such as: Section E, | | |
| | Higher-Level Contract Quality Requirements, Contract | | |
| | Data Requirements List (DD Forms 1423 with Blocks 17 | | |
| | and 18 completed with Not Separately Priced (NSP)). | | |
| | Contractor must be registered in ORCA at | | |
| | https: //orca.bpn.gov/ with all required | | |
| | Representations and Certifications. In addition, the | | |
| | Offeror must also include, in his/her proposal, the | | |
| | computation for use of Government-Owned Production | | |
| | and Research Property, if applicable. | | |
10 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
| | The contractor shall provide a signed copy release | | |
| | citing the contract number and giving the | | |
| | Government permission to reproduce and use | | |
| | copyrighted information, including that on vendor | | |
| | components and parts that would be published in the | | |
| | respective Government Technical Manuals. The release | | |
| | letter dhall be submitted to the Contracting Officer. | | |
b. Volume II (Technical) of the Proposals shall be limited to a maximum 30 single sided pages, excluding the Table of Contents and the test data matrix. The Technical Volume shall have a separate index, which contains narrative titles that are cross-referenced to both the applicable Statement of Work (SOW) paragraph and page number. This index shall not count against the Page limitation for the
Technical Volume. The narrative discussions shall also be related to the applicable SOW paragraph by placing the appropriate SOW number at the beginning of the discussion text.
c. Volumes I, IV, V, and VI of the Proposal has no page limit.
d. Volume III has no page limit
L.3.2 Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and solicitation number in the header and/or footer. A Table of Contents shall be created using the Table of Contents feature in MS Word. MS Word (.doc) files shall use the following page setup parameters:
Margins Top, Bottom, Left, Right - 1"
Gutter 0"
From Edge Header, Footer 0.5"
Page Size, Width 8.5"
Page Size, Height 11"
L.3.3 Length:
L.3.3.1 Each volume shall be as brief as possible, consistent with complete submission. The page count will be made by counting the pages from left to right, consecutively. Pages that exceed the page limitation will be returned to the Offeror and will not be evaluated. Each paragraph shall be separated by at least one blank line. Annexes, documentation and attachments that are submitted by the Offeror, which are not required as part of the RFP, will count against the page limitations. If pages are printed on both sides, each side will count as a separate page. The following will not count against page limitations: volume title pages, table of contents pages, cross-referencing pages, indices, acronym lists and page dividers (used to separate proposal sections). Pages shall not exceed 8-
1/2 inches in width by 11 inches in length; foldout pages depicting such items as sketches, factory floor layouts, etc. may be used, with each fold counted as one additional page. The font used shall not be less than 10 point.
L.3.3.2 Price Volume. Any documentation that is based on or includes mathematical calculations (e.g., calculations for rental value of government property in the Offeror's possession, calculations where there is the appearance of unbalanced pricing, etc.) shall be submitted in electronic, executable format utilizing Microsoft Excel. Any additional information necessary to explain the proposed pricing that does not contain mathematical calculations may be submitted in Adobe, Microsoft Word or Microsoft Excel format.
L.3.3.3 Deviation from Requested Format. Request for deviations from the requested format shall be submitted to the Procuring
Contracting Officer (PCO) no later than 15 days after release of the solicitation. Offerors shall provide an explanation, in a clearly relatable format such as a matrix, of any differences between the manner in which the proposal was requested and the manner in which it is proposed to be submitted.
L.3.3.4 The Offeror is responsible for including sufficient details to permit a complete and accurate evaluation of the proposal.
Offerors shall provide a proposal that, at a minimum, addresses those evaluation Factors and Subfactors required in Section M of the
RFP.
L.3.3.5 File Packaging - All of the proposal files shall be seperate uploads in their native format, i.e. .doc, .xls, .ppt, etc.Please note Self extracting .exe files will not be accepted.
L.4 SPECIFIC PROPOSAL INSTRUCTIONS
Offerors are responsible for including sufficient details (i.e. drawings, test data) to permit a complete and accurate evaluation strictly from a technical standpoint. The Offeror shall provide detailed narrative discussions that address the SOW, the Purchase
Descriptions, and CDRL's of the solicitation, as applicable. All information and data provided shall be specific to the Mounted Machine
Gun Optic, components and assemblies, except for the area of Past Performance. In the response to the Request for Proposal the Offeror must address the following Factors and Sub-Factors:
11 18
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
L.4.1. VOLUME II TECHNICAL FACTOR
L.4.1.1. Sub-Factor A FEASIBILITY
L.4.1.1.1. Offerors shall provide details on their Feasibility for producing of the MMO to meet the requirements of the solicitation.
Offerors shall provide any Test Data they may have resulting from tests on their current design. Data may be a result of tests conducted by the contractor, or tests conducted by a certified third party. Any test data that can substantiate the Offeror's claim to the performance of their design shall be submitted, if available. The Offeror shall describe how closely their current commercial design meets the requirements of the Purchase Description and if not, the necessary steps needed to achieve meeting the requirements.
L.4.1.1.2. The Offeror shall provide the Technology Readiness Level (TRL) and Manufacturing Readiness Level (MRL) of their current commercial product, prior to any redesigns for this effort.
L.4.1.1.3. The Offeror shall also detail the proposed approach and provide substantiating information to meet all the requirements of the Purchase Description (PD), including the laser filter and the reticle. The Offeror's technical data, documentation and supporting rationale shall be complete, specific and substantially show how the offered MMO will meet the applicable requirements.
L.4.1.1.4. The substantiating information may include, but is not limited to, commercial literature or brochures, test data, historical information, analytical support, supporting rationale, design documentation, pictures and/or videos supporting conformance of the proposed MMO to the Purchase Description. The Offeror shall identify all design activity necessary to meet the performance requirements and provide any available substantiated data which supports that the proposed MMO will meet the Purchase Description requirements.
Validated test and inspection data which establishes conformance of the offered configuration to the required performance levels represents the most credible form of substantiating data. The Offeror shall provide test data for only the configuration being offered, not of a current design that does not fully meet MMO Purchase Description Requirements. The Offeror must demonstrate understanding of the optical requirements by presenting calculations for determining the proper optical characteristics. Any substantiating data will count towards the page limits of Volume II (technical).
L.4.1.1.5. Laser Protection Filters:
L.4.1.1.5.1. The unclassified terms of unclassified Purchase Description and secret ARDEC Drawing 19200:13010593 LFU Codes: Lambda 1 through Lambda 9 and OD1 through OD4 are provided for your convenience to report and document in unclassified formats. There shall be no mention of specific wavelength bands, laser wavelengths, rejection levels, optical densities, specific tests lasers and/or laser makes and models. Photopic and scotopic transmission curves shall not include any wavelength scale. Failure to follow these guidelines may result in a breach of security and appropriate Government action against the Offeror, and may result in immediate rejection of the proposal.
L.4.1.1.5.2. The Offeror shall propose to meet all requirements for the laser rejection coatings and shall describe the specific filter technology planned to design and manufacture the laser filter optical element. The specific technology that will provide laser rejection level and throughput levels of the Purchase Description shall be described. The following specific areas shall be addressed in sufficient detail that demonstrates a complete technical understanding of the following:
a. General filter coating and absorbing glass design for Lambdas 1-9 and their relationship to both photopic and scotopic transmission.
b. The angle of incidence at the filter location (must be related to optical density).
L.4.1.1.5.3. Technical proposals that only mention a similar Army laser filter and assume the Government evaluator has specific performance knowledge of that "similar" filter may be found unacceptable.
L.4.1.1.6. Reticle Presence:
L.4.1.1.6.1. If the reticle is not of the embedded type, in addressing Reticle Presence, Purchase Description, and the Offeror shall also provide a certification…