USNS WASHINGTON CHAMBERS ROHDD Solicitation.docx

DOCX document 134 KB Posted

Attached to
SOLICITATION USNS WASHINGTON CHAMBERS ROHDD Federal contract opportunity
Solicitation number
N3220520R4122
Issued by
Department of the Navy Military Sealift Command

About this file

This document is a solicitation for regular overhaul and dry-docking services for the USNS WASHINGTON CHAMBERS. The solicitation is issued by the Department of the Navy Military Sealift Command and seeks Category A work items including vessel maintenance, testing and quality assurance services. Potential offerors must be capable of performing the full scope of work within their own facilities utilizing their own workforce or qualified subcontractors. The work is to be completed within 76 calendar days from contract award at the contractor's shipyard facility. The solicitation includes attachments outlining the work item package, contractor pricing breakdowns for Category A and B items, a government furnished material list, and other supporting documentation. The closing date for proposals is not specified in this document.

View the file

Other files for this federal contract opportunity

Other files attached to SOLICITATION USNS WASHINGTON CHAMBERS ROHDD, newest first.
File Type Posted
USNS WASHINGTON CHAMBERS ROHDD Solicitation Amendment 0004.docx DOCX document
USNS WASHINGTON CHAMBERS ROHDD Solicitation Amendment 0003.docx DOCX document
USNS WASHINGTON CHAMBERS ROHDD Solicitation Amendment 0002.docx DOCX document
USNS WASHINGTON CHAMBERS ROHDD Solicitation Amendment 0001.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220520R4122

Section B - Supplies or Services and Prices

CLAUSES INCORPORATED BY FULL TEXT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" WIs

FFP

Prepare for and accomplish the ROH/DD of the USNS WASHINGTON CHAMBERS (T-AKE 11) Total Category "A" WIs $_____________

Proposed unit price per KWh of electrical shore power $_____ IAW WI 0011, 7.1.1 Proposed unit price per gallon of potable water $______ IAW WI 0011, 7.1.3 Proposed unit price per gallon of distilled water $______ IAW WI 0011, 7.1.4 Proposed unit price per gallon of bilge water removal $______ IAW WI 0011, 7.1.18 Proposed unit price per crane usage $______ IAW WI 0011, 7.9.1 Proposed Hazardous Waste handling fee rate IAW WI 0023, 7.4.3. ______%

CDRLs FOR CLINs INCLUDING OPTION CLINs, IF EXERCISED:

The data to be furnished hereunder shall be prepared and submitted IAW the CDRL, DD Form 1423, Exhibit A, attached hereto. The CDRLs form a part of the schedule of this solicitation.

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR and ODC

AGR

(10,000) man-hours @ $________ per man-hour = $_____________

ODC

Base $1,000,000.00

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 - Continuation of Services

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0131

WI 0131- Kick Pipe Replacement

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0615

WI 0615- Flight Deck Net Replacement/Repair

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE

Category "B" WI 0902

WI 0902- DryDocking/Undocking Vessell

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE

Category "B" WI 0918

WI 0918- Freeboard Cleaning and Spot Blast

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE

Category "B" WI 0960

WI 0960- Underwater Hull Cleaning and Spot Blast

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE

Category "B" WI 0967

WI 0967- Bilge Keel Repairs

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0010 $______________

The contractor shall enter the total proposed price of all CLINs.

Section B, Price Schedule, detailed information

1. Attachment J-2, Category “A” WIs, provides a WI breakdown of CLIN 0001 pricing.

2. AGR and ODC

a. This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated during the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blastingTank cleaning
WeldingMachinists (inside and outside)
BurningBrazing
CarpentryElectrical work
Electronic workShipfitting
LaggingPainting
BoilermakingPipefitting
Sheetmetal workEngineering
RiggingStaging/scaffolding
General laborFire Watch

b. Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

TestingQuality Assurance
PlanningCleaning (except tank cleaning)
Material handling & warehousingSecurity
SurveyingAdministration
TransportationPurchasing staff
LoftingOther indirect support
Supervision

c. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's FBLR and not separately priced.

d. The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The ACO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

e. The base cost stated in this CLIN does not include the profit or G&A rates.

f. This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

3. AGR details.

a. The Government may utilize CLIN 0002 for and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the ACO to take any of the three (3) options set forth in subparagraph “d” below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and for negotiating changes. As part of the contractor’s proposal submission for AGR, the following shall be included:

- FBLR
- Proposed Labor Mix/Categories
- Proposed Man Hours
- Total Proposed AGR

c. Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “d”, below.

d. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

e. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in subparagraphs “d.1” and “d.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

f. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0010 at contract completion shall be de-obligated.

4. ODC details.

a. The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. ODC does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 ODC, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with AGR, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders ODC pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the ODC and will permit the ACO to take any of the three options set forth in subparagraph “e” below. As part of the contractor’s proposal submission for ODCs, the following shall be included:

MaterialEquipment
-Part number- Part number
-Order quantity- Order quantity
-Unit price- Unit price
-Total price- Total price

Other Direct Costs not captured above

- Travel

- Per diem (lodging, M&IE daily rates)

- Subcontractor Proposal Breakdown shall include but not be limited to, Material (Part number, Order Quantity, Unit Price, and Total Price), equipment (Part Number, Order Quantity, Unit Price, and Total Price), labor (FBLR, Proposed Labor Mix/Categories, and Proposed Manhours), and ODC (Travel and Per Diem)

- Etc.

The G&A and profit rates proposed shall be the same as the rates provided under CLIN 0002.

c. The contractor shall demonstrate due diligence in the assessment, evaluation, and determination resulting in the proposed utilization of other than local specialized labor resources. Only with ACO approval to proceed will a contractor, technical representative, or subcontractor be reimbursed for reasonable per diem costs (transportation, travel expenses, lodging, meals, and incidental expenses) required in connection with the associated change order. Per diem costs are considered reasonable, allowable, and reimbursable only to the extent that they do not exceed the allowed per diem rate in effect at the time of travel as set forth in the JTR.

d. Considering, G&A and profit rates have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of ODCs proposed to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) the costs of the ODCs are fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “e”, below.

e. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

f. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the ODC at the contractor's facility. Furthermore, in cases described in subparagraphs “e.1” and “e.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

g. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for the ODC (CLIN 0002). Settlement of ODC (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0010 at contract completion shall be de-obligated.

5. Attachment J-3, Category “B” WIs, provides a WI breakdown of CLIN 0003 through 0010 pricing.

Section C - Descriptions and Specifications

ACRONYM TABLE

ABIH
American Board of Industrial Hygiene
ABR
Agreement for Boat Repair
ABS
American Bureau of Shipping
ACO
Administrative Contracting Officer
AGR
Additional Government Requirements
AIHA
American Industrial Hygiene Association
ALT
Alternate
AMT
Amount
BLDG
Building
CCO
Contract Change Order
CD
Compact Disc
CDRL
Contract Data Requirements List
CD-ROM
Compact Disc Read-Only Memory
CFM
Contractor Furnished Material
CFP
Contractor Furnished Property
CFR
Condition Found Report
CHENG
Chief Engineer
CFR
Code of Federal Regulations
CIH
Certified Industrial Hygienist
CLIN
Contract Line Item Number

CONUS

CPARS

Contiguous United States Contractor Performance Assessment Reporting System

DBIDS
Defense Biometric Identification Systems
DFARS
Defense Federal Acquisition Regulation Supplement
DOD
Department of Defense
DOD SAFE
Department of Defense Secure Access File Exchange
DON
Department of the Navy
EMAIL
Electronic Mail
ESRS
Electronic Subcontract Report System
FAPIIS
Federal Awardee Performance and Integrity Information System
FAR
Federal Acquisition Regulation
FBLR
Fully-Burdened Labor Rate
F/CC
Fibers Per Cubic Centimeter
FPCON
Force Protection Condition
FTR
Federal Travel Regulations
G&A
General and Administrative
GFI-TD
Government Furnished Information – Technical Data
GFM
Government Furnished Material
GFP
Government Furnished Property
GPE
Governmentwide Point of Entry
IAW
In Accordance With
ID
Identification
ISO
International Organization for Standardization
JTR
Joint Travel Regulations
KO
Contracting Officer
KWh
Kilowatt Hour
LLTM
Long Lead Time Material
LPTA
Lowest Price Technically Acceptable
M&IE
Meals and Incidental Expenses
MSC
Military Sealift Command
MSCREP
Military Sealift Command Representative
MM
Millimeter
MSRA
Master Ship Repair Agreement
MTA
Mid-Term Availability
N/A
Not Applicable
NCACS
Navy Commercial Access Control System
NDA
Non-Disclosure Agreement
NO
Number
NSP
Not Separately Priced
ODC
Other Direct Costs
PAT
Proficiency in Analytical Testing

PDF

PII

Portable Document Format Personally Identifiable Information

PM
Program Manager
PPE
Principle Port Engineer
PRIME
Prime Contractor
QA
Quality Assurance
QC
Quality Control
REV
Revision
RFC
Request for Specification Clarification
RFP
Request for Proposal
ROH/DD
Regular Overhaul/Dry-Docking
SECNAV
Secretary of the Navy
SF
Standard Form
SUB
Subcontractor
TPSN
Time Phased Sequencing Network
TWA
Time-Weighted Average
USC
United States Code
USCG
United States Coast Guard
USNS
United States Naval Ship
VR
Voyage Repair
WAWF
Wide Area Workflow
WI
Work Item

SCOPE OF WORK

1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS WASHINGTON CHAMBERS (T-AKE 11) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.

2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):

a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.

b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.

c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.

d. Using management procedures and systems to identify behind schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.

e. Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.

f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.

g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.

h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.

i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.

j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.

k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.

3. Contract work shall be performed by an eligible contractor as defined below.

a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.

b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:

1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.

2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.

3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.

4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.

5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.

6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.

7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.

8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.

9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records, which indicate type of material, date, and place of disposal.

10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:

· Pier, with services in place, accessible to the CLASS size ship for birthing

· Structural Shop

· Machine Shop

· Pipe Shop

· Electrical/Electronic Shop

· Carpentry Shop

· Rigging Equipment

· Dry-dock – when required for docking of vessel in performance of the specification

11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.

c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.

4. Asbestos removal requirements.

a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.

b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.

c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).

d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.

e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.

f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:

1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.

2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.

3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.

4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.

g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).

h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.

i. The contractor shall insert this instruction in all subcontracts entered into under this contract.

5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and will require specific approval by the KO.

6. Substitution of key personnel.

a. The contractor agrees to assign to this contract those persons identified as key personnel whose resumes were submitted with the proposal and who are necessary to fulfill the requirements of this contract. No substitution of key personnel shall be made except IAW these instructions.

b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.

c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced. The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.

7. It is anticipated the ship will arrive at the contractor’s yard on or about 04 JAN 2021. All work shall be completed in no more than 76 calendar days from the actual start date designated by the Government at the time of contract award.

8. The place of performance for this contract shall be the contractor’s facility.

9. This award consummates the contract, which consists of the following documents: (a) the Government’s solicitation and your final proposal revision submitted on {date} inclusive of all discussion and clarifications responses and (b) this award/contract.

Table 1: List of WIs:

CATEGORY “A” WORK ITEMS

001INTENT, SCOPE, GENERAL REQUIREMENTS, AND DEFINITIONS
002TECHNICAL AND MANUFACTURER’S REPRESENTATIVES
003APPROACH, BERTH, AND MOORING REQUIREMENTS
004TESTING AND QUALITY ASSURANCE
005ELECTRICAL SAFETY PROCEDURE REQUIREMENTS
006HEAVY WEATHER PLAN
007COLD WEATHER PLAN
010FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM
011FURNISH GENERAL SERVICES
012INFORMATION TECHNOLOGY
013PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS
014PREPARATION OF WEIGHT AND MOMENT REPORT
015INTEGRATED LOGISTICS AND GFM SUPPORT REQUIREMENTS
016FIRE PROTECTION AND SHIP’S SAFETY PROGRAM
017HANDLING SHIP’S STORES
018DELIVERY AND REDELIVERY OF THE VESSEL
019SHIPBOARD ACCESS AND SECURITY
020GAS FREE CERTIFICATES
021CLEAN AND GAS FREE TANKS, VOIDS, COFFERDAMS AND SPACES
022DOCK TRIALS AND SEA TRIAL
023HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR’S FACILITY
024PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY
090DAILY COVID-19 PREVENTION AND CONTROL SERVICES REV J 5-14-2020 PERFORMANCE BASED CLEANING
101TAKE_CSI_BALLAST TANK ZINC INSPECTION (2.5 YR)
105TANK BOUNDARY TESTING AND STRUCTURAL SURVEY ABS 2
106HULL SURVEY SUPPORT SPECIAL SURVEY 2
107EXTERIOR_DECK_GRATINGS_REPLACEMENT_(T-ALT_457)
109MMR PLENUM DOOR INSTALL (TALT 408)
110COMPOSITE VENT GRATING REPLACEMENT (TALT 524)
112WEIGHT TEST INSTALLED HOISTS
113HULL VENT MATERIAL REPLACEMENT (TALT 425)
155TAKE_CCSI_TANK VENT INSPECTION (5 YR)
201TAKE_CSI_PROPULSION MOTOR AND COOLER CLEANING, INSPECTION AND MAINTENANCE (2.5 YR) (SCSI)
202MDE FLEXIBLE CONNECTORS (FLEX HOSE) REPLACEMENT (10-YR) (CSI)
204TAKE_CSI_MDE CONTROL SAFETY INSPECTION AND TEST (1 YR) (SCSI)
205TAKE_CSI_AUTOMATION AND PROPULSION CONTROL INSPECTION AND TEST (1 YR) (SCSI)
206TAKE_CSI_VULKAN COUPLING INSPECTIONS (1 YR) (SCSI)
207TAKE_CSI_PROPULSION MOTOR PEDESTAL BEARING INSPECTION (5 YR) (SCSI)
208MDE RESILIENT MOUNTS REPLACEMENTS
209MAIN MACHINARY BILGE CLEANING
210BMAIN ENGINE 9 CYLINDER SERVICE (30K HRS
211VULKAN COUPLING REPLACEMENT
301BTAKE_CSI_CLEANING MAIN GENERATORS & PROPULSION CONTROL SYSTEM (10 YR) (SCSI)
302HIGH VOLTAGE CABLE CRIMP CONNECTOR INSPECTION
303TAKE_CSI_HIGH VOLTAGE, SHIP'S SERVICE, AND EMERGENCY SWITCHBOARD INSPECTION AND CLEANING (2.5 YR)
305OP 4 STOREROOMS LIGHTING UPGRADE TALT 374
308EATON TIME DELAYS REPACEMENT TALT 496
310CHLOROPAC POWER SUPPLY SOURCE MODIFICATION T-ALT 474
401VOYAGE DATA RECORDER, BATTERY - REPLACE (1 X 5 YEARS)
402TAKE_CSI_ANTENNA PREVENTATIVE MAINTENANCE (5 YR)
403COMMS SYS PM_REV -
405TAKE_CSI_ANTENNA RIGGING PHOTOS (10 YR)
408TAKE_CSI_WIND SPEED MEASURING AND INDICATION SYSTEM CERTIFICATION (3 YR)
410HYDRA RADIO UPGRADE TALT 472 AND SYSTEM GROOM
451TAKE_CCSI_ANNUAL RADAR SERVICE
452TAKE_CCSI_ANNUAL ECDIS SERVICE (SCSI)
453TAKE_CCSI_ANNUAL GYRO SYSTEM
454TAKE_CCSI_ANNUAL VDR RECERTIFICATION
455TAKE_CCSI_ANNUAL RADIO COMMUNICATION EQUIPMENT RECERTIFICATION
456TAKE_CCSI_MAGNETIC COMPASS SERVICE (2 YR)
457TAKE_CCSI_EPIRB SERVICE (5 YR)
459ECHO SOUNDER SERVICE (1YR)_TAKE_CCSI
460TAKE_CCSI_ANNUAL INSPECTION OF ALARMS
504BTAKE_CSI_CARGO CRANE MAINTENANCE AND RETESTING (10 YR) (SCSI)
505EDG LUBE OIL COOLER INSTALLATION T-ALT 359
506TAKE_CSI_EMERGENCY DIESEL GENERATOR -ANNUAL TESTING AND INSPECTION (1 YR) (SCSI)
507EDG FLEXIBLE HOSES REPLACEMENT (5-YR)
509TAKE_CSI_DISTILLING PLANT MAINTENANCE (5 YR)
510OIL CONTENT METER CALIBRATION (SCSI)
512BTAKE_CSI_MAGAZINE SPRINKLER GAUGE SPRINKLER CALIBRATION - T11-14
514RELIEF VALVE TESTING (CSI)
516TAKE_CSI_SEWAGE SYSTEM PIPING CLEANING (2.5 YR)
521INCINERATOR INSPECTION AND MAINTENANCE
523BOW THRUSTER LUBE OIL PIPING MOD (T-ALT 291)
525AT SEA FUELING VALVE INSTALLATION (T-ALT 265)
527TAKE_CSI_BRINE SYSTEM FLUSH (5 YR)
528BMAGAZINE SPRINKLER VALVE OVERHAUL_MONTREAL (10 YR)
529CARGO BRINE SYSTEM VALVE REPLACEMENT
530TAKE_CSI_MAIN DIESEL GENERATOR PEDESTAL BEARING INSPECTION (5 YR) (SCSI)
531TAKE_CSI_SCBA CASCADE FILL STATION HYDRO TEST (5 YR)
532AFT STEERING MTR CTLR INDICATOR LIGHT RELOCATION TALT 503
537EDG FO LO REACH ROD MODS T-ALT 17-0471
546TAKE_CSI_STEERING GEAR PREVENTIVE MAINTENANCE (10 YR)
557ANCHOR WINDLASS ANNUAL INSPECTION
562TAKE_CCSI_SCBA ANNUAL INSPECTION
563TAKE_CCSI_SCBA AIR COMPRESSOR AND FILLING STATION INSPECTION & MAINTENANCE (1 YR)
565TAKE_CCSI_FIXED GAS FIREFIGHTING SYSTEM INSPECTION AND TEST (1 YR) (SCSI)
567TAKE_CCSI_FIXED FOAM FIREFIGHTING SYSTEM INSPECTION AND TEST (1 YR) (SCSI)
569TAKE_CCSI_FIRE AND SMOKE DETECTION ALARM SYSTEM (1 YR) (SCSI)
570TAKE_CCSI_PORTABLE FIRE EXTINGUISHER SERVICE (1 YR)
571TAKE_CCSI_FIRE AND SMOKE DAMPER SERVICE (1 YR) (SCSI)
572TAKE_CCSI_DEEP FAT FRYER AND RANGE FIRE EXTINGUISHING SYSTEM (1 YR) (SCSI)
573TAKE_CCSI_FIRE HOSES (1 YR) (SCSI)
575TAKE_CSI_WATER MIST FIREFIGHTING SYSTEM - INSPECTION AND TEST (1 YR) (SCSI)
576REVERSE_OSMOSIS_UNIT_CLEANING,_INSPECTION AND MAINTENANCE
601LB RHIB DAVITS ACCOM LDR ANNUAL INSPECTIONS
606FLIGHT DECK NON-SKID RENEWAL
608GALLEY OVEN REPLACEMENT
610GALLEY AND MSO EQUIPMENT CALIBRATION
614LIFE BOAT AND RHIB GEL COAT PRESERVATION
652TAKE_CCSI_LIFEBOAT DAVIT SERVICE AND INSPECTION (5 YR)
654TAKE_CCSI_RESCUE BOAT AND DAVIT SERVICE (5 YR)
655TAKE_CCSI_IMMERSION SUIT SERVICE (3 YR)
656TAKE_CCSI_ANNUAL LIFE RAFT CERTIFICATION
658TAKE_CCSI_ACCOMMODATION LADDER MAINTENANCE AND TESTING (5 YR)
659ADDITIONAL LIFEBOAT, RESCUE BOAT AND ASSOCIATE DAVIT REPAIRS
801GALLEY AND LAUNDRY EXHAUST DUCT CLEANING
803BRINE AND DEFROST PUMP AND MOTOR REPLACEMENT AND OVERHAULS (1)
804AIR HANDLER AND FAN COIL UNIT CLEANING
807CARGO AND AC PLANT INSP AND GROOM
809NO 3 AC COMPRESSOR OVERHAULING REV-
851TAKE_CCSI_ANNUAL GALLEY VENTILATION AND GAYLORD HOOD CLEANING
853TAKE_CCSI_ACCOMMODATION VENT SYSTEM CLEANING (5 YR)
901TAKE_CCSI_DRYDOCKING AND UNDOCKING THE VESSEL (2.5 YRS)
903PROPELLER SHAFT AND STERN TUBE INSPECTION WAFT SEAL
904TAKE_CSI_STERN_TUBE_SEAL_INSPECTION_(FW_SYSTEM)_(5_YR)
905BTAKE_CSI_BOW THRUSTER MAINTENANCE (5 YR)
907TAKE_CSI_POLISH BOW THRUSTER PROPELLER (2.5 YR)
908TAKE_CSI_RENEW SEACHEST, ROPE GUARD, AND BOW THRUSTER ZINCS (5 YR)
909ANCHOR AND ANCHOR CHAIN RANGING
912SHAFT GROUNDING SYSTEM MAINTENANCE
913TAKE_CSI_RENEW WASTER PIECES (5 YR)
915FREEBOARD CLEANING AND PAINTING (NEAR WHITE B
917VALVE MOV GROOM
953TAKE_CCSI_ANCHOR CHAINS AND LOCKERS (5 YR)
956TAKE_CCSI_OVERHAULING SEA VALVES (5 YR)
959TAKE_CCSI_UNDERWATER HULL CLEANING AND PAINTING - NEAR WHITE BLAST (10YR)
962TAKE_CCSI_CATHODIC PROTECTION SYSTEM (2.5 YR)
966SHAFT ALIGNMENT AND BEARING REACTION CHECKS_TAKE_CCSI
1004HP AIR RELIEF VALVE CALIBRATION
1005HP AIR FLASK INSPECTION
1021RAM_TENSIONER_AND_CARGO_KINGPOST_SHEAVE_REFURBISHM
1022UNREP_FAS_FAIRLEAD_AND_SOT_BLOCK_REFURBISHMENT
1023TRANSFER HEAD REFURBISHMENT
1026400HZ_AND_28VDC_AND_WINDBIRD_RECERTIFICATION
1050TAKE_CCSI_SLIDING BLOCK CHAIN REPLACEMENT (5 YR)

CATEGORY “B” WORK ITEMS

025PHYSICAL_SECURITY_AT_PRIVATE_CONTRACTOR_FACILITY_REV_28NOV18
030CONTINUATION_OF_SERVICES,_REV_OCT_18
131KICK PIPE REPLACEMENT
615FLIGHT DECK NET REPAIR/REPLACEMENT
902DRY_DOCKING_AND_UNDOCKING_VESSEL
918FREEBOARD CLEANING AND PAINTING (SPOT BLAST)
960UNDERWATER HULL CLEANING AND PA SPOT
967BILGE_KEEL_REPAIRS

Section D - Packaging and Marking

WOOD PACKAGING MATERIAL (WPM) - ADDITIONAL DELIVERY INSTRUCTIONS

In accordance with the requirements of International Standards for Phytosanitary Measures (ISPM) 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM). WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). All materials must include certification markings in accordance with ALSC standards and be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved "DUNNAGE" stamp. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.

(end of instructions)

Section E - Inspection and Acceptance

CLAUSES INCORPORATED BY REFERENCE

252.217-7005
Inspection and Manner of Doing Work
JUL 2009
252.217-7006
Title
DEC 1991
252.217-7013
Guarantees
DEC 1991

Section F - Delivery and Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE
52.242-15
Stop-Work Order
AUG 1989
52.242-17
Government Delay Of Work
APR 1984
52.247-55
F.O.B. Point For Delivery Of Government-Furnished Property
JUN 2003

Section G - Contract Administration data

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s): INVOICE

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

INVOICE

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF
Data to be entered in WAWF
Pay Official DoDAAC
N32205

Issue By DoDAAC

Admin DoDAAC**

Inspect By DoDAAC

Ship To Code
N62387

Ship From Code

Mark For Code

Service Approver (DoDAAC)

Service Acceptor (DoDAAC)

Accept at Other DoDAAC

LPO DoDAAC

DCAA Auditor DoDAAC

Other DoDAAC(s)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

MSCHQ_WAWF@NAVY.MIL

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

MSC SPECIFIC WIDE AREA WORKFLOW (WAWF) INSTRUCTIONS (AUG 2012)

The information contained in this instruction is supplemental to DFARS 252.232-7006.

The information contained in the table in DFARS 252.232-7006 is for WAWF purposes only. Information included in DFARS 252.232-7006 and this WAWF instruction apply only to WAWF Invoicing and WAWF Receiving Reports. Contradictory information elsewhere in this contract, e.g. Ship to DoDAAC, shall be followed per the terms and conditions of the contract.

When entering the invoice into WAWF, the Contractor shall fill in the DoDAAC fields or DoDAAC extensions exactly as shown in the table in DFARS 252.232-7006. Fields that should not be filled in when entering the invoice into WAWF will be indicated with the direction, “Leave Blank.”

In some situations the WAWF system will pre-populate the “Pay DoDAAC,” “Admin By DoDAAC” and “Issue By DoDAAC.” The Contractor shall verify that those DoDAACs automatically entered by the WAWF system match the information in the table in DFARS 252.232-7006. If these DoDAACs do not match, then the Contractor shall correct the field(s).

If Receiving Reports are required, ensure that the “Inspection” and “Acceptance” defaults of “destination” for both fields are not changed in the WAWF online interface.

The CLINs on the WAWF invoice shall be entered exactly as set forth in the contract document including CLIN number (e.g. 0001), Quantity (may be adjusted for actual quantity or dollar value delivered and invoiced), and Unit Price (e.g. $1.00). The dollar amounts on each CLIN or SubCLIN on the WAWF invoice shall reflect final performance values, but in no instance can the dollar amount for each CLIN or SubCLIN exceed what is specified in the contract document. The Contractor shall bill to the lowest level, e.g., the SubCLIN level. The Quantity and Unit of Measure fields must be filled out exactly as indicated in the CLINs and SubCLINs to reduce the possibility of the invoice being delayed or rejected during processing.

Before closing out of an invoice session in WAWF, but after submitting the document or documents, the Contractor will be given the option to send additional email notifications by clicking on the “Send More Email Notifications” link that appears on the page.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .