Transformers Revised Section 7_0.pdf

PDF 44 KB Posted

Attached to
Replacement of Transformer and Switches - Salinas, CA Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area

View the file

Other files for this federal contract opportunity

Other files attached to Replacement of Transformer and Switches - Salinas, CA, newest first.
File Type Posted
12905B22Q0060 Amd 0002.pdf PDF
12905B22Q0060 Transformer Replacement RFI Answers.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised section

7.0 Base Item:

A. All work will be performed in compliance to the NEC & NFPA70 codes.

B. Contact PG&E as required to coordinate the replacements of the transformers.

C. Provide a detailed timeline of each task D. Remove old equipment and return removed equipment to USDA maintenance personal for accountability.

Remove existing equipment and dispose equipment that will no longer be used except for the circuit breakers. Disposal of these items will be done in accordance with local laws and ordinances. Return existing circuit breakers to the maintenance personnel onsite for accountability.

E. Install equipment efficiently to limit downtime and provide advance notice of power loss to Administrative Officer for coordination purposes.

Install new equipment efficiently and provide temporary power when power loss will be longer than 2hrs. Coordinate with the Administrative Officer anytime power will be lost.

Temporary power is required for power losses lasting longer than 2 hours due to critical research equipment onsite.

F. Prior to final inspection clean the area and remove any trash, unused materials, and debris