Technical_Questionnaire.docx
DOCX document 24 KB Posted
- Attached to
- Ravine Restoration Federal contract opportunity
- Solicitation number
- 140P6422R0014
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Specifications_-_Ravine_Restoration_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Sol_140P6422R0014_Amd_0001.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| Wage_Determination_-_Bayfield_Co.pdf | ||
| Technical_Questionnaire.pdf | ||
| Bid_Schedule_-_Ravine_Restoration.xlsx | XLSX spreadsheet | |
| Sol_140P6422R0014.pdf | ||
| Specifications_-_Ravine_Restoration.pdf | ||
| Bid_Schedule_-_Ravine_Restoration.pdf | ||
| Past_Performance_Questionnaire.doc | DOC document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONNAIRE
Ravine Restoration
Apostle Islands National Lakeshore
OFFEROR:
SOLICITATION #:
DATE:
PLEASE NOTE: IN ADDITION TO PRICING PROVIDED ON THE BID/PRICE SCHEDULE, YOUR RESPONSES ON THIS QUESTIONNAIRE (AND YOUR RESPONSES ON THE PAST PERFORMANCE QUESTIONNAIRE) ARE CRITICAL TO THE SELECTION OFFICIAL WHEN EVALUATING A PROPOSAL FOR AWARD. INADEQUATE OR VAGUE RESPONSES MAY RESULT IN A LOWER RATING (PLEASE SEE SECTION M OF THE SOLICITATION FOR EVALUATION INFORMATION). YOU MAY USE ADDITIONAL PAGES FOR YOUR RESPONSES, IF NEEDED.
SUBFACTOR #1 – Technical Approach
Technical approach is your means and methods to complete the technical aspect of required work as described in the project specifications. Submit a written narrative limited to 5 pages describing your technical approach to the specific aspects below. Additional pages will not be evaluated. Pictures can be included and will not be counted towards the page limitation.
· Approach to Critical Contract Requirements: Describe your approach to successfully accomplish stream/ravine restoration or similar in accordance with requirements outlined in the Project Specifications and Drawings within proposed contract performance period and budget.
SUBFACTOR #2 – Key Personnel
Submit breakdown of key personnel as identified below with experience in ravine/stream restoration or similar. All personnel proposed are subject to substitution requirements contained in this solicitation.
· Project Manager
· Superintendent
· Construction Management (field staff)/
· On-Site Safety Specialist/Manager
SUBFACTOR #3 – Project Experience
Submit "Project Experience" addressing specific experience working in ravine/stream restoration or similar in the below section/box.
NOTE: Submit the same projects for Past Performance as submitted under this factor.
SUBFACTOR #4 – Schedule
Submit your proposed construction schedule for THIS SPECIFIC PROJECT showing completion within the required period of performance contained in this solicitation with accompanying schedule narrative. Submit your schedule so that it is clear and concise. There is no preprinted form for this submittal.
SUBFACTOR #5 – Safety
Submit a written narrative limited to 5 pages describing your company’s Construction Safety Program and an assessment of the safety risks associated with this construction project. Please describe your safety plan for a project of this nature.