Statement of Work SOW Air Handling Unit Replacement Building 39 .docx

DOCX document 778 KB Posted

Attached to
Replace Air Handling Unit (AHU) - Building 39 Federal contract opportunity
Solicitation number
12405B23Q0442
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery

About this file

This statement of work outlines requirements for replacing an air handling unit at a USDA research facility. The scope of work includes removing an existing 7.5-ton package unit and installing a new single pass unit that is 1 to 1.5 tons larger, multi-stage, and high efficiency. Additional requirements are to provide a new thermostat, reconnect and modify existing ductwork including supply duct insulation, upgrade electrical if needed, and route the condensate line away from a nearby walkway. The contractor must follow all USDA physical security and safety rules, work can only be done Monday through Friday from 8am to 4pm excluding holidays, and the contractor is responsible for cleanup.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Air Handling Unit (AHU) - Building 39, newest first.
File Type Posted
SF1449 SOLICITATION 12405B23Q0442.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Replace Building 39 Air Handling Unit (AHU) Southeast Poultry Research Lab 6/29/2023

GENERAL

SCOPE OF WORK. This contract is located at the USNPRC at 934 College Station Road Athens GA, 30605. The contract requirements are defined in this Statement of Work (SOW).

The purpose of this SOW is to replace 39 AHU. The scope of work includes the following:

· Replace existing 7.5 ton Carrier package unit, model 48HJR009-H-651—with a single pass unit.

· Size new unit up 1 to 1.5 tons.

· New unit shall be multi-stage.

· Propose a high efficiency unit.

· New thermostat.

· Reconnect existing ductwork. Modify if needed including supply duct insulation.

· Existing breaker is 25A. If proposed unit needs upgraded wire size and breaker it must be included in the pricing.

· Route condensate line away from nearby walkway into grass behind building.

· Startup and test.

PHYSICAL SECURITY. Contractor will be required to follow all USDA physical security and safety rule/regulations.

HOURS OF OPERATION. Normal Hours. The USNPRC is open Monday through Friday from 8am until 4pm except for Government holidays.

GOVERNMENT-FURNISHED PROPERTY AND SERVICES

No Government-furnished property will be provided. Government-furnished utilities will be provided where available.

CONTRACTOR-FURNISHED ITEMS AND SERVICES

GENERAL. Contractor shall furnish everything required to perform this Statement of Work.

CLEAN-UP. The Contractor is responsible for cleanup of any work site.

image1.jpeg image2.jpeg