Statement of Work for the RCAG Tower Replacement Project located in Horton Oregon.pdf
PDF 555 KB Posted
- Attached to
- Award Notice: Tower Construction Horton OR Federal contract opportunity
- Solicitation number
- 6973GH-21-C-00048
About this file
This document provides a statement of work and related award notice for a federal tower replacement project. The statement of work details requirements for demolishing existing communication towers at two sites in Horton, Oregon and designing, fabricating, and installing new self-supporting towers. Key requirements include tower design and foundation construction, demolition and disposal of existing towers, installation of electronic cables and grounding systems, and project closeout documentation. The related award notice indicates that contract 6973GH-21-C-00048 for this tower replacement project was awarded on May 5, 2021 to KOBO Utility Construction Corp. in the amount of $671,480 by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
WS-21-00386
RCAG Tower Replacement Project
Horton, Oregon
December 2020
Introduction: The FAA is planning to select a contractor for Horton telecommunication tower replacement project including demolition of existing towers, and design, manufacture and installation of new RCAG towers at two FAA QXW & QXWA facilities located at Horton, Oregon.
Project Description: The QXW RCAG facility will have two (2) new 40ft Self Standing towers installed. The QXWA RCAG facility will also consist of two (2) new 40ft Self Standing towers installed. The towers will be supported by concrete foundations, type TBD based on the soil conditions. Telecommunication equipment and electronic cables are mounted on the tower platform as detailed in construction drawings and project specification. The towers also consist of lightning protection system to be connected to the existing grounding system. The existing
QXW site consists of three existing 40ft guy-wire towers located at a plot approximately 200’ x
100’ and QXWA site consists of two 40ft and two 60ft existing guy-wire towers at a plot approximately 100’ x 100’. The sites are located at Horton, OR, and are max. 0.3miles far away.
The project includes design, procurement and installation of new towers and associated platform, design/construction of foundations, procurement/installation of electronic cables, lightning protection system, prefabricated manholes, enclosures, conduits and associated material, hardware and connectors as required. The project also includes all construction activities required to complete the project per specifications and construction drawings. All existing guy – wire towers as well as one decommissioned telco tower (at QXW site) to be demolished and the material to be recycled or disposed per this project.
The existing site plans of QXW and QXWA sites are shown in appendix A & B. The proposed locations of the towers is shown in construction drawings attached to this document.
Local district System Support Center (SSC) will provide the necessary escort to the sites.
Note: The procurement and installation of electronic cables from tower junction box to communication antennas and from building junction box to radio racks inside the building, as well as procurement and installation of communication antennas are excluded from this scope of work. (GFM are provided in section 1 11 00 project specification)
Task Description: The contractor shall provide all personnel, equipment, tools, materials, supplies, supervision, labor and other items and services necessary to design, fabricate, prepare for shipment, delivering and installation of new towers and demolition of existing towers for
Horton Tower replacement project. The contractor is responsible for all work activities to complete the Horton tower replacement project as detailed in project specifications and construction drawings attached to this Statement of Work (SOW) and in accordance with the latest version of the applicable codes and standards as referenced to the project specifications.
Work includes but not limited to:
1. Perform an independent underground utility locate prior to the excavation. Perform onsite review of marked locations with FAA and Resident Engineer (RE) / Contract
Officer Representative (COR) prior to excavation activities. Some areas may require hand digging to ensure no interruptions will occur
2. The demolition - construction of towers to be conducted in distinct phases per sequences specified in the construction drawings
3. Quality Control concrete testing shall be done by an independent testing agency approved by the FAA
4. Contractor is responsible for demolition and recycling of three (3) existing guy-wire towers at QXW site, four (4) existing guy-wire towers at QXWA site and associated structure, foundation, existing antennas and all associated antenna material including conduits, antenna mounts, grounding, antenna cable enclosures, coaxial cables, and lightning protection materials, manhole and trenches
5. Demolish and dispose of existing concrete blocks (supporting existing guy anchors) at both sites per construction drawings
6. Demolish one existing decommissioned (Telco) timber tower (at QXW site only) and dispose waste material per construction drawings and project specifications.
7. Contractor is responsible to perform abatement where activities impact existing regulated materials in accordance to project specifications, local, state and federal requirements. Remove and properly dispose of all waste materials from the site.
8. Contractor is responsible to design, supply and construction of the tower foundation
(type TBD), per TIA-222-H standard requirements, project specifications and site geotechnical report recommendations. Design calculation report and construction drawings shall be provided by contractor and approved by FAA.
9. The contractor to purchase and deliver two (2) new 40’ self-supporting antenna towers to QXW site and two (2) new 40’ self-supporting RCAG communication antenna towers to QXWA site. The towers will be delivered to the sites by the tower fabricator or contractor. Contractor shall provide the complete tower in accordance with all specification requirements including anchor bolts, safety ladder, safety climbing devices, anti-climbing device/tower ladder door, eight fully operational/retractable swing-arm antenna mounts, two (2) air terminal support masts, lockable access hatches and all other hardware essential for erecting the tower. The supply list shall be completed per project specifications and construction drawings. It is the responsibility of the contractor or its subcontractor to provide the design of the antenna towers.
Calculation report and construction drawings shall be provided and approved by FAA.
10. Hot dipped galvanized and coat per Section 09 97 00, Special Coatings, tower elements and fasteners as required to minimizing the possibility of premature corrosion.
11. Contractor is responsible for offloading and installing the new towers. Contractor shall be responsible for touching up any damaged paint and/or galvanization sections of the tower during construction.
12. Supply and install of one NEMA 4x SS electronic enclosure (J-box) on each tower platform per construction drawings. Supply and install the J-box supports.
13. Supply and install of one NEMA 4x SS enclosure to be mounted on external wall of the building at each site (one J-Box each site) per construction drawings. Supply and install the
J-box support.
14. Supply and install electronic coaxial cables and connectors between tower J-box and building J-box per construction drawings. Provide supports on tower and coaxial cable shield grounding kit on each antenna tower. Supply RGS conduits for containing the coaxial cables including all elbows, clamps, and supports for installation or connection. Excavate trenches from new towers to the building for RGS conduits. The conduits shall be buried per construction drawing and the trenches shall be backfilled after conduit installed.
15. Provide coaxial cable tests and test report.
16. Electrical grounding and lightning protection at communication antenna towers: This includes: Excavate and backfill perimeter trench around new antenna towers for new EES, Modify existing RCAG facility EES and bond new antenna tower EES to the modified EES;
Provide air terminals and down conductors on antenna towers; Provide antenna tower electrical ground bonds to ladder, antenna cables enclosures, structural steel, foundation rebar, antenna mounts, and coaxial cable shields; Provide conductors/conduit to bond down conductors and antenna cable enclosures per construction drawings;
17. Perform earth resistance tests of new EES system and provide written test reports.
18. Contractor is responsible for terminations and testing of towers’ ground connections.
19. Contractor to provide two (2) Dyna-Glide Climbing Protection System Fall Arresters per site (total 4ea). The fall arresters shall be delivered at the same time as the climbing protection system and remains on-site after project is completed.
All material shall be delivered at construction FAA QXW and QXWA sites located at
Horton, OR.
Additional Information: Public underground utility lines, power and phone shall be located by calling 811 and coordinating with the city entities. Also, locate private FAA utilities including power and comm./telecom cable. Contractor must use ground penetrating radar (GRP) or equivalent technology to locate private FAA utilities. Clearly mark all findings before starting any excavation/digging or other underground activities. All permits and work plans shall be submitted and approved before work is started. Access to the site must be coordinated with the
FAA in advance.
Project Specific Work Plans: The contractor is required to submit written work plans in accordance with the submittal requirements set out in section 01 33 00, Submittal Procedures, for critical items of work set out in this section, in the technical specifications, or elsewhere in the contract documents. Work associated with the required work plans shall not commence until approval has been provided.
Work Plan shall address the site safety plan, underground utility damage prevention, crane work, fall protection, risk management plan, hazard assessment of the work site, pre-installation work plan, construction schedule and demolition plan.
Requested Submittals: The contractor is solely responsible for creating a Submittal Schedule identifying whether the submittals are samples, cut sheets, certified test results, and adding additional submittals as required by specifications, drawings or as recommended by a manufacturer. As applicable, the submittal schedule must state the action required for testing and inspection with the name of the persons authorized to review the submittal. The contractor shall submit the Submittal Schedule to the contracting officer for approval. See section 01 33 00 of project specification for complete submittal list and submittal procedure. At a minimum, the following preconstruction submittal items must be provided to the FAA for review and approval before notice to proceed:
1. Work break down structure (WBS) including construction schedule details
2. Contractor site-specific safety plan
3. Reinforcing steel Data sheet
4. Concrete mix design
5. Contractor personnel climbing certificates
6. List of proposed subcontractors
Contractor shall provide construction submittal items as listed in section 1 33 00 to the FAA for review and approval prior to installation including but not limited to:
1. Substitutions and all requested changes
2. Subsurface Locate Contractor Qualifications
3. Material safety data sheets, certification, manufacture catalog and instructions
4. Test reports ,
5. Delivery tickets
6. Tower manufacturer specification and drawings
7. Qualifications and Certifications of independent inspections and testing firms.
8. Design data including calculation report, construction drawing, mix designs, analyses or other data pertaining to a part of work.
Warranties & Guarantees: Contractor must provide warranties/guarantees executed by the respective manufacturers, suppliers, and subcontractors for all installations as required in the contract or as is customarily provided with the particular piece of equipment or system. All warranties are to be executed, in writing, for the benefit of the FAA. Contractor must provide complete information for each item per project specification.
Cleaning and Waste Management: Contractor is required to maintain the worksite including storage areas clean and orderly during progress of the work per project requirements and specifications. The contractor will be personally responsible for the storage of tools and materials.
The contractor must require each subcontractor engaged upon the work to bear full responsibility for cleaning up during and immediately upon completion of their work.
Prior to final inspection, thoroughly clean entire worksite and exterior and interior of any building, remove debris and rubbish, remove tools and reseed disturbed areas as detailed in section of 1 74 00 of project specification.
Closeout: The contractor must coordinate with the resident engineer (RE), the date to schedule the Contractor Acceptance Inspection (CAI) per project specification requirements (See Section
1 77 00 of project specification).
The RE shall conduct an inspection of the facility to verify all contract conditions are met.
Prior to final acceptance, the contractor must assemble all appropriate warranties, product information, certifications, equipment installation instructions, Safety Data Sheets (SDS), and the results of all tests.
Appendix A: QXW Existing Site plan
Appendix B: QXWA Existing Site plan
| Horton Tower Project-SOW |
| QXW RCAG -existing Drawings |
| QXWA RCAG existing Drawings |