This statement of work outlines requirements for the purchase and installation of 155mm prior to rifle pneumatic bore gages for Watervliet Arsenal. The contractor shall provide bore gages capable of measuring barrel diameters ranging from 154.5mm to 155.8mm to a maximum depth of 30 feet. The gages must utilize a Dimentron-style body with an opposing pneumatic slide mechanism and integrated air blow-off to avoid marring gun bores. Additional requirements include a 1840 column amplifier-type readout, master set rings in specified sizes, storage cases, a minimum of two days of manufacturer support for installation and training, and a complete list of wear components and spare parts. The related federal contract opportunity is solicitation number W911PT22Q0021 for the purchase of two 155mm post-rifle and two 155mm pre-rifle pneumatic bore gages as specified in the statement of work. The proposed contract is 100% set aside for small businesses and proposals must include valid SAM registrations and representations. The solicitation will be issued electronically on beta.SAM and any amendments must be obtained periodically to remain responsive.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911PT22Q0021 - Air Gages.pdf | ||
| STATEMENT OF WORK - 155MM POST RIFLE AIR GAGES ODP-P.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
PURCHASE AND INSTALATION OF
155MM PRE-RIFLE PNEUMATIC BORE GAGES
Watervliet Arsenal Building 35-2
PR 75220003
PRODUCTION PLANNING (ODP-P)
PART 1 GENERAL
1.01 Overview.
A. This Statement of Work (SOW) defines the requirements for 155mm prior to rifle bore gages.
1.02 Hours of Operation.
A. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.03 General Requirements.
A. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf B. Bore gage capable of measuring in-process bore diameters ranging from 154.5mm to 155.8mm using 2 point contact gaging LVDT probes.
C. Measure bore diameters to a max depth of 30 feet. Gage handle to include graduations for bore depth measurement in 1/16” increments.
D. Dimentron style body will utilize an opposing pneumatic slide mechinism and air blow off built into the body of the measuring head to avoid marring gun bores.
E. All pneumatics to be activated manually by valve or fot switch F. 1840 column amplifier type readout G. Include all accessories required to operate the gage, including valves, foot switches etc.
H. Master set rings to be provided in the following sizes: 155.7956mm, 155.3210mm, 155.2956mm, 155.2702mm, 154.7956mm I. Up to 3 pelican type storage cases per gage as required.
J. Minimum 2 days of manufacturer/vendor support required for installation and training at Watervliet Arsenal.
K. Include complete list and source of supply for all wear components and or spare parts including measuring contact points, spacers, air hose, electrical cables and measuring head components.
L. Function and repeatability test to be performed at WVA.
1.04 Safety Requirements.
A. General.
1. The contractor shall be responsible for complying with all DOD, Army, Federal and State health and safety requirements that are applicable to this project, and shall use all means and precautions available to ensure the safety of the occupants and protection to the existing buildings and structures.
1.05 Applicable Documents.
A. Watervliet Arsenal Instructions for Contractors (WAIC).
1.06 Submittals.
A. The contractor shall e-mail all submittals to the Contracting Specialist for review and approval. All submittals require government approval unless otherwise explicitly stated.
PART 2 PRODUCTS
2.01 General.
A. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon and Polychlorinated Biphenyls (PCB).
B. All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation and disposal of the product.
2.02 Products and Materials.
A. Bore gage for diameter measurement of 155mm barrels prior to rifling.
B. Installation and training required for use of bore gage.
File details come from the government source that posted it. Updated .