Solicitation Amendment

View the file

Other files for this federal contract opportunity

Other files attached to Arm Assembly, Pivot, newest first.
File Type Posted
SPRDL1-18-R-0154_FBO_Solicitation.pdf PDF
SPI.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0002 2018APR10

SPRDL1

DLA LAND WARREN

WARREN, MI 48397-5000

DELLE REMSEY

EMAIL: DELLE.V.REMSEY.CIV@MAIL.MIL

SPRDL1-18-R-0154

2018MAR28

X

X 2018MAY11 01:00pm

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 7

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: DELLE REMSEY

Buyer Office Symbol/Telephone Number: ZGAA/(586)467-1160

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

The purposes of Amendment 0002 are to:

1. Extend the solicitation due date to May 11, 2018 (1:00 pm - EST).

2. Add clauses:

a. 52.242-4008 (Routing of Special Process Approvals)

b. 52.211-4017 (Painting Test)

c. 52.209-1 (Qualification Requirements)

3. Revise clause 52.247-4006 (Method of Evaluation of Transportation for FOB Origin Offers).

****Note: Due to system issues, Amendment 0001 is obsolete and does not apply.****__________________________________________________________________________________

*** END OF NARRATIVE A0002 ***

2 7

SPRDL1-18-R-0154 0002

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION E - INSPECTION AND ACCEPTANCE

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

E-1 ADDED 52.211-4017 REQUIREMENTS FOR PRETREATMENTS AND CHEMICAL AGENT RESISTANT COATINGS NOV/2014

(TACOM) LOCAL WARREN - PAINTED MATERIEL

(a) Scope

(1) This clause applies to contracts requiring Chemical Conversion Coatings and Pretreatments for Metallic Substrates, Chemical

Agent Resistant Coating (CARC), and their related materials. The requirements in this clause clarify and supplement those in the contract, unless nullified elsewhere in the contract or through an approved Request for Deviation.

(2) Coating qualification, spot paint repair, and MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base coatings are not within the scope of this clause.

(b) Definitions

(1) The contracting agency, appropriate agency, procuring authority, engineering authority, procuring agency, and procuring activity is the PCO or designee.

(2) The prime contractor is the company awarded this contract, and the subcontractors comprise all companies involved in providing coated parts to the prime contractor, including companies that apply the coatings.

(c) General Requirements Clarifications

(1) The government retains the right for onsite verification of the prime contractors and its subcontractors products, processes, procedures, and test reports.

(2) The prime contractor shall be responsible for itself and its subcontractors to produce and maintain detailed process control plans, process control data, pre-production approval testing, ongoing quality control & quality control testing, and test reports.

This information shall be available upon government request.

(3) The prime contractor shall immediately notify the PCO and the Defense Contract Management Agency (DCMA) of any failure to meet preproduction and production requirements.

(4) Each cleaning method shall be treated as a separate step in the process documentation.

(5) The Gage Repeatability and Reproducibility (Gage R&R) error shall be less than 30 percent for all process and product measurement systems.

(6) Products with hexavalent chromium, including but not limited to certain fastener finishes, shall not be used. Additionally, CARC topcoats containing siliceous additives to control gloss are prohibited.

(7) CARC primer and CARC topcoat shall not be applied directly to bare metal or plastic, except as provided for in MIL-DTL-53072.

(8) If the contract specifies application of CARC materials over a non-CARC coating, then both CARC primer and CARC topcoat are required. The complete coating system shall meet the requirements for CARC defined in TT-C-490.

(9) Neutral salt spray (NSS) testing shall not be used to validate compliance with materiel life cycle requirements; NSS is a production quality test and does not predict field performance.

(d) Pre-Production Approval Clarifications

(1) Pre-production testing shall include:

(i) Thickness of each layer of the coating system;

(ii) Coating system adhesion;

(iii) Salt spray performance; and

(iv) For phosphate pretreatments, the phosphate coating weight, crystal size and shape, and scanning electron microscope photos of the phosphate coatings at 500x and 1000x magnification.

(2) Pre-production test samples shall be from the material used for production parts, pieces cut from production representative parts, or production representative parts. Standardized test coupons shall not be used.

(3) Nine samples shall be produced for the required testing and shall include: three cleaned and pretreated test samples, three samples with the complete paint system and, depending on the CARC paint system, either three samples with pretreatment plus primer or three samples with metal-rich primer plus primer.

(4) One or more ISO 17025 laboratories shall conduct pre-production testing on the nine test samples in accordance with (IAW) the applicable test method accreditations. The applicable ISO 17025 test method accreditations include ASTM B117 Salt Spray, ASTM B244

Thickness of Non-Conductive Coatings on Non-Magnetic Metals, ASTM B487 Measurement of Metal and Oxide Coating Thickness, ASTM B499

Thickness of Non-Conductive Coatings on Magnetic Metals, and ASTM D3359 Measuring Adhesion by Tape Test.

(5) Unless required elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

(6) Test procedures shall be submitted IAW the Contract Data Requirements List (CDRL) DI-NDTI-80603 documenting Pretreatment and

Chemical Agent Resistant Coating procedures when this CDRL is included in the contract.

(7) Test reports from the ISO 17025 accredited labs shall be submitted for Pretreatment and Chemical Agent Resistant Coating testing specified in paragraph (d)(4) of this clause IAW the Contract Data Requirements List (CDRL) DI-NDTI-80809 when this CDRL is included in the contract.

(e) Production Testing Clarifications

(1) At a minimum, ongoing production quality tests shall conducted and recorded daily for coating adhesion and coating thickness, and monthly for salt spray testing. Use of ISO accredited laboratories is optional for these ongoing tests of production parts.

(2) Production parts or pieces cut from production parts shall be used for ongoing production quality testing. Standardized test

3 7

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

coupons shall not be used.

(3) Unless specified elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

[End of Clause]

E-2 ADDED 52.242-4008 ROUTING OF SPECIAL PROCESS APPROVALS DEC/2005

(TACOM)

(a) The Technical Data Package for this contract contains one or more of the following specifications:

MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base

TT-C-490 Chemical Conversion Coatings and Pretreatment for Ferrous Surfaces (Base for Organic Coatings)

MIL-W-12332 Welding Resistance, Spot: Weldable Aluminum Alloys

MIL-W-45210 Welding Resistance, Spot: Weldable Aluminum Alloys

*Drawing 12479550 Ground Combat Vehicle Welding Code - Steel

*Drawing 12472301 Ground Combat Vehicle Welding Code - Aluminum

* If these drawings are not available with your procurement package, please contact the contract specialist on page 1.

(b) The specifications listed in paragraph 1 may require you to get approval from the Government prior to production for one or more special processes involved in producing the item. The following shall apply, unless stated elsewhere in the contract:

(1) You shall prepare the written procedures as the specification requires.

(2) Procedures requiring Government approval shall be routed to the Administrative Contracting Officer (ACO) for review and approval. If the ACO is unable to perform a review, the ACO shall forward the procedure to the Procuring Contracting Officer (PCO) for assistance in the review and approval process. The correct address for the PCO is on the face page of this contract.

(3) You shall cite (i) the contract number and (ii) the governing specification or standard on all procedures you submit for approval.

(4) The DCMA will provide a copy of their approval/rejection notices to the PCO.

(5) DCMA is required to qualify the processes of the major coating subcontractors used by the prime contractors.

[End of Clause]

4 7

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION I - CONTRACT CLAUSES

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

I-1 CHANGED 52.209-1 QUALIFICATION REQUIREMENTS FEB/1995

(a) Definition. Qualification requirement, as used in this clause, means a Government requirement for testing or other quality assurance demonstration that must be completed before award.

(b) One or more qualification requirements apply to the supplies or services covered by this contract. For those supplies or services requiring qualification, whether the covered product or service is an end item under this contract or simply a component of an end item, the product, manufacturer, or source must have demonstrated that it meets the standards prescribed for qualification before award of this contract. The product, manufacturer, or source must be qualified at the time of award whether or not the name of the product, manufacturer, or source is actually included on a qualified products list, qualified manufacturers list, or qualified bidders list.

Offerors should contact the agency activity designated below to obtain all requirements that they or their products or services, or their subcontractors or their products or services, must satisfy to become qualified and to arrange for an opportunity to demonstrate their abilities to meet the standards specified for qualification.

Name:

Competition Management Office

Address:

By email: Usarmy.detroit.tacom.mbx.lcmc-competition-management-of@mail.mil

By mail: 6501 E. 11 Mile Rd., ATTN: AMSTA-CSC-M, MS 309, Warren, MI 48397-5000

(c) If an offeror, manufacturer, source, product or service covered by a qualification requirement has already met the standards specified, the relevant information noted below should be provided.

Offerors Name _______________________________________________________

Manufacturers Name __________________________________________________

Sources Name ________________________________________________________

Item Name ____________________________________________________________

Service Identification _______________________________________________

Test Number (to the extent known) __________________________________________________________

(d) Even though a product or service subject to a qualification requirement is not itself an end item under this contract, the product, manufacturer, or source must nevertheless be qualified at the time of award of this contract. This is necessary whether the Contractor or a subcontractor will ultimately provide the product or service in question. If, after award, the Contracting Officer discovers that an applicable qualification requirement was not in fact met at the time of award, the Contracting Officer may either terminate this contract for default or allow performance to continue if adequate consideration is offered and the action is determined to be otherwise in the Governments best interests.

(e) If an offeror, manufacturer, source, product or service has met the qualification requirement but is not yet on a qualified products list, qualified manufacturers list, or qualified bidders list, the offeror must submit evidence of qualification prior to award of this contract. Unless determined to be in the Governments interest, award of this contract shall not be delayed to permit an offeror to submit evidence of qualification.

(f) Any change in location or ownership of the plant where a previously qualified product or service was manufactured or performed requires reevaluation of the qualification. Similarly, any change in location or ownership of a previously qualified manufacturer or source requires reevaluation of the qualification. The reevaluation must be accomplished before the date of award.

(End of Clause)

5 7

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

6 7

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION M - EVALUATION FACTORS FOR AWARD

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

M-1 CHANGED 52.247-4006 METHOD OF EVALUATION FOR F.O.B. ORIGIN TRANSPORTATION OFFERS DEC/2015

(TACOM)

(a) For the evaluation of this offer, we will use the lowest freight rates from the Transportation Officer that are:

- in effect (or the lowest rates that will become effective before the expected date of initial shipment), and

- on file or published with the Transportation Officer by the date of bid opening (or by the closing date specified for requests for proposals), and

- for the Government selected method of shipment, and

- based upon the following freight classification:

STCC ITEM NO.: 3599990

NMFC ITEM NO.: 133300

[End of Provision]