SPRDL1-18-Q-0469_Questions.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
Gas Filter Element Federal contract opportunity
Solicitation number
SPRDL1-18-Q-0469
Issued by
Department of the Army Materiel Command TACOM Life Cycle Management Command

About this file

KTR Questions and Government Responses

View the file

Other files for this federal contract opportunity

Other files attached to Gas Filter Element, newest first.
File Type Posted
SPRDL118Q0469_for_FBO.pdf PDF
SPRDL118Q0469_CDRLs_Attachment_0001.rtf RTF text file
https://www.fbo.gov/fedteds/SPRDL118Q0469 —

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionGovernment Response
I don’t see listed in the solicitation the guaranteed minimum order quantity. Are the quantities listed in CLIN’s 0001AA, 0002AA, and 0003AA firm quantities? Meaning when you place the initial order for CLIN 0001AA you will be ordering 178 each? When and if you exercise option CLIN’s 0002AA and 0003AA you will be ordering 134 each year?0001AA is a firm quantity. If we exercise 0002AA we will be ordering 134 more, if we exercise 0003AA we will be ordering 134 more.
I do not see in your solicitation the Order Limitations clause 52.216-19. Is that not a requirement for this solicitation?This is not required for this solicitation. It is anticipated that this order will be under the SAT.
On First Article CLIN 0001AB you have listed 20 each. The item QAP and the solicitation clause 52.209-4513 call out that each First Article you must present 20 units. Then on your CLIN 0001AB you have 20 First Articles, generally speaking we see that as 1 LOT because the quantity is called out in the solicitation or in the item specification. I am assuming you aren’t requesting pricing for 20 First Articles consisting of 20 Filter Elements correct? You are wanting pricing for 1 First Article which consists of 20 units correct? I just want to make sure we price correctly.Correct. We are requesting 1 LOT of 20 units for FAT.
On Page 23 of 60, paragraph c, you have the Government required delivery schedule with first article test of a quantity of 446 120 days ARO. This quantity represents all 3 ordering years, but I am assuming you aren’t ordering all 3 ordering years with the first order correct? Is that quantity actually 178 to be delivered 120 days ARO?120 ARO.