KTR Questions and Government Responses
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPRDL118Q0469_for_FBO.pdf | ||
| SPRDL118Q0469_CDRLs_Attachment_0001.rtf | RTF text file | |
| https://www.fbo.gov/fedteds/SPRDL118Q0469 | — |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question | Government Response |
| I don’t see listed in the solicitation the guaranteed minimum order quantity. Are the quantities listed in CLIN’s 0001AA, 0002AA, and 0003AA firm quantities? Meaning when you place the initial order for CLIN 0001AA you will be ordering 178 each? When and if you exercise option CLIN’s 0002AA and 0003AA you will be ordering 134 each year? | 0001AA is a firm quantity. If we exercise 0002AA we will be ordering 134 more, if we exercise 0003AA we will be ordering 134 more. |
| I do not see in your solicitation the Order Limitations clause 52.216-19. Is that not a requirement for this solicitation? | This is not required for this solicitation. It is anticipated that this order will be under the SAT. |
| On First Article CLIN 0001AB you have listed 20 each. The item QAP and the solicitation clause 52.209-4513 call out that each First Article you must present 20 units. Then on your CLIN 0001AB you have 20 First Articles, generally speaking we see that as 1 LOT because the quantity is called out in the solicitation or in the item specification. I am assuming you aren’t requesting pricing for 20 First Articles consisting of 20 Filter Elements correct? You are wanting pricing for 1 First Article which consists of 20 units correct? I just want to make sure we price correctly. | Correct. We are requesting 1 LOT of 20 units for FAT. |
| On Page 23 of 60, paragraph c, you have the Government required delivery schedule with first article test of a quantity of 446 120 days ARO. This quantity represents all 3 ordering years, but I am assuming you aren’t ordering all 3 ordering years with the first order correct? Is that quantity actually 178 to be delivered 120 days ARO? | 120 ARO. |