About this file
This justification for other than full and open competition details a sole source procurement of level-1 shaft sleeves from MetalTek International. The requirement was posted to BetaSam with solicitation number SPMYM3-20-Q-3056 but received no responses. As stated in an attached certification, the Military Services would be seriously injured by delays to this acquisition for shipyard maintenance. Market research in the form of a sources sought notice also received no responses. Previous acquisitions for this material from MetalTek took 9-12 months for delivery after award, demonstrating the need for an expedited sole source contract to MetalTek. Negotiations will ensure a fair and reasonable price for this procurement, and the contracting activity will seek earlier competition on future similar requirements to overcome barriers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 93524001 TDP.pdf | ||
| 93194011 (TDP) PNTDP0085-SHAFT SLEEVE.pdf | ||
| SPMYM3-20-Q-3056.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification for Other Than Full & Open Competition (November 2011)
6. The use of the authority cited in other than 10. U.S.C. 2304(c)(2) above is based on:
Not Applicable
7. Efforts to ensure that offers are solicited from as many sources as practicable are:
[X] The acquisition will be synopsized and any firm requesting a solicitation copy will be provided one.
This requirement will be posted to BetaSam utilizing solicitation number SPMYM3-20-Q-3056.
8. A market survey:
[X] was conducted, and firms indicating an interest in the acquisition will be solicited. Market research efforts, include:
Sources sought notice SPMYM3-20-Q-5S02 was posted to BetaSam. No responses were received.
9. Additional facts supporting other than full and open competition are:
[X] As stated in the attached certification by the requiring activity, the Military Services will be seriously injured if contract award is delayed. The extent and nature of harm are detailed in the attached certification
Please see the attached email traffic with the information regarding the impact of delays to this acquisition.
10. A listing of sources, if any, indicating an interest in the acquisition are: (If none, so state)
MetalTek International 905 E. St. Paul Avenue Waukesha, WI 53188 USA Cage Code: 93812
11. The actions being taken to overcome barriers to competition before any subsequent acquisitions are made are:
(If none, so state and explain why not.)
The Portsmouth Naval Shipyard will continue to try to initiate the procurement process far enough in advance to allow for attempted competition on these type of requirements.
12. I hereby determine that the anticipated cost to the Government will be fair and reasonable.
Previous acquisitions will be looked at for this material and an inflation analysis developing a should cost will be conducted. Negotiations will be held with MetalTek to obtain the best price possible for the Government.
13. Additional facts, if any, supporting this determination:
Information was provided to demonstrate the length of time that can pass between the initiation of a requirement to the time the material arrives on the Shipyard. Three examples provided by the Shipyard are as follows:
SPMYM3-11-C-3044: Awarded to Metaltek on 9/21/2011, received 9/2012.
SPMYM3-11-C-3047: Awarded to Metaltek on 9/21/2011, received 8/2012.
SPMYM3-11-C-3012: Awarded to Metaltek on 4/27/2011, received 9/2011.
Justification for Other Than Full & Open Competition (November 2011)
HEAD OF THE CONTRACTING ACTIVITY
I have reviewed and approve this Justification $93,000,000 or below.
Name and Title Signature Phone Date