About this file
This document is an amendment to a solicitation for the procurement of ventilation hatch houses. The Defense Logistics Agency Land and Maritime is seeking proposals to design and fabricate replacement ventilation hatch houses measuring approximately 9 feet 5 inches by 14 feet 8 inches. The hatch houses must have the capability to interface with an external crane for lifting components that are 8 feet by 7 feet 9 inches. Electrical power requirements are 440 volts. Responses were due by February 9, 2022. The amendment provides answers to questions from potential offerors to clarify requirements. No drawings, specifications, or technical data for the needed hatch house design were available from the agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment I - PS -29076 REV B Drawing.pdf | ||
| Amendment SPMYM122R00020002.pdf | ||
| Solicitation SPMYM122R0002.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N4215812744920
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
I. The purpose of this amendment is to answ er questions submitted to the Contracting Off ice for this solicitation.
II. All other contract terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X SPMYM122R0002
X 9B. DATED (SEE ITEM 11)
09-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Mar-2022
CODE
DLA MARITIME NORFOLK
SHAWNTA WELLS
CODE NMAB.P6
(757) 278-5075/FAX 396-8119
PORTSMOUTH VA 23709
SPMYM1 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SPMYM122R0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
QUESTIONS & ANSWERS
1. Q: We are working on the quote for you but wanted to advise that dure to the size of the project; progress payments will be required, please advise if this will be an issue.
A: Progress payments will not be required. However; partial deliveries and partial payments may be authorized as delivery is staggered.
2. Q: Are there any available pictures, prints or technical documents for the above solicitation regarding hatch houses?
A: There are no available pictures, prints or technical documents for this solicitation.
3. Q: Will the drawings be pre-approved before fabrication?
A: The drawings will be pre-approved before fabrication.
4. Q: How many windows and doors are wanted?
A: No windows and one door.
5. Q: Will these be steel or aluminum?
A: There is no preference; either steel or aluminum will be acceptable.
6. Q: Who designed and/or fabricated the current hatch houses in use?
A: The original ventilation hatch houses were designed and fabricated by H.P.S. Fabrications, Inc. as they were procured in 2011.
7. Q: Is the Diagrams on page 6 a conceptual Hatch house or the existing ones?
A: The diagram on page 6 is a conceptual hatch house.
8. Q: Are there dimensional max/minimum height drawings?
A: There are no dimensional max/minimum height drawings.
9. Q: What are the power requirements for the ventilation system?
A: The power requirements for the ventilation system is 440 volts.
10. Q: What is the required static pressure?
A: The required static pressure is unknown.
11. Q: What are the power requirements for the entire hatch house?
A: The power requirements for the ventilation system is 440 volts.
12. Q: Is an overhead crane required or just capability to use external crane?
A: Capability to use external crane.
13. Q: What is the required clear opening for external crane use?
A: The required clear opening for external crane use is 8 ft by 7 ft 9 in.
SPMYM122R0002
14. Q: Please clarify intent to supply and exhaust air or just supply air.
A: The intent is to supply or exhaust air.
15. Q: Could you also tell me how you are mounting the units to the subs?
A: It will be based on your design.
16. Q: Do you have a Cad data file-stepfiles and pdf files?
A: There are no Cad data file-stepfiles and pdf files.
17. Q: Do you have actual sizes? They can done with A-0 fire insulated walls?
A: The actual size is 9 ft 5 in. by 14 ft 8 in.