About this file

This is a solicitation for dock-side repairs and maintenance services for the USCGC SPENCER (WMEC 905) from June 16, 2021 through August 10, 2021. Services include cleaning, inspection, testing and repair or replacement of ship systems and components such as heat exchangers, exhaust piping, lube oil coolers, potable water tanks, air receivers and compressed air system valves. Required submittals are a completed price schedule, signed amendments and technical documentation. Quotes must follow instructions and include all submittals to be considered. The Coast Guard is the contracting agency seeking these ship repair and system maintenance services to be performed at its facility.

View the file

Other files for this federal contract opportunity

Other files attached to Dock-Side: USCGC SPENCER FY21 DS1, newest first.
File Type Posted
SPENCER Amendment 0001 of Solicitation P4566100.pdf PDF
0001 pages 2-3 SPENCER DS Repairs.pdf PDF
Spencer DS1 FY21 RFQ.pdf PDF
SPENCER DS FY21 SOSS BLANK.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC SPENCER (WMEC 905)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2021

Developed By: Cedricka M Dalton

(Rev-0, 30 December 2020)

USCGC SPENCER (WMEC-270B) DOCKSIDE AVAILABILITY FY2021

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics ............................................................................................................................. xii General Requirements WORK ITEM 1: Seawater Heat Exchangers; Clean, Inspect And Hydro WORK ITEM 2: Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean WORK ITEM 3: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 4: Lube Oil Heat Exchangers; Clean, Inspect And Hydro WORK ITEM 5: Chill Water System, Clean And Flush WORK ITEM 6: Potable Water Pneumatic Tank(s), Clean and Inspect WORK ITEM 7: Hot Water Accumulator Tanks, Clean and Inspect WORK ITEM 8: Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift ... 38 WORK ITEM 9: Appleton FB 20-21 Single Point Davit (SPD), Renew WORK ITEM 10: Sewage Discharge and Transfer Pumps, Renew WORK ITEM 11: Grey Water Holding Tank(s), Clean and Inspect WORK ITEM 12: Sewage Holding Tank(s), Clean and Inspect WORK ITEM 13: Sewage Piping, Clean And Flush WORK ITEM 14: Tanks (Grey Water Holding), Preserve “Partial” WORK ITEM 15: Tanks (Sewage Holding), Preserve “Partial” WORK ITEM 16: Sewage Control System, Upgrade WORK ITEM 17: Hydraulic Oil Fill Cap and Deck Fitting, Renew WORK ITEM 18: Lube Oil Fill Cap and Deck Fitting, Renew WORK ITEM 19: Navigation Shop Deck Plating, and Drip Pan, Renew WORK ITEM 20: Deck Drain Piping, Renew WORK ITEM 21: Tank Manhole Covers, Renew WORK ITEM 22: Bridge Windows, Renew WORK ITEM 23: Kick Pipes, Renew WORK ITEM 24: Plenum Fan Space Decks, Renew WORK ITEM 25: Deck Covering (Interior Wet/Dry), Renew WORK ITEM 26: Deck Covering, Electrical Matting, Renew WORK ITEM 27: Berthing Shower Pans and Deck Covering, Renew WORK ITEM 28: Flexible Couplings, Renew WORK ITEM 29: Fuel Vent Piping, Renew iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 901 WMEC 612-004, Rev A, NAVSEA Certified Flight Deck Net Installation

Coast Guard Drawing 905 WMEC 131-001, Rev D, Main Deck, Plate & Frame, FWD 101

Coast Guard Drawing 905 WMEC 131-002, Rev C, Main Deck Plating & Framing AFT 182

Coast Guard Drawing 905 WMEC 131-003, Rev D, Mn Dk Pl & Fr 101-182

Coast Guard Drawing 905 WMEC 136-002, Rev E, 01 Level Pl & Fr AFT 182

Coast Guard Drawing 905 WMEC 136-003, Rev E, 01 Level Pl & Fr 101-182

Coast Guard Drawing 905 WMEC 152-001, Rev E, Dk Hse Strl Bhds 02 Lvl Ext

Coast Guard Drawing 905 WMEC 152-002, Rev F, Dk Hse Strl Bhds 02 Lvl Int

Coast Guard Drawing 905 WMEC 152-005, Rev C, 02 Level Plating & Framework

Coast Guard Drawing 905 WMEC 162-001, Rev B, Stacks

Coast Guard Drawing 905 WMEC 167-001, Rev M, List of Structural Closures

Coast Guard Drawing 905 WMEC 201-001, Rev H, Engine Room Arrangement

Coast Guard Drawing 905 WMEC 245-005, Rev B, CPCH Prop Hyd Fill and Transfer Sys Diag

Coast Guard Drawing 905 WMEC 245-010, Rev C, CPCH Hydraulic Fill & Xfer System A&D

Coast Guard Drawing 905 WMEC 256-002, Rev J, Eng Rm SW Cooling Sys A&D

Coast Guard Drawing 905 WMEC 256-008, Rev B, SSDG Modification JW Cooling System Mod

Coast Guard Drawing 905 WMEC 256-011, Rev -, Mn and Aux SW Cooling Sys Diag

Coast Guard Drawing 905 WMEC 259-001, Rev D, Diesel Exhaust System Diagram

Coast Guard Drawing 905 WMEC 259-002, Rev C, Diesel Exhaust System Arr & Det

Coast Guard Drawing 905 WMEC 262-002, Rev E, Lube Oil Service System A&D

Coast Guard Drawing 905 WMEC 262-008, Rev -, Lube Oil System Diagram

Coast Guard Drawing 905 WMEC 264-001, Rev E, L.O. Fill, Xfr & Purification Sys A & D

Coast Guard Drawing 905 WMEC 310-008, Rev B, Emergency Diesel Generator Arrangement & Details

Coast Guard Drawing 905 WMEC 320-014, Rev AJ, Electrical One-Line Diagram

Coast Guard Drawing 905 WMEC 320-015, Rev -, Power System Mods Pilot House Window

Replacement

Coast Guard Drawing 905 WMEC 320-054, Rev E, Power System Mods Incidental to Sewage Control

Panels Replacement

Coast Guard Drawing 905 WMEC 501-002, Rev C, Aux Mchry Sp No 2 Arrangement v (Rev-0)

Coast Guard Drawing 905 WMEC 501-003, Rev F, Steering Gear Room Arrangement

Coast Guard Drawing 905 WMEC 505-007, Rev J, Piping Sys Cleaning & Flushing Procedures

Coast Guard Drawing 905 WMEC 505-008, Rev B, Bulkhead, Deck & Shell Piping Penetrations

Coast Guard Drawing 905 WMEC 506-002, Rev G, Ovfl, Air Escape & Sounding Tube A&D Fwd FR

Coast Guard Drawing 905 WMEC 506-006, Rev -, Overflow Air Escape and Sounding Tube System

Diagram

Coast Guard Drawing 905 WMEC 514-001, Rev F, HVAC System Diagram

Coast Guard Drawing 905 WMEC 514-020, Rev E, CHW & HW Sys Diag

Coast Guard Drawing 905 WMEC 514-021, Rev C, CHW & HW System Machinery Spaces A&D

Coast Guard Drawing 905 WMEC 514-022, Rev B, CHW & HW Piping System Mn Dk & Blw A&D

Coast Guard Drawing 905 WMEC 514-024, Rev B, CHW & HW Pipe Sys 01 Lvl & Abv – A&D

Coast Guard Drawing 905 WMEC 517-002, Rev F, Waste Heat Recovery / Ship Service Diesel Generator

Jacket Water – A&D

Coast Guard Drawing 905 WMEC 517-007, Rev B, Main Propulsion Engine Jacket Water System A&D

Coast Guard Drawing 905 WMEC 528-001, Rev K, Plumbing Vents & Drains Sys Diagram

Coast Guard Drawing 905 WMEC 528-006, Rev D, Vents & Drains Main Deck A & D

Coast Guard Drawing 905 WMEC 528-007, Rev A, Vents/Drains, 01 Level and Above – A & D

Coast Guard Drawing 905 WMEC 533-009, Rev B, Potable Water Brominator System Diagram

Coast Guard Drawing 905 WMEC 551-001, Rev R, Compressed Air System Diagram

Coast Guard Drawing 905 WMEC 551-007, Rev A, Air Receivers Instl & Arr

Coast Guard Drawing 905 WMEC 583-032, Rev -, Arrangement Mods to Suit Inboard Location of

Appleton Marine Crane Model FB 20-21

Coast Guard Drawing 905 WMEC 593-001, Rev C, Vacuum Flush Collection System Electrical

Schematic Diagram

Coast Guard Drawing 905 WMEC 593-002, Rev A, Sewage Vacuum System Component Installation

Arrangement and Detail

Coast Guard Drawing 905 WMEC 593-003, Rev F, Sewage Transfer System Diagram

Coast Guard Drawing 905 WMEC 593-004, Rev E, Sewage Transfer System - A&D

Coast Guard Drawing 905 WMEC 593-005, Rev B, Sewage Vacuum System Diagram

Coast Guard Drawing 905 WMEC 593-006, Rev F, Sewage Vacuum System Below Main Deck – A&D

Coast Guard Drawing 905 WMEC 593-007, Rev D, Sewage Vacuum Sys, Mn Deck & Abv – A&D

Coast Guard Drawing 905 WMEC 625-001, Rev A, Window List Fxd, Plt & Aprt

Coast Guard Drawing 905 WMEC 625-002, Rev B, Pilothouse Window Installation A&D

Coast Guard Drawing 905 WMEC 625-003, Rev A, Pilot House Window Replacement

Coast Guard Drawing 905 WMEC 634-001, Rev D, Deck Covering Schedule

Coast Guard Drawing 905 WMEC 801-003, Rev H, General Arrangement 02/Pilothouse & Above

Coast Guard Drawing 905 WMEC 801-004, Rev F, General Arrangement 01 Level

Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement Main Deck

Coast Guard Drawing 905 WMEC 801-020, Rev D, Booklet of General Plans

NAVSEA Drawing 803-5184097, Rev B, Safety Nets, Dk Edge, Aluminum Frame, Nylon Net vi (Rev-0)

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 2723, Jun 2007, Manufacturer’s Instruction Book—SWBS

Group(s) 593, Sewage Holding System

Coast Guard Technical Publication (TP) 2815, Oct 2017, Reduction Gear

Coast Guard Technical Publication (TP) 2817, SWBS 245, Section A, Feb 2018, Controllable Pitch

Propeller System

Coast Guard Technical Publication (TP) 2820, May 2017, Ship Service Diesel Generator

Coast Guard Technical Publication (TP) 2820A, May 2017, Ship Service Diesel Generator

Coast Guard Technical Publication (TP) 2839, Aug 2020, Manufacturer’s Instruction Book—SWBS

Group(s) 588-593, Sections A and B

Coast Guard Technical Publication (TP) 2839, SWBS 593, Feb 2013, Sewage Holding System

Coast Guard Technical Publication (TP) 4645, Sep 2020, Manufacturer’s Instruction Book—SWBS

Group(s) 593, Vacuum Sewage Collection System

Coast Guard Technical Publication (TP) 4647, Apr 2019, FM/ALCO 251 Engine – Operations and

Maintenance Manual

Coast Guard Technical Publication (TP) 4924, Jun 2019, Section 583-A, Technical Manual for Folding

Boom Crane – Model FB20-21

Coast Guard Technical Publication (TP) 5446, Jan 2016, 270’ WMEC Vacuum Sewage System Control

Panels, Sections A and B

Coast Guard Technical Publication (TP) 5490, SWBS 565, Apr 2018, Fin Stabilizer System

Coast Guard Technical Publication (TP) T9625-AA-MMO-010, May 2014, Window, Electrically

Heated/Deicing

Coast Guard Technical Publication 3910B, April 2020, Air Conditioning System, R-134A S/W Cooled

Chilled – Model 90RMC050-D-610

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2018, Overhaul AC

Electrical Motors

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2018, Shipboard

Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2018, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary

Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2018, Install Interior

Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2018, Temporary

Hull Accesses vii (Rev-0)

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

American Petroleum Institute (API) Standard 527, 5th Edition, July 2020, Seat Tightness of Pressure

Relief Valves

American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and

Welding End

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates

Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone

Manufacturer’s Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP-1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 3, (SSPC-SP-3), 2018, Power Tool Cleaning viii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

1 N MDE JW Seal Kit NSN: 2930-01-602-8570 P/N:

KAM Thermal Equipment

LTD, 10-1AEW SEAL

2 ea. 1,250.00

1 N Red Gear LO cooler parts kit

NSN: 2815-01-682-3386 2 ea. 1,500.00

1 N CPP cooler gasket NSN: 5330-01-115-7912 2 ea. 150.00

1 N CPP cooler gasket NSN: 5330-01-023-7639 2 ea. 150.00

1 N CPP cooler lantern ring NSN: 4320-01-627-3872 2 ea. 450.00

1 N CPP cooler packing ring

NSN: 5330-00-486-2397 4 ea. 150.00

1 N SSDG JW gasket NSN: 5330-01-542-5893 2 ea. 150.00

1 N SSDG JW gasket NSN: 5330-01-546-1720 2 ea. 150.00

1 N SSDG cooler zinc NSN: 2930-00-167-0450 2 ea. 200.00

1 N SSDG cooler pipe plug NSN: 4730-00-163-5756 2 ea. 300.00

1 N EDG JW seal NSN: 5330-00-238-7689 1 ea. 200.00

1 N EDG cooler gasket NSN: 5330-00-237-7874 1 ea. 200.00

1 N EDG cooler gasket NSN: 5330-01-209-2855 1 ea. 300.00

1 N EDG cooler gasket NSN: 5330-01-208-6768 2 ea. 250.00

1 N Fin cooler gasket NSN: 5330-01-622-9908 PN:

00-622-9908

24 ea. 78.00

4 N MDE LO Seal Kit NSN: 2930-01-602-8561 P/N:

KAM Thermal Equipment

LTD, 12-1AEW SEAL

2 ea. 1,250.00

4 N SSDG LO Gasket NSN: 5330-00-128-9755 P/N:

00-128-755

2 ea. 100.00

4 N SSDG LO Gasket NSN: 5330-00-128-9754 P/N:

00-128-9754

2 ea. 100.00

4 N SSDG LO Gasket NSN: 5330-00-122-3951 P/N:

00-122-3951

4 ea. 100.00

4 N SSDG LO Seal NSN: 5330-01-297-1215 P/N:

01-297-1215

4 ea. 100.00

4 N SSDG LO Packing NSN: 5330-00-367-5954 P/N:

00-367-5954

2 ea. 100.00

4 N EDG LO Gasket NSN: 5330-00-936-2162 2 ea. 100.00

4 N EDG LO Packing NSN: 5331-00-663-5075 1 ea. 100.00

4 N EDG LO Gasket NSN: 5330-01-326-7454 2 ea. 100.00

9 Y Appleton FB 20-21

Single Point Davit

NSN: 3950-01-619-5772 1 ea. 86,888.24

9 N Hook, Release NSN: 4030-01-467-1005 1 ea. 4,000.00

10 N Sewage Discharge

Pump

NSN: 4320-01-131-0841 2 ea. 4,719.00 ix (Rev-0)

10 N Sewage Transfer Pump NSN: 4320-01-112-0008 2 ea. 4,719.00

16 N Vacuum sewage control panel

NSN: 4630-01-F12-3000 1 ea. 20,250.00

16 N Sewage holding tank control panel

NSN: 4630-01-F12-2999 1 ea. 13,250.00

16 N Forward grey water control panel

NSN: 4540-01-F12-2998 1 ea. 10,000.00

16 N Aft grey water control panel

NSN: 4540-01-F12-2997 1 ea. 12,500.00

16 N Magnetrol sewage holding tank sensor

NSN: 6680-01-650-1215 1 ea. 4,200.00

22 N Window Assembly, 24 in x 30 in, Clear

Opening

PN: KS-19941-2 6 ea. 5,580.00

22 N PC5 Crank Assembly PN: KS-19940F 2 ea. 1,487.00

22 N Window Assembly, 18 in x 30 in, Clear

Opening

PN: KS-19941-3 1 ea. 4,943.00

22 N Window Controller NSN: 2090-00-475-0142 PN:

KS-12000

9 ea. 612.00

22 N Connector, Ship

Supply to Controller

NSN: 5935-01-602-3125 PN:

KS-24732

18 ea. 50.00

22 N Connector, Controller

Output to Junction Box

NSN: 5935-01-602-3126 PN:

KS-24733

18 ea. 50.00

22 N Connector, Input to

Junction Box

NSN: 5935-01-602-3129 PN:

KS-24735

18 ea. 50.00

22 N Junction Box PN: KS-12000J 11 ea. 295.00

22 N Cable LSTSGU-4, Power Electrical 9Z

NSN: 6145-01-201-9498 200 ft. 1.00

22 N Cable, Power Electrical NSN: 6145-01-201-9495 PN:

LSFHOF-3

200 ft. 1.25

22 N Wiper Controllers PN: KS-9283 10 ea. 613.00

22 N PC 14 Sliding Channel

Felt

PN: KS-19440F 20 ft. 5.25

22 N ½ inch Channel

Glazing Gasket, 12 foot length

PN: 1153 2 ea. 70.00

28 N 4 x 6 231/NP SGL

Arch Nitrile Expansion

Joint

PN: 040X0631P 2 ea. 328.60

28 N Style 481.4 in 150 lb retaining ring

PN: RNG4810400 7 ea. 74.20

28 N Assembly, 491 Limit

Rods

PN: CR491 1 ea. 77.23

28 N 4 x 5 240E/NP SGL

Arch Nitrile Expansion

Joint

PN: 040X0540EP 1 ea. 151.43

28 N 3 x 5 240-E/NP Nitrile with JIS Flanges

PN: 030X0540EP 2 ea. 127.20 x (Rev-0)

28 N 6 x 5 240-E/NP Nitrile

PN: 060X0540EP 1 ea. 245.31

28 N 4 x 6 231/NP SGL

Arch Nitrile Expansion

Joint

PN: 040X0631P 2 ea. 328.60

28 N 231/NP SGL Arch Neo

Cover, Nitrile Tube

Expansion Joint

PN: EJ231 5 ea. 545.13

28 N Style 481.6 in 150 lb retaining ring

PN: RNG4810600 1 ea. 90.86

28 N 3 x 6 231/NP SGL

Arch Nitrile Expansion

Joint

PN: 030X0631P 1 ea. 310.42

28 N Style 481.3 in 150 lb retaining ring

PN: RNG4810300 1 ea. 60.57

28 N 6 x 5 240-E/NP Nitrile

PN: 060X0540EP 1 ea. 245.31 xi (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4

(Inspection report particulars)):

Work

Item Title

11 Grey Water Holding Tank(s), Clean and Inspect

12 Sewage Holding Tank(s), Clean and Inspect

22 Bridge Windows, Renew

26 Deck Covering, Electrical Matting, Renew xii (Rev-0)

PRINCIPAL CHARACTERISTICS

270' WMEC (B-CLASS)

PHYSICAL

Length overall 270' 0"

Length between perpendiculars 255' 0"

Beam molded 38' 0"

Depth molded, main deck amidships, 01 level amidships

23' 7"

31' 4"

Full load displacement 1,886 long tons

Draft, full load to baseline amidships 14' 2"

Highest projection above baseline

*height approximated

≈ 110' 0"

Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase

Frame spacing 1' 0"

MACHINERY

Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,650 BHP each

Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-1350 Generators. 475

KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Number of propellers 2

Propeller diameter 9' 0"

Number of blades, each 4

Pitch Controllable

Shaft RPM 260

Shaft diameter 10.55" at exit of hull

Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each

TANK CAPACITIES

Diesel fuel total (95%) 79,950 gal.

JP-5 total (95%) 19,626 gal.

Potable water total (100%) 8,553 gal.

Hydraulic & lube oil total (95%) 2,561 gal.

1 (Rev-0)

00000_0220_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

2 (Rev-0)

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor shall be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-

Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 shall be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-

130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive testing/inspection (NDT/NDI) in accordance with NAVSEA TP 1688. The Contractor shall be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-

Class” cutters, the Contractor shall provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s shall be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor shall ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

3 (Rev-0)

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in

NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding

Weldox 900 shall be considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Large Quantity

Generator (LQG).

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

4 (Rev-0)

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC Standard Specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:

None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-3A - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

TIME

8 (Rev-0)

QA-3B - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

11 (Rev-0)

25600_0420_210_270_295

REC_25600_210_270_295_270’ WMEC ‘B’ Class (ALL) (0520)

WORK ITEM 1: Seawater Heat Exchangers; Clean, Inspect And Hydro

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following heat exchanger(s):

TABLE 1 – HEAT EXCHANGERS

SYSTEM LOCATION OEM / MODEL QTY

Fin Stabilizer Hydraulic Oil Aux Machry Sp II (3-

82-0-E)

Alfa-Laval, p/n M3-FG 2

SSDG Jacket Water Engine Room (3-103-

0-E)

Caterpillar, p/n 4W4642 2

MDE Jacket Water Engine Room (3-103-

0-E)

KAM Thermal, p/n BEW 12-

EDG Jacket Water Aft Steering (2-229-0-

E)

Caterpillar, p/n 3N-8888

Reduction Gear Lube Oil Engine Room (3-103-

0-E)

IRL Thermal, p/n 44248-5071

CPP Hydraulic Oil Engine Room (3-103-

0-E)

ITT Standard, p/n 5-126-04-036-

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED COST

($/UNIT)

N MDE JW Seal Kit NSN: 2930-01-602-8570

P/N: KAM Thermal

Equipment LTD, 10-1AEW

SEAL

2 ea. 1,250.00

N Red Gear LO cooler parts kit NSN: 2815-01-682-3386 2 ea. 1,500.00

N CPP cooler gasket NSN: 5330-01-115-7912 2 ea. 150.00

N CPP cooler gasket NSN: 5330-01-023-7639 2 ea. 150.00

N CPP cooler lantern ring NSN: 4320-01-627-3872 2 ea. 450.00

N CPP cooler packing ring NSN: 5330-00-486-2397 4 ea. 150.00

N SSDG JW gasket NSN: 5330-01-542-5893 2 ea. 150.00

N SSDG JW gasket NSN: 5330-01-546-1720 2 ea. 150.00

N SSDG cooler zinc NSN: 2930-00-167-0450 2 ea. 200.00

12 (Rev-0)

N SSDG cooler pipe plug NSN: 4730-00-163-5756 2 ea. 300.00

N EDG JW seal NSN: 5330-00-238-7689 1 ea. 200.00

N EDG cooler gasket NSN: 5330-00-237-7874 1 ea. 200.00

N EDG cooler gasket NSN: 5330-01-209-2855 1 ea. 300.00

N EDG cooler gasket NSN: 5330-01-208-6768 2 ea. 250.00

N Fin cooler gasket NSN: 5330-01-622-9908

PN: 00-622-9908

24 ea. 78.00

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 201-001, Rev H, Engine Room Arrangement

Coast Guard Drawing 905 WMEC 256-002, Rev J, Eng Rm SW Cooling Sys A&D

Coast Guard Drawing 905 WMEC 256-008, Rev B, SSDG Modification JW Cooling System

Mod

Coast Guard Drawing 905 WMEC 310-008, Rev B, Emergency Diesel Generator Arrangement &

Details

Coast Guard Drawing 905 WMEC 501-002, Rev C, Aux Mchry Sp No 2 Arrangement

Coast Guard Drawing 905 WMEC 501-003, Rev F, Steering Gear Room Arrangement

Coast Guard Drawing 905 WMEC 517-002, Rev F, Waste Heat Recovery / Ship Service Diesel

Generator Jacket Water – A&D

Coast Guard Drawing 905 WMEC 517-007, Rev B, Main Propulsion Engine Jacket Water

System A&D

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 2815, Oct 2017, Reduction Gear

Coast Guard Technical Publication (TP) 2817, SWBS 245, Section A, Feb 2018, Controllable

Pitch Propeller System

Coast Guard Technical Publication (TP) 2820, May 2017, Ship Service Diesel Generator

Coast Guard Technical Publication (TP) 5490, SWBS 565, Apr 2018, Fin Stabilizer System

Coast Guard Technical Publication (TP) 4647, Apr 2019, FM/ALCO 251 Engine – Operations and Maintenance Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone

13 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Install blanks on the open ends of piping to prevent any contamination or foreign debris from entering the affected systems. Ensure that all cleaning equipment or media used in the cleaning process do not cause any damage to cooler components.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Piping and hoses

Filters

Deck plating and associated framing

Electrical cables

Thermal insulation.

3.2 Fluid disposition, disposal. Dispose of all removed fluids in accordance with all applicable Federal, state, and local regulations.

3.3 Disassemble. The Contractor shall drain and disassemble the designated heat exchangers (see paragraph 1.1 (Intent)) to the extent necessary to perform all work specified herein. The Contractor shall refer to Coast Guard Drawings listed under Section 2 (References) and TPs 5490 (Section titled “Plate

Heat Exchanger – Instruction Manual”), 2820A (Sections E and H), 4647 (Section A), 2815 (Section A) and 2817 (Section A) for guidance.. Perform all disassembly and reassembly in accordance with manufacturer-recommended procedures using manufacturer-recommended tooling to ensure parts are reinstalled in proper sequence and configuration.

3.4 Inspection. Before cleaning is begun, the Contractor shall visually inspect all heat exchanger surfaces for excessive deterioration and any other defects. Submit a CFR.

3.5 Cleaning requirements. The Contractor shall clean all interior and exterior heat transfer surfaces to a state free of all debris, scale and surface contaminants in accordance with the heat exchanger manufacturer’s recommendations, and in compliance with all Federal, state, and local environmental regulations. Ensure that chemical cleaners do not damage the environment, heat exchanger or the vessel.

14 (Rev-0)

Historically, chemical cleaning has been necessary to thoroughly clean most heat exchanger tubes.

3.6 Pipe flushing. The Contractor shall flush all new and disturbed piping with clean fresh water until all debris is removed but no longer than five minutes. Ensure flushing fluid is directed to move scale and foreign debris away from installed machinery to prevent possible damage upon operational testing.

Submit a CFR documenting date and time of flushing process and level of pipe cleanliness.

3.6.1 Dispose of flushing fluid in accordance with all applicable Federal, state, and local regulations.

WARNING

Do not drain any fluids including fresh water, into any space, bilge, or exterior location.

3.7 Reassembly. After authorized repairs, if any, the Contractor shall reassemble each heat exchanger.

3.7.1 Renew all software (seals, gaskets, O-rings, lantern rings).

3.7.2 Renew isolation fittings/mounts and fasteners if disturbed. Apply silicone rubber sealant conforming to CID A-A-59588 around all fasteners, nozzles or gaskets that penetrate the hull.

3.7.3 Renew all hoses, thermostats and anodes as applicable.

NOTE

See related work item “Lube Oil Heat Exchangers; Clean, Inspect And

Hydro” so work can be coordinated to minimize loss/renewal of jacket water.

3.7.4 Refill all heat exchanger fluid levels, including all jacket water in all disturbed engines and piping, in accordance with manufacturer and vessel specifications. Prior to recirculation through the engines, the

Contractor shall test the jacket water for chloride and nitrite concentrations in accordance with manufacturer recommendations in the presence of the Coast Guard Inspector. Submit a CFR.

3.8 Reinstallation. After completion of testing and all authorized repairs, if any, the Contractor shall reinstall each cooler (if previously removed). Where applicable, renew all zinc electrode plates, gaskets, and recessed hex-head bolts in accordance with the manufacturer's specifications. Apply a copper-based anti-seize compound on all bolts, and torque in accordance with manufacturer’s specifications.

3.9 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

3.10 Cleanliness requirement. The Contractor shall visually inspect and ensure that all cleaned surfaces are completely free of debris and surface contaminants. Submit a CFR.

CAUTION

Extreme caution must be taken to not exceed manufacturer’s recommended test pressure during hydrostatic testing.

15 (Rev-0)

3.11 Pressure test. After all authorized work is complete and prior to reconnecting the heat exchanger(s), the Contractor shall pressure test each heat exchanger to the manufacturer’s recommended test pressure in accordance with the applicable Coast Guard drawing listed under Section 2 (References). In the absence of a specified test pressure noted in the Coast Guard drawing, the Contractor shall pressure test each heat exchanger in accordance with paragraph C2.7 (Heat exchangers and fluid coolers) of SFLC Std Spec

5000. Ensure zero leakage from or permanent deformation of pressure-containing parts by repairing all leaks, deformations, and discrepancies. Submit a CFR.

3.12 Label plates. The Contractor shall attach an anodized aluminum test data plate to each heat exchanger using epoxy resin cement. Ensure that each plate is engraved with ¼-inch high letters, stating the following:

Test pressure.

Test date.

Testing facility.

NOTE

If the heat exchanger design makes mounting a test data plate impractical, the

Government reserves the right to request written documentation of the above-listed testing data in lieu of a test data plate, at no additional cost to the

Government.

3.13 Leak test. After reconnecting the heat exchanger(s) on the vessel (and post undocking, if applicable), the Contractor shall perform an operational test of the heat exchanger and associated system piping for one hour using the system fluid at normal operating pressure. Ensure zero visible leakage from or deformation of mechanical parts by repairing all leaks and discrepancies. Submit a CFR.

4. NOTES

4.1 Contractor furnished equipment. The following parts list is provided to assist the Contractor in identifying some of the parts that may be required to accomplish the work detailed above for each fin stabilizer heat exchanger. This list may not reflect the most recent part number changes by the manufacturer; and this list is not fully comprehensive of the parts required to accomplish this work item.

The Contractor shall verify all part numbers and quantities with the manufacturer, prior to ordering. The

Contractor is cautioned to verify the cost of all materials required to complete this work item prior to submitting a bid price.

TABLE 2 – GASKET INFORMATION

ITEM

DESCRIPTION

NSN/PN

QTY (PER

COOLER)

M3 NBR GLUE ON

Channel Plate Gasket

Alpha Laval

P/N: 32263-

0954-6

End Plate Gasket

Alpha Laval

P/N:

3900840171-06

2*

*End plate gasket is a 32263-0954-6 gasket cut in half.

16 (Rev-0)

17 (Rev-0)

25901_0320_FLT

REC_25901_FLT_270 WMEC ‘B’ Class (ALL) (0420)

WORK ITEM 2: Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the Main Diesel Engine

(MDE) exhaust piping system, including the associated stack uptakes.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 162-001, Rev B, Stacks

Coast Guard Drawing 905 WMEC 259-001, Rev D, Diesel Exhaust…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .