Summary
This is a Special Provisions and General Requirements document for the City of Minneapolis Department of Public Works for the 2nd Avenue South Sanitary Sewer Replacement project (CSA00126007D). The project involves replacing approximately 156 linear feet of existing 10-inch by 14.5-inch elliptical cement pipe with 12-inch HDPE pipe using pipe bursting methods. The work is located in 2nd Avenue South between Grant Street and South 12th Street. The contractor will provide pipe bursting work only, while the City will provide remaining work including bursting pits, manhole removal and replacement, service reconnections, pavement and landscaping restoration, sanitary sewer bypass pumping, traffic control, permits, and quality control testing. The construction document is dated March 2026, and the project has been certified by registered professional engineer Bruce Wagener (License No. 21223). Key contact for pre-bid questions is Kimberly Wilson at the Minneapolis Public Service Building, 612-673-2340.
The contract specifies comprehensive requirements for traffic maintenance, ADA compliance, pedestrian access, erosion control, and bypass pumping operations. The contractor must maintain access to residences and apartments throughout construction with limited interruptions, maintain pedestrian crosswalks at intersections, and implement sophisticated flow control systems to prevent sewage discharge. Liquidated damages are assessed at $1,000 per calendar day for failure to meet completion dates. The contractor must secure all necessary permits including utility connections, traffic obstruction permits, erosion control permits, noise permits, and environmental permits. Additionally, the contractor is responsible for providing certified erosion control supervisors, ADA-certified personnel for pedestrian facility construction, and qualified pipe bursting operators with minimum three years of experience and 2,000 feet of prior installations. All work must comply with MnDOT specifications, Minneapolis Public Works Standard Plates, and PROWAG accessibility guidelines.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| BID-PW-Pipe_Bursting___HDPE_Pipe_Installation.pdf | ||
| 2026-04-07_2nd_Ave_S_Sanitary_Sewer_Replacement-_Signed.pdf | ||
| Responsible_Contractor_A1_A2_combined.pdf | ||
| Pipe_Bursting_-_Qualifications_Form_Fillable.pdf | ||
| Call_for_Bids_Event_4127.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Minneapolis Public Works 309 2nd Avenue South
Minneapolis, MN 55421
2nd Ave S Sanitary Sewer Replacement
VOLUME 1
SPECIAL PROVISIONS AND GENERAL REQUIREMENTS
Construction Documents
March 2026
2ND AVE S SANITARY SEWER REPLACEMENT CERTIFICATION
CITY PROJECT NO. CSA00126007D
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000
City of Minneapolis
DEPARTMENT OF PUBLIC WORKS
Special Provisions and General Requirements for
2nd Ave S Sanitary Sewer Replacement
I hereby certify that all other Sections of these Special Provisions were prepared by me, or under my direct supervision, and that I am a duly Registered Professional Engineer under the laws of the State of Minnesota.
Print Name: Bruce Wagener
Signature:
Date: March 24, 2026 License No. 21223
2ND AVE S SANITARY SEWER REPLACEMENT SPECIAL PROVISIONS
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000
Index – Division SP
SCOPE OF WORK
CONTACT INFORMATION
ADDITIONAL INFORMATION
SP-1 WORK SEQUENCE
SP-2 MAINTENANCE DURING CONSTRUCTION
SP-3 (1404 & 2563) MAINTENANCE OF TRAFFIC AND TRAFFIC CONTROL
SP-4 (1408) VALUE ENGINEERING INCENTIVE
SP-5 (1502) PLANS AND WORKING DRAWINGS
SP-6 (1504) COORDINATION OF CONTRACT DOCUMENTS
SP-7 (1508) CONSTRUCTION SURVEYING
SP-8 (1601) SOURCE OF SUPPLY AND QUALITY
SP-9 (1603) MATERIALS: SPECIFICATIONS, SAMPLES, TESTS, AND ACCEPTANCE
SP-10 (1702) PERMITS, LICENSES AND TAXES
SP-11 (1714) RESPONSIBILITY FOR DAMAGE CLAIMS
SP-12 (1717) AIR, LAND AND WATER POLLUTION
SP-13 (1802) QUALIFICATIONS OF WORKERS
SP-14 (1803) PROGRESS SCHEDULES
SP-15 (1804) PROSECUTION OF WORK (ADA)
SP-16 (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME
SP-17 (1807) FAILURE TO COMPLETE WORK ON TIME
SP-18 (1903) COMPENSATION FOR ALTERED QUANTITIES
SP-19 (1905) COMPENSATION FOR ELIMINATED ITEMS
SP-20 (1906) PARTIAL PAYMENTS
SP-21 (1908) FINAL ESTIMATE AND PAYMENT – CONDITIONS AND PROCESS
SP-22 (2021) MOBILIZATION
SP-23 (2031) FIELD OFFICE
SP-24 (2104) REMOVE PAVEMENT & MISCELLANEOUS STRUCTURES
SP-25 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA)
SP-26 (2105) EXCAVATION AND EMBANKMENT
SP-27 (2503) EXCAVATION AND PREPARATION OF TRENCH
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000
SP-28 (2503) SEWER PIPE
SP-29 (2503) RECONNECT SEWER SERVICE
SP-30 (2506) MANHOLES AND CATCH BASINS
SP-31 (2521) DRILL AND GROUT REINF BAR (EPOXY COATED) (ADA) (NOT USED)
SP-32 (2521) CONCRETE WALK (ADA) (NOT USED)
SP-33 (2531) CONCRETE CURB AND GUTTER (NOT USED)
SP-34 (2531) CONCRETE CURB DESIGN V (ADA) (NOT USED)
SP-35 (2531) TRUNCATED DOMES (NOT USED)
SP-36 (2563) TRAFFIC CONTROL SUPERVISOR (NOT USED)
SP-37 (2563) ALTERNATE PEDESTRIAN ROUTE (NOT USED)
SP-38 STORM WATER MANAGEMENT
SP-39 SANITARY SEWER SYSTEM BYPASS PUMPING
SP-40 (2641) SANITARY PIPE REPLACEMENT BY PIPE BURSTING
APPENDICES
Kimberly Wilson Highlight
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 1
DIVISION SP
SPECIAL PROVISIONS AND GENERAL REQUIREMENTS
for
2nd Ave S Sanitary Sewer Replacement
Governing specifications and their order of precedence are as follows:
1. DIVISION SP, SPECIAL PROVISIONS AND GENERAL REQUIREMENTS.
2. DIVISION S, STANDARD SUPPLEMENTAL SPECIFICATIONS FOR THE
CONSTRUCTION OF PUBLIC INFRASTRUCTURE IN THE CITY OF MINNEAPOLIS,
Latest Edition.
3. STANDARD SPECIFICATIONS FOR CONSTRUCTION, State of Minnesota Department of Transportation, Latest Edition, and amendments.
SCOPE OF WORK
The project is located in 2nd Avenue South between Grant Street and South 12th Street. This project involves replacing approximately 156 lf of existing 10-inch by 14.5-inch elliptical cement pipe with 12-inch HDPE by pipe bursting methods. The Contractor shall provide pipe bursting work only.
The City will provide the remainder of the work, including:
1. Pipe bursting pits.
2. Removal and replacement of two sanitary sewer manholes.
3. Reestablishing sanitary pipe and service connections.
4. Removals and site restoration for curb, gutter, pavement, and landscaping.
5. Sanitary sewer bypass pumping.
6. Associated traffic control.
7. Construction Permits.
8. Field quality control, including compaction testing, concrete testing, and asphalt testing.
CONTACT INFORMATION
Questions prior to bidding and regarding bidding shall be directed to:
Kimberly Wilson Public Service Building 505 4th Ave S, Room 310 Minneapolis, MN 55401 612-673-2340 or Email: Kimberly.Wilson@minneapolismn.gov
ADDITIONAL INFORMATION
1. Soil Boring Report, Kilo Engineering, Kilo Project No. 25-943. The report is included in
Appendix A.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 2
SP-1 WORK SEQUENCE
The work shall be staged to minimize disruption to the neighborhood, and the surrounding community.
Contractor shall maintain access to those residences and apartments that enter/exit off of the project corridor throughout construction.
1.01 CONTINUITY OF OPERATIONS
A. The existing storm sewer and sanitary sewer pipes are currently and continuously receiving storm or sanitary flows, and those functions shall not be interrupted except as specified herein. The Contractor shall coordinate the work to avoid any interference with normal operation.
1.02 UNCONTROLLED DISCHARGES
A. Dumping or free flow of sewage on public or private property, gutters, streets, sidewalks, or into storm sewer is prohibited.
B. The bypass pumping plan shall include an emergency response plan to be followed in the event of a failure of the bypass pumping system.
C. In the event an accidental uncontrolled discharge is caused by the Contractor's operations, the Owner shall immediately be entitled to employ others to stop the uncontrolled discharge without giving written notice to the Contractor. Penalties imposed on the Owner as a result of any uncontrolled discharge caused by the actions of the Contractor, his employees, or subcontractors, shall be borne in full by the Contractor, including legal fees and other expenses to the Owner resulting directly or indirectly from the uncontrolled discharge.
1.03 SUBMITTALS
A. In accordance with SP-5 (1502), Plans and Working Drawings, the Contractor shall submit a detailed outage plan and time schedule for operations which will make it necessary to remove pipes or manholes from service. The schedule shall be coordinated with the construction schedule specified in these Special Provisions and the General Conditions of the Contract.
The detailed plan shall describe the Contractor's method for preventing uncontrolled discharge of sanitary sewer flow from all active connections, the length of time required to complete the work along the affected services, and all necessary equipment which the Contractor shall provide in order to prevent uncontrolled discharge.
B. The Contractor shall observe the following restrictions:
1. Pipes shall be isolated, dewatered, in accordance with the detailed outage plan and schedule.
2. The Engineer shall be notified in writing at least two weeks in advance of the planned operation.
1.04 SEQUENCE AND SCHEDULE OF CONSTRUCTION
A. The following specific conditions shall be met:
1. The pipe bursting shall be completed when required by the City. Coordinate pipe bursting work with the City crews who will be providing bursting pits and all other work.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 3
B. Other public and private utility construction may occur simultaneously to the sanitary sewer construction work. Contractor shall coordinate construction efforts with the City and other Contractors throughout the life of the project.
SP-2 MAINTENANCE DURING CONSTRUCTION
This work of this section will be performed by the City even though it refers to the Contractor.
The provisions of Section 1514 of the Standard Specifications for Construction, State of Minnesota
Department of Transportation is amended as follows:
Maintenance during construction shall include street cleaning, snow removal, and dust control.
2.01 STREET CLEANING
A. The Contractor’s requirements for sweeping as required under MnDOT 1514 shall mean that the City Engineer may require additional street sweeping (broom) of the roads adjacent to the project area to provide safe conditions for the traveling public, to prevent environmental damage, to address homeowner concerns, or to comply with local regulatory requirements.
1. Contractor shall supply mechanical street sweeping a minimum of one time per day, or at the direction of the Engineer. Areas for street sweeping shall include all paved areas within the right-of-way where construction is taking place.
B. The Contractor shall maintain drainage for all work sites at all times. When existing drainage facilities are severed or otherwise rendered inoperable, the Contractor shall construct as much of the designed drainage system as may be necessary to maintain adequate drainage.
Temporary grading and/or ditching may also be required to maintain drainage. Any temporary grading and ditching that is required shall be completed as an incidental expense unless it is part of the designed project earthwork. All temporary drainage work shall be completed to the satisfaction of the Engineer.
C. The Contractor shall comply with Erosion Control Specifications and/or with the Erosion Control Plan. That compliance does not relieve the Contractor from their responsibility for cleaning the sewer system should any soil be washed into it.
2.02 DUST CONTROL
A. Dust Control in the Project Area – Maintain all excavations, embankment, stockpiles, access roads, waste areas, borrow areas, and all other work areas or areas adjacent to the work area impacted by the work and within or without the project boundaries free from dust which could cause the standards for air pollution to be exceeded and which would cause a hazard or nuisance to others.
B. Perform dust control operations, in an approved manner, whenever necessary or when directed by the Engineer, even though other work on the project may be suspended. It should be assumed that dust control will be performed, at a minimum, on a weekly basis.
C. Dust control shall be generally accomplished by the use of water.
D. Methods of controlling dust shall meet all air pollutant standards as set forth by Federal and State regulatory agencies.
E. An approved method of stabilization consisting of sprinkling or other similar methods will be permitted to control dust.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 4
F. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor shall have sufficient competent equipment on the job to accomplish this. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs, as determined by the Engineer, even though other work on the project may be suspended.
2.03 SNOW AND ICE REMOVAL
A. Snow and ice removal in the right-of-way of Project Area in each stage currently working in, and those areas that are not able to be plowed by the City due to the Work and as directed by the City – Maintain all excavations, embankment, stockpiles, access roads, plant sites, waste areas, borrow areas, and all other work areas within the project area free of snow and ice both for the performance of the Work as well as for access across approved sections of the work zone by the public.
B. Perform snow and ice removal operations, in an approved manner, whenever necessary or when directed by the Engineer, even though other work on the project may be suspended.
C. Snow shall not be piled on private property. Snow piles shall not impact the travel of the public.
D. If offsite snow disposal is required, it shall be at no additional cost to the City.
2.04 MEASUREMENT AND PAYMENT
A. Maintenance During Construction shall be paid by the Lump Sum and shall be full compensation for all labor, materials, and equipment required to provide street sweeping, dust control, and snow and ice removal for the duration of construction.
SP-3 (1404 & 2563) MAINTENANCE OF TRAFFIC AND TRAFFIC CONTROL
This work of this section will be performed by the City even though it refers to the Contractor.
The provisions of Sections 1404 and 2563 of the Standard Specifications for Construction, State of
Minnesota Department of Transportation are amended as follows:
The Contractor will maintain safe and appropriate accommodations in accordance with the following:
1. For local traffic access to and from driveways, parking lot entrances and exits, delivery zones, and other locations noted in the Staging Plans where access is to be maintained.
2. Pedestrian access crossing each intersection must always be maintained on 3 of the 4 legs of the intersection. If the contractor is unable to provide these crossings, a pedestrian detour shall be added to their traffic control plan for approval by the Engineer.
The Contractor may request exceptions to these requirements (e.g., overnight closures, weekend closures, extension of one-lane traffic impacts, etc.) by providing a minimum of two weeks’ notice to the Engineer and the City of Minneapolis Traffic and Parking Services Division and will be subject to their joint approval. Approval of any modifications to these requirements may include, but not be limited to, the use of additional traffic control devices, advance notification signage, portable changeable message signage, and police officer use. As a condition of any approval, such necessary items will be incidental to the
Lump Sum price for Traffic Control.
The City of Minneapolis Traffic and Parking Services Division oversees permitting requirements for obstruction and lane use permitting. Any roadway drive lane or parking lane closure requires an obstruction permit, which can be obtained online through the City’s permitting program
(https://minneapolis.mn.roway.net/).
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 5
All traffic control devices shall conform and be installed in accordance to:
• the "Minnesota Manual on Uniform Traffic Control Devices" (MN MUTCD);
• Part 6K, "Field Manual for Temporary Traffic Control Zone Layouts" (Field Manual);
• the Speed Limits in Work Zones Guideline
• the Minnesota Flagging Handbook;
• the MnDOT Standard Signs and Markings Manual;
The Contractor shall furnish, install, maintain, and remove all traffic control devices required to provide safe movement of vehicular traffic through the Project during the life of the Contract from the start of
Contract operations to the completion thereof. The Engineer will have the right to modify the requirements for traffic control as deemed necessary due to existing field conditions. The streets shall be kept open to traffic at all times, except as modified below.
Traffic control devices include, but are not limited to, barricades, warning signs, trailers, flashers, cones, and drums, as required and sufficient barricade ballasts to maintain barricade stability. The Lump Sum price for Traffic Control will include all required items to meet the approved traffic control plans.
3.01 SPECIAL PROJECT REQUIREMENTS
A. The staging and traffic control plans included in the Plans are intended to provide general guidance for the Contractor. The Contractor will prepare and submit to the Engineer for review and approval detailed traffic control plans and sign layouts at least 7 days prior to the anticipated installation of traffic control devices for a stage or phase of construction work.
Traffic control plans should include all elements intended to be installed and wording utilized on all signage. Vehicle lane widths and pedestrian access route dimensions, including any driveways or building access points, will also be shown. No work that restricts pedestrians, vehicles, or bicycles will be permitted until the submitted traffic control plans and sign layouts have been approved by the Engineer.
B. The Contractor will notify the Engineer in writing or through a recurring meeting (i.e., a weekly meeting) at least 48 hours prior to the start of any construction operation that will necessitate new or modified sidewalk or lane closure, or internal traffic control signing.
C. Maintaining Pedestrian Access:
1. The Contractor will furnish and install metal pedestrian fence barricades to guide and protect pedestrian movements adjacent to and through work areas. The Contractor will maintain pedestrian crosswalks at all times at all intersections in the project area in accordance with this Specifications unless otherwise approved by the Engineer.
Temporary crosswalk accommodations will be delineated with metal pedestrian fence barricades, signing, temporary striping, or other methods as approved by the Engineer.
Pedestrian fence barricades will be considered incidental to the Lump Sum bid price for Traffic Control.
2. Temporary pedestrian routes will have a minimum of eight feet (8’) of clear width of hard surface unless granted an exception by the Engineer. It will be the Contractor’s responsibility to coordinate the sidewalk removal and reconstruction with affected businesses and property managers and provide a temporary ADA-compliant hard surfaced access route as required. Acceptable temporary surfaces will be constructed of either 1.5” bituminous pavement, temporary wood, plastic, or metal pedestrian plates, or temporary wood or metal pedestrian bridges as approved by the Engineer.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 6
3.02 TRAFFIC CONTROL
A. Where not provided for in the Plan, the Contractor will submit the proposed traffic control layout to the Engineer for approval at least seven (7) days prior to the start of construction where that traffic control layout is instituted. The Contractor does not need to submit layouts that can be found in the Field Manual. All other layouts that are not found in the plan or Field Manual shall be submitted. At least 24 hours prior to placement, all traffic control devices shall be available on the Project for inspection by the Engineer. The Contractor shall modify his/her proposed traffic control layout and/or devices as deemed necessary by the Engineer.
B. The Contractor shall be responsible for the immediate repair or replacement of all traffic control devices that become damaged, moved or destroyed, of all lights that cease to function properly, and of all barricade ballasts that are damaged, destroyed, or otherwise fail to stabilize the barricades. The Contractor shall further provide sufficient surveillance of all traffic control devices at least once every 24 hours.
C. The Contractor shall furnish names, addresses, and phone numbers of at least three (3) individuals responsible for the placement and maintenance of traffic control devices. These individuals shall be "on call" 24 hours per day, seven days per week during the times any traffic control devices, furnished and installed by the Contractor, are in place. The required information shall be submitted to the Engineer at the Preconstruction Meeting. The Contractor shall also furnish the names, addresses, and phone numbers of those individuals to the following.
1. The City of Minneapolis Public Works Department 612-673-5750
2. City of Minneapolis Police Department 612-673-3000
3. City of Minneapolis Fire Department 612-673-3000
4. City of Minneapolis Clerk 612-673-3000
D. The Contractor shall inspect, on a daily basis, all traffic control devices, which the Contractor has furnished and installed, and verify that the devices are placed in accordance with the Traffic Control Layouts, these Special Provisions, and/or the MN MUTCD. Any discrepancy between the placement and the required placement shall be immediately corrected.
E. The Contractor shall be required to respond immediately to any call from the Engineer or his designated representative concerning any request for improving or correcting traffic control devices.
F. The Contractor is required to meet the traffic control device quality standards as determined in the Field Manual. The Contractor shall immediately replace traffic control devices that are deemed unacceptable. Signs that are dirty and result in a noticeable loss of reflectivity at night are also considered unacceptable and shall be cleaned or replaced. The Contractor shall be required to respond immediately to any call from the Engineer or his designated representative concerning the notification of unacceptable traffic control devices.
G. The person performing the inspection in paragraph (C) above shall be required to make a daily log. This log shall also include the date and time any changes in the stages, phases, or portions thereof go into effect. The log shall identify the location and verify that the devices are placed as directed or corrected in accordance with the Plan. All entries in the log shall include the date and time of the entry and be signed by the person making the inspection. The Engineer reserves the right to request copies of the inspection logs, as he deems necessary.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 7
H. The Contractor shall provide copies of the inspection logs on a weekly basis on a day of the week determined by the Engineer. Additionally, the Engineer may request copies of the logs at any time he deems necessary.
I. If, at any time, the Contractor fails to, in a timely manner, properly furnish, install, maintain or remove any of the required traffic control devices, the City reserves the right to correct the deficiency. Each time the City takes such corrective action, the costs thereof, including mobilization, plus $5,000 will be deducted from monies due or coming due the Contractor.
3.03 GENERAL REQUIREMENTS
A. All portable sign assemblies shall be perpendicular to the ground. No roll-up signs will be allowed unless authorized by the Engineer. No traffic control device (signs, channelizing devices, arrow boards, etc.) shall be weighted so they become hazardous to motorists and workers. The approved ballast system for devices mounted on temporary portable supports is sandbags, unless it is designed, crash tested, and approved for the specific device. During freezing conditions, the sand for bags shall be mixed with a deicer to prevent the sand from freezing. The sandbags shall be placed and maintained at the base of the traffic control device to the satisfaction of the Engineer.
When signs will remain in the same location for more than 30 consecutive days the signs shall be post mounted. This would not include portable signs, which are set up and taken down at the beginning and end of each work shift. The signs must be post mounted according to the Typical Temporary Sign Framing and Installation Detail Sheet found in the Plan or in these Special Provisions.
B. When signs are installed, they shall be mounted on posts driven into the ground at the proper height and lateral offset as detailed in the MN MUTCD.
C. All temporary rigid signs shall be fabricated with an approved retroreflective sheeting material of the appropriate color, and be listed under the Approved/Qualified Products List (APL/QPL) for either “Sheeting for Rigid Temporary Work Zone Signs, Delineators, and Markers (Type IX and XI)” or “Sheeting for Rigid Permanent Signs, Delineators, and Markers (Type IX and XI)”. In-place signs that still apply during temporary operations need no change in sign sheeting.
Temporary rigid signs shall have an easily identifiable marking on the face to make the identification of approved retroreflective sign sheeting. This marking verifies that the sign sheeting has been approved for temporary rigid signs. Temporary rigid signs four square feet and less in size, all barricades, and route markers will be exempt from this marking. Refer to the instructions for the marking of temporary signs that are on the APL or directly at the following link: http://www.dot.state.mn.us/products/signing/pdf/typelabel.pdf.
The sheeting materials APL/QPL, including the retroreflective sheeting types, is located at http://www.dot.state.mn.us/products/signing/sheeting.html.
D. At the beginning of the Project, the Contractor shall store at least 10 extra Type III barricades and 20 extra retroreflective drums, at a convenient location within the Project limits, to be used at the discretion of the Engineer. Furnishing and erecting these traffic control devices shall be incidental.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 8
If additional devices, beyond the quantity specified above, are ordered by the Engineer the Contractor will be compensated according to Paragraph 4.11 of this Section.
E. In Place Signing
1. All in place signs and delineators which interfere with the Contractor's normal operation, shall be relocated outside of the work area by the Contractor at the direction of the Engineer. Any signs that are removed and might be reused are to be stored in such a manner as to protect the sign from scratching, fading, or other harmful results until said signs are reinstalled or delivered to the City. Upon completion of work at each sign location, or at the direction of the Engineer, the signs shall be replaced as near to their original locations as possible or to a location designated by the Engineer. Signs and structures damaged by the Contractor shall be replaced by him at his own expense.
Regulatory signs, not otherwise covered by this Contract, may only be removed, replaced, or relocated by City personnel.
2. All costs incurred to relocate, salvage, and reinstall in place signing shall be incidental.
F. The Contractor shall provide protective devices necessary to protect traffic from excavations, drop-offs, falling objects, splatter or other hazards that may exist during construction. This work will be incidental. The Contractor will not be allowed to suspend material, equipment, tools and personnel over traffic unless a lane closure is established below. Lane closures required for protection of traffic from excavations, suspended materials, equipment, tools, and personnel are incidental.
G. The Contractor will not be permitted to park vehicles or construction equipment in a location that obstructs any traffic control device. The parking of workers' private vehicles will not be allowed within the Project limits unless so approved by the Engineer.
H. Where materials or equipment are stored within 30 feet of through traffic, the Contractor shall provide Type B channelizers, barricades or barriers, placed near the object to warn and protect traffic.
I. High Visibility Apparel
1. All workers within the road Right-of-Way who are exposed to either traffic or to construction equipment shall wear reflectorized high-visibility safety apparel.
2. High-visibility safety apparel means personal protective safety clothing that is intended to provide conspicuity during both daytime and nighttime usage and meets the minimum performance Class 2 requirements of the ANSI/ISEA 107 – 2004 publication entitled “American National Standard for High-Visibility Safety Apparel and Headwear”.
3. Additional Requirements: ANSI/ISEA 107-2004 Class 3 Requirements (Class 2 Vest with Class E Long Pants)
a. Flaggers– In addition to an ANSI Class 2 vest, shirt, or jacket, flagger shall wear high visibility Class E long pants and a hat.
b. Nighttime and Low Light Conditions – All workers working at night or in low light conditions shall wear high visibility Class E long pants in addition to an ANSI Class 2 vest, shirt, or jacket and retro-reflective headgear.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 9
4. All high visibility apparel must be worn in the manner for which it was designed. All apparel worn on the torso must be closed in the front to provide contiguous 360-degree visibility. If a worker’s high-visibility apparel becomes faded, worn, torn, dirty, or defaced, reducing the conspicuity of the apparel, the apparel shall be removed from service and replaced with new apparel.
J. Night Work
1. When work will be performed between the official hours of sunset and sunrise, all appropriate practices for night work will apply.
2. The Contractor shall provide sufficient numbers of light plants to illuminate the work area as determined by the Engineer. Light plants required for the illumination of the work area shall be incidental.
3. The Contractor shall provide a sufficient amount of 2-inch wide highly reflective vehicle marking tape to be applied to Contractor vehicles and equipment. This tape shall be incidental and shall be on the Approved Products List for “Conspicuity Vehicle Sheeting (Type VII)” as found at: http://www.dot.state.mn.us/products/signing/sheeting.html.
Vehicle examples to be marked with tape are Contractor rollers, paver, millers and other equipment normally found in the lane closure.
K. On projects requiring drums per MnDOT Standard Plate No. 8000J (Channelizers – Type B), the Contractor shall:
1. Provide all drums with 4-inch sheeting material per the Standard Plate, or
2. Provide all drums with 6-inch fluorescent orange and white sheeting material, with no gap between sheeting layers.
3.04 VEHICLE WARNING LIGHT SPECIFICATION
A. All Contractors, subcontractors' and suppliers' mobile equipment, operating within the limits of the Project with potential exposure to passing traffic, shall be equipped with operable warning lights that meet the appropriate requirements of the SAE specifications. This would include closed roads that are open to local traffic only. This also includes any vehicle that enters the traveled roadway at any time. The SAE specification requirements are as follows:
1. Optical Warning Devices for Authorized Emergency, Maintenance, and Service Vehicles- SAE Specification J845.
2. Directional Flashing Optical Warning Devices for Authorized Emergency, Maintenance, and Service Vehicles - SAE Specification J595.
3. Lights shall be mounted so that at least one light is visible at all times from a height of
3.5 feet and from a 60-foot radius about the equipment. In order to meet the 360 degree at 60-foot radius requirements supplemental lighting may be used. All supplemental lights must be SAE Class 1 certified. This specification is to be used for both day and nighttime operations. All costs incurred to provide warning lights shall be at no cost to the Department. These warning lights shall also be operating and visible when a vehicle decelerates to enter a construction work zone and again when a vehicle leaves the work zone and enters the traveled traffic lane.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 10
3.05 LANE CLOSURE REQUIREMENTS
A. Temporary lane closures or other traffic restrictions by the Contractor, during work hours and consistent with the time restrictions, will be permitted only during those hours and at those locations approved by the Engineer. Requests for temporary lane closures shall be made at least 48 hours prior to the closure. When the Contractor uses a temporary lane closure, the closure shall be incidental work.
B. Unless otherwise approved by the Engineer, any temporary lane closure that is adjacent to traffic, and is extending to or beyond 1,000 feet shall have a minimum of one Type III barricade, or 3 drums, placed in the closed lane for every 1,000 feet of extension. Any lane closure that is adjacent to traffic and in-place 3 days or more, shall use the Type III barricade only.
C. All lane closures shall have Drum (Type B) Channelizers with florescent reflectorized sheeting in the lane closure taper and in any shifts in traffic alignment.
D. Short Term Duration lane closures will not be permitted during inclement weather, rush hour periods, nor any other time when, in the opinion of the Engineer, the lane closure will be a greater than normal hazard to traffic.
3.06 FLAGGER TRAINING AND REQUIREMENTS
A. Any person acting as a flagger on this Project shall have attended a training session taught by a Contractor’s qualified trainer. The Contractor’s qualified trainer shall have completed a “MnDOT Flagger Train the Trainer Session” in the five years before the start date of this Contract and shall be on file as a qualified flagger trainer with the Department. The Flagger Trainer’s name and Qualification Number shall be furnished by the Contractor at the pre-construction meeting. The Contractor shall provide all flaggers with the MnDOT Flagger Handbook and shall observe the rules and regulations contained therein. This handbook shall be in the possession of all flaggers while flagging on the Project. The Contractor shall obtain handbooks from the Department. Flaggers shall not be assigned other duties while working as authorized flaggers. The “Checklist for Flagger training” form shall be furnished to the Engineer any time a new flagger reports to work on the Project. The "Checklist for Flagger Training" form is found at:
http://www.dot.state.mn.us/const/wzs/documents/flaggertrainingchecklist.pdf
B. The Contractor shall furnish Flaggers as required to adequately control traffic. Flaggers shall conform to the requirements set forth in the MN MUTCD. Providing such Flaggers shall be incidental.
C. The Contractor shall provide two-way radios for Flaggers.
D. Flaggers shall wear high visibility retroreflective safety vests, pants and hats at all times while actively flagging on the Project. High visibility apparel shall also comply with current Minnesota OSHA Rules 5207.0100 and 5207.1000.
E. All signs associated with the flagging operation must be removed or covered when flagging operations are not present.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 11
F. The Contractor shall coordinate the flagging operations in a manner that causes as little delay to the traveling public as possible, and at no time shall the delay exceed 5 minutes between the hours of 6 AM and 6 PM, and 10 minutes between the hours of 6 PM and 6 AM. In the event that the Contractor is unable to meet the maximum delay requirements, operations shall shut down until such time a new traffic control plan is developed which does meet the maximum delay requirement.
G. If hauling operations create hazards for the traveling public, the Contractor will be required to provide additional flaggers, as directed by the Engineer. Providing additional flaggers for hauling operations that create hazards for the traveling public shall be incidental.
3.07 MILLING, SEALCOATING, AND PAVING OPERATIONS
A. Traffic will be allowed on milled surfaces; however, the Contractor shall be responsible for furnishing and installing interim striping as directed by the Engineer. Payment for Interim striping will be made as provided for in MnDOT 2580 – Interim Pavement Marking.
B. When traffic is allowed to drive on a milled or uneven surface, the Contractor shall furnish and install "GROOVED PAVEMENT" and "BUMP" signs with "Advisory Speed" plates at locations determined by the Engineer. Payment for these signs shall be incidental to the lump sum payment for traffic control.
C. Any drop-off where traffic will cross from or to the in-place surface, or from or to a milled surface, shall be tapered and/or chamfered so as to provide for the safe passage of traffic.
D. The Contractor shall schedule construction operations to minimize traffic exposure to uneven lanes, milled edges, and edge drop-offs. Only after every attempt has been made to avoid these conditions and one or more of them are deemed necessary, the Contractor shall provide and maintain the appropriate traffic control in accordance with the "DROP OFF GUIDELINES" in the Field Manual.
E. The Contractor shall not mill any notches for surfacing tapers until immediately prior to paving, except that with the Engineer's permission, the Contractor may mill the notches, and install and maintain temporary bituminous tapers to provide for the safe passage of traffic until the surfacing taper is installed.
F. Constructing and milling tapers and/or chamfers shall be incidental.
G. The Contractor shall maintain traffic with a minimum of delay during milling and paving operations at intersections controlled by signals or by all-way stop signs. The Contractor shall provide off-duty police officers, at no expense to the City, to direct and control traffic around and through milling and paving operations at those intersections. "Police officer" means every officer authorized to direct or regulate traffic or to make arrests for violations of traffic rules.
3.08 SIGNAL AND LIGHTING SYSTEMS
A. The Contractor shall not interfere with the operation of any traffic signal system, except as required by the Contract. The Contractor shall notify the Engineer at least 24 hours prior to beginning any work that will interfere with any traffic signal system or its detectors.
B. The in-place signal system(s) shall remain in operation during construction.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 12
3.09 MAINTENANCE AND STAGING OF TRAFFIC CONTROL
A. The Contractor shall maintain, at all times, the existing traffic movements at all intersections.
B. Pedestrian traffic shall be maintained and guided through the Project at all times.
C. The Contractor may request parking restrictions in construction areas and in advance of construction areas as needed. Refer to The City of Minneapolis Traffic and Parking Services Division permitting requirements for obstruction and lane use permitting. Any roadway drive lane or parking lane closure requires an obstruction permit, which can be obtained online through the City’s permitting program (https://minneapolis.mn.roway.net/).
D. The Contractor shall furnish, install, and maintain two "ROAD WORK AHEAD" and one (1) "END ROAD WORK" signs in advance of and beyond each end of the construction limits as directed by the Engineer. The Contractor shall also furnish, install, and maintain one (1) "ROAD WORK AHEAD" sign in advance of the construction limits for each approach leg on all intersecting roads and streets, with additional signs as directed by the Engineer. The signs shall conform to the standards shown in the MN MUTCD. Furnishing and erecting these signs shall be incidental. The signs shall remain the property of the Contractor.
E. The Contractor shall cover all signs that are not consistent with traffic operations. The cover should be a plate of solid material covering the entire legend or all of that part of the legend that is inappropriate. Bolt the cover to the sign and place a minimum of 1/8 inch spacers (such as plastic or rubber) between the sign face and the cover. See the Typical Temporary Sign Framing and Installation Details Sheet found in the Plan or at http://www.dot.state.mn.us/trafficeng/workzone/wz-templets/pdf/layout%2020.pdf for details. This work will be done as required by the Engineer.
F. Street identification signage shall be maintained at all times. Where the only existing signs are small city or county signs located at the intersection, street names and address numbers shall be maintained by temporary installations as required by the Engineer. This is necessary to maintain the 911 emergency system.
G. The Contractor shall maintain a lane width of not less than 12 feet in each direction, unless shown otherwise in the Drawings, and approved by the Engineer. In no case shall traffic be allowed or forced onto the shoulders as a result of the Contractors operations without prior approval of the Engineer.
H. As each road segment is completed, the Contractor shall install the final signing and pavement markings required to safely open that road to traffic. This work shall be completed on or before the date of opening as approved by the Engineer. Overhead signs may be temporarily ground mounted at the Contractor's expense.
3.10 MEASUREMENT AND PAYMENT
A. Traffic control will be measured and paid as follows:
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 13
1. Payment for all traffic control required to complete the Project as shown in the Drawings and specified in these Special Provisions shall be made as a lump sum payment under Item 2563.601 (Traffic Control). Payment includes all costs associated with furnishing, installing, maintaining, relocating and subsequently removing traffic control devices (including flaggers) as required. No additional measurement for payment will be made for individual activities and devices that constitute Traffic Control, except for other traffic control Bid Items specifically provided in the Contract.
2. Traffic Control layouts or devices not shown in the plan or stated in these Special Provisions that are a necessary part of the Contractor’s operations to complete the project as shown in the plan are incidental to the lump sum traffic control item. There will be no increase or decrease in the lump sum payment or additional payment for other traffic control Contract Items, except as provided in Paragraph 4.11 of this Section.
B. Traffic Control Payment Schedule will be as follows:
1. When 5 percent of the Contract amount is earned, 50 percent of the amount bid for traffic control will be paid.
2. When 10 percent, or more, of the Contract amount is earned, an additional 25 percent of the amount bid for traffic control will be paid.
3. When 50 percent, or more, of the Contract amount is earned, an additional 20 percent of the amount bid for traffic control will be paid.
4. The remaining 5 percent bid for traffic control will be paid when all work has been completed and accepted.
3.11 ADDITIONAL TRAFFIC CONTROL DEVICES AND EXTENDED USE OF TRAFFIC
CONTROL DEVICES
A. The City will also use the predetermined prices in Table 2563-1 to pay for (1) additional temporary lane closures for Extra Work; and (2) extended use for all traffic control devices which are impacted by excusable and compensable delays, as defined in MnDOT 1806.2B.
B. The City will not use the predetermined unit prices listed in Table 2563-1 if payment for a device is specifically provided for elsewhere in the Contract.
C. General Requirements:
1. The Contractor must furnish the additional traffic control devices as ordered by the Engineer.
2. The devices installed must meet contract requirements and be in a functional and legible condition as determined in the sole discretion of the Engineer. Devices not meeting these requirements must be immediately replaced or repaired.
D. Measurement:
1. Flashers, barricades, reflectorized drums, portable changeable message signs, 48-inch x 48-inch signs, and flashing arrow boards will be measured by the number of individual units of each type multiplied by the number of Calendar Days each unit is in service.
2. Driven post supports and all mounting hardware for 48-inch x 48-inch signs and Standard Signs are considered incidental.
3. Standard Signs, other than 48 x 48-inch signs, will be measured by the face area of signs furnished multiplied by the number of Calendar Days each square foot of sign is in service.
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 14
4. Standard Signs with Portable Supports will be calculated and paid for as follows: Total Standard Sign Sq. Ft + Portable Support Cost (listed in Table 2563-1) = Standard Signs with Portable Supports Cost per day.
5. Construction Signs - Special will be measured by the sign face area thereof furnished, installed including supports, and removed as specified.
6. Temporary Molded Plastic Barrier and Temporary Concrete Barrier will be measured by the number of linear feet furnished multiplied by the number of Calendar Days each linear foot the barrier is in service.
7. Flaggers and Police Officers will be measured by the number of hours each is in service on the job. Police Officers shall be equipped with a patrol vehicle at all times on the job.
E. Payment:
1. For contracts without a sub-contract agreement for traffic control services; reasonable invoices may be accepted for additional traffic control devices obtained. The reasonableness of the invoice for additional traffic control is subject to audit in accordance with MnDOT 1721.
2. Total compensation for Additional Traffic Control Devices and the Extended Use of Traffic Control Devices will have a maximum payout allowance based on average lifespan as determined by the City.
3. The following devices will have a 180 Day maximum pay out allowance: Reflectorized Cones/Weighted Channelizer Devices, Surface Mounted/Weighted Delineators, Opposing Traffic Lane Divider, Reflectorized Safety Drum, Reflectorized Safety Drum w/Down Arrow, Flasher Type A (Low Intensity), Flasher Type B (High Intensity) and Flasher Type C (Steady Burn).
4. The following devices will have a 365 Day maximum pay out allowance: Type I Barricade, Type II Barricade, Direction Indicator Barricade, Type III Barricade, 48 X 48 Inch Standard Sign, 48 X 48 Inch Standard Sign with Portable Supports, Standard Signs, Standard Signs with Portable Supports, Standard Signs Portable Support Cost per day, Construction Sign - Special, Temporary Plastic Molded Barrier and Temporary Concrete Barrier Energy Absorption End Treatment System.
5. The following devices have a maximum pay out allowance five years or greater:
Temporary Concrete Barrier, Portable Changeable Message Board, Flashing Arrow Board and Portable Radar Trailer.
6. Devices, Flagger and Police Officers:
a. Payment for all additional traffic control devices, Flaggers and police officers, as ordered by the Engineer, will be made in accordance with the following schedule:
Table 2563-1 ADDITIONAL TRAFFIC CONTROL DEVICES, FLAGGERS and POLICE OFFICERS
Item
Number Item Unit
Pre-determined
Price
2563.610 Flagger Hour * 1
2563.610 Police Officer Hour * 2
2563.613 Reflectorized Cones/Weighted Channelizer Devices Each/Day $0.16
2563.613 Surface Mounted/Weighted Delineators Each/Day $0.25
2563.613 Opposing Traffic Lane Divider Each/Day $1.44
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 15
Item
Number Item Unit
Pre-determined
Price
2563.613 Type I Barricade Each/Day $0.34
2563.613 Type II Barricade Each/Day $0.31
2563.613 Direction Indicator Barricade Each/Day $0.46
2563.613 Type III Barricade Each/Day $1.76
2563.613 Reflectorized Safety Drum Each/Day $0.61
2563.613 Reflectorized Safety Drum w/Down Arrow Each/Day $0.75
2563.613 Flasher Type A (Low Intensity) Each/Day $0.29
2563.613 Flasher Type B (High Intensity) Each/Day $0.61
2563.613 Flasher Type C (Steady Burn) Each/Day $0.26
2563.613 48 X 48 Inch Standard Sign Each/Day $0.86
2563.613 48 X 48 Inch Standard Sign W/Port. Sup. Each/Day $1.39
2563.613 Roll up Sign W/Stand Each/Day $1.43
2563.617 Standard Signs
Square
Foot/Day $0.17
2563.613 Standard Signs W/ Portable Supports Each/Day $TBD
Standard Sign Portable Support Cost per day $0.53
2563.618 Construction Sign Special Square Foot $44.09
2563.603 Temporary Plastic Molded Barrier
Linear
Foot/Day $0.29
2563.603 Temporary Concrete Barrier
Linear
Foot/Day $0.05
2563.613 Temp. Concrete Barrier Energy Absorption End Treat. Sys. Each/Day $39.10
2563.613 Portable Changeable Message Board Each/Day $225.00
2563.613 Flashing Arrow Board * 3 Each/Day $7.88
2563.613 Portable Radar Trailer * 3 Each/Day $24.40
*1 When Considered Extra Work, will be paid in accordance with MnDOT 1904.4A.
*2 Shall be paid at the invoice price plus 10% *3 The Contractor shall continually operate each Flashing Arrow Board or Portable Radar
Trailer at maximum legibility.
b. Labor:
1) Payment for labor to furnish, install, and remove additional traffic control devices listed in Table 2563-1 as set forth in C.1 “Devices, Flagger and Police Officers”, will be in accordance with MnDOT 1904.3(4) or 1904.4A.
2) Payment for labor to inspect and maintain additional traffic control devices will be incidental to the 2563.601 (Traffic Control) Item already contained in the Plan during the original contract period, unless a contract revision meets the requirements listed in MnDOT 1402.3.
3) Payment for labor to inspect and maintain all traffic control devices, when an extension of contract time is due to an excusable and compensable delay in accordance with MnDOT 1806.2B, will be in accordance with MnDOT 1904.3(4) or 1904.4A.
c. Equipment:
CITY OF MINNEAPOLIS, MN
TKDA PROJECT NO. 23181.000 PAGE 16
1) Payment for equipment to furnish, install, and remove additional traffic control devices listed in Table 2563-1 as set forth in C.1 “Devices, Flagger and Police Officers”, shall be in accordance with MnDOT 1904.3(4) or 1904.4C.
2) Payment for equipment to inspect and maintain additional traffic control devices will be incidental to the 2563.601 (Traffic Control) Item already contained in the Plan during the original contract period, unless a contract revision meets the requirements listed in MnDOT 1402.3.
3) Payment for equipment to inspect and maintain all traffic control devices, when an extension of contract time is due to an excusable and compensable delay in accordance with MnDOT 1806.2B, will be in accordance with MnDOT 1904.3(4) or 1904.4C.
SP-4 (1408) VALUE ENGINEERING INCENTIVE
Proposals for alternative designs, methods and materials will be considered consistent with MnDOT
Section 1408.
SP-5 (1502) PLANS AND WORKING DRAWINGS
This Section includes the requirements for compiling, processing, and transmitting submittals required for execution of the project.
5.01 SUMMARY
A. Section includes:
1. Submittal procedures.
2. List of subcontractors and suppliers.
3. Schedules of Operation.
4. Schedules of Values.
5. Payment Schedule.
6. Applications for Payment.
7. Shop Drawings and Samples.
8. Schedule of Submittals.
5.02 SUBMITTAL PROCEDURES
A. Schedule submittals to expedite the project and deliver to the appropriate office of the Engineer. Coordinate submission of related items.
B. Transmit each submittal with a cover letter or form, identifying project, contractor, subcontractor, or supplier, pertinent drawing sheet and detail number and specification section number, as appropriate.
C. Electronic files will be acceptable, transmitted via email. Discuss the document distribution pathways with City and Engineer.
D. Apply Contractor's stamp, signed or initialed certifying that review, verification of products required, field dimensions, adjacent construction work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
E. Identify variations from Contract Documents and product or system limitations, which may be detrimental to successful performance of the completed work.