SP4702-18-R-0525 Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to RENOVATE BLDG 11 SECTION 12 FOR DOD OIG, newest first.
File Type Posted
SP470218R0525_Amendment_0001.pdf PDF
SP470218R0525.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP4702-18-R-0525

Amendment 0002

Question #1: RFI 26 response states that Audio Video equipment is not included in the SOW, so Spec Section 27 is not included. Understand that AV equipment is not included, however, DIV 27 covers ALL Communications features of work.

Drawing sheet E-103A Data System Scope states that the contractor is to furnish and install on conduit and cabling for “all data”. Does “all data” refer only to communications (data drops for CAT 6 and DSL as identified on the symbol legend), or does “all data” include conduit and cabling for audio-video components (components/equipment by furnished and installed by government)?

If the E103-A Data System Scope applies only to communication and not A/V conduit or cabling, is there any guiding specification for the communications that the subcontractor should follow?

If by chance there are indeed audio/video conduits/J-boxes or any cabling to be installed by the contractor then please provide proposed AV locations and direction?

Response: The low-voltage plan on sheet E103-A depicts the couple of “A/V” equipment locations where a j-box and conduit are required for television and also security devices. DLA designers were given no guidance on the a/v equipment side of things so they just planned for a j-box and conduit that goes back to the communications closet. The security system requirements and install is to be coordinated with the government security system designer/installer after award per the notes on the drawing. We were not allowed to issue the security drawings for public use prior to award (FOUO).

The information regarding the data/network install is located on sheet E-103B and was provided to DLA by the OIG, if contractors feel that additional information is required we can look into developing a Section 27 specification but what is provided should be enough information to provide a bid package.

Question #2:

Amend 1 Govt Response to RFI No. 2 asked for clarification regarding the location of LEED references in the specs. Answer:

017419-1.7 092900-1.5.1 096500-1.2.3, 2.4 099000-1.2, 3.11

Response:

Revised 01 74 19 attached to amendment – LEED requirement for waste management is valid.

09 29 00 as incorporated in solicitation is valid. LEED as it pertains to manufacturer distance from job site is valid.

Revised 09 65 00 attached to amendment . References to keeping a LEED notebook is deleted. References to VOC content are valid.

09 90 00 I do not see any LEED references in section 3.11.

Question #3: Amend 1 Govt Reponse to RFI No. 5 indicates that the government does require insulation to be fastened with acoustic sealant and states that there is a particular product desired for that application: Please provide the product data on the acoustic sealant which is to be used to “glue” the batt insulation in place to keep it from sliding/settling?

SP4702-18-R-0525

Response:

http://www.ositough.com/content/dam/uac/osi/master/PDFs/TDS/TD-OSI-SC175-Acoustical- Sealant-2018-08-07.pdf

The OSI product will work or an approved equivalent shall be submitted for securing the insulation. The glue is necessary because of the acoustic sound deadening requirements.

Clips/fasteners may be used to ensure the insulation does not sag. To Clarify, Clips/fasteners may be used in addition to the glue/adhesive, but shall not be a substitute

Question #4: Section 07 84 43 - Fire Resistant Joint Sealant: This spec is listed in the RFP TOC but cannot be found in the RFP package, please advise/provide? There is a PDS for 3M Fire Barrier Sealant FD 150+ in the RFP specs binder where 07 84 43 would reside, is the PDS for the 35 FD 150+ intended to be the 07 84 43 spec? Is the 3M FD 150+ supposed to be the acoustic sealant that the government would like the contractor to try to use to glue the in-wall batt insulation to the back of the gypsum board to keep it from sliding/settling?

Response: This product, 3M Fire Barrier Sealant FD 150+, shall be used for wall penetrations where fire walls are present. It is not a substitute for the acoustic adhesive/glue.

Reference on table of contents to specification Section 07 84 43 is erroneous. There is no Section 07 84 43 for this solicitation. PDF for 3M Fire Barrier is intended to be the 07 84 43 spec.

Question #5: Section 26 09 23.00 40 - Lighting Control Devices: This spec is listed in the RFP TOC but cannot be found in the RFP package, please advise/provide?

Response: There is no lighting control device specification required – disregard reference to Section 26 09 23.00 40

Question #6: Regarding Amend 1 Govt Response to RFI No. 18 and revised Technical Quals of Site Staff: May the contractor provide a full time on-site dual role Superintendent/SSHO who has successfully completed the 30-hr OSHA Construction Safety Training w/ 5-years of industry safety & construction experience and a separate dual role Project Manager/CQCM that has 5-years of industry safety & construction experience and has successfully completed the USACE CQMC course who will visit the project site on a routine basis to perform QC inspections (not full time on-site)?

Response: Yes

Question #7: In regards to Amendment 1, question #26 it states Div. 27 is not needed. On sheet E103-B, in the top left corner there are Div. 27 requirements. I just want to clarify that Amendment 1 supersedes the drawing.

Response: The reference to Division 27 specifications on sheet E-103B is in reference to developing the cost estimate and breaking out the electrical costs and the communications systems costs. All work required for this contract is shown on the drawings – all other work required for division 27 work will be performed by others.

SP4702-18-R-0525

Amendment 0002 http://www.ositough.com/content/dam/uac/osi/master/PDFs/TDS/TD-OSI-SC175-Acoustical-Sealant-2018-08-07.pdf http://www.ositough.com/content/dam/uac/osi/master/PDFs/TDS/TD-OSI-SC175-Acoustical-Sealant-2018-08-07.pdf

SECTION 01 74 19 Page 1

SECTION TABLE OF CONTENTS DIVISION

01 - GENERAL REQUIREMENTS SECTION

01 74 19

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

03/18

PART 1 GENERAL

1.1 REFERENCES

1.2 GOVERNMENT POLICY

1.3 MANAGEMENT

1.4 SUBMITTALS

1.5 MEETINGS

1.6 WASTE MANAGEMENT PLAN

1.7 RECORDS

1.8 REPORTS

1.9 COLLECTION

1.9.1 Source Separated Method.

1.9.2 Co-Mingled Method.

1.9.3 Other Methods.

1.10 DISPOSAL

1.10.1 Reuse.

1.10.2 Recycle.

1.10.3 Compost

1.10.4 Waste.

1.10.5 Return

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 74 19 Page 2

SECTION 01 74 19

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

03/18

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED BD+C (2009; R 2010) Leadership in Energy and

Environmental Design(tm) Building Design and Construction (LEED-NC)

LEED GBDC Ref Guide (2009; R 2010) LEED Reference Guide for

Green Building Design, Construction and

Major Renovations of Commercial and

Institutional Buildings including Core &

Shell and K-12 Projects

1.2 GOVERNMENT POLICY

Government policy is to apply sound environmental principles in the design, construction and use of facilities. As part of the implementation of that policy: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. Divert a minimum of 50 percent by weight of total project solid waste from the landfill.

1.3 MANAGEMENT

Develop and implement a waste management program. Take a pro-active, responsible role in the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort. The Environmental Manager, as specified in Section 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS, is responsible for instructing workers and overseeing and documenting results of the Waste Management Plan for the project. Construction and demolition waste includes products of demolition or removal, excess or unusable construction materials, packaging materials for construction products, and other materials generated during the construction process but not incorporated into the work. In the management of waste, consider the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates. Implement any special programs involving rebates or similar incentives related to recycling of waste.

Revenues or other savings obtained for salvage, or recycling accrue to the

Contractor. Appropriately permit firms and facilities used for recycling, reuse, and disposal for the intended use to the extent required by federal, state, and local regulations. Also, provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.

SECTION 01 74 19 Page 3

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Waste Management Plan; G

SD-11 Closeout Submittals

Records; G

Reports; G

1.5 MEETINGS

Conduct Construction Waste Management meetings. After award of the

Contract and prior to commencement of work, schedule and conduct a meeting with the Contracting Officer to discuss the proposed Waste Management Plan and to develop a mutual understanding relative to the details of waste management. The requirements for this meeting may be fulfilled during the coordination and mutual understanding meeting outlined in Section

01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION. At a minimum, discuss environmental and waste management goals and issues at the following additional meetings:

a. Pre-bid meeting.

b. Preconstruction meeting.

c. Regular QC meetings.

d. Work safety meetings.

1.6 WASTE MANAGEMENT PLAN

Submit a waste management plan within 15 days after notice to proceed.

The plan demonstrates how to meet the project waste diversion goal. Also, include the following in the plan:

a. Name of individuals on the Contractor's staff responsible for waste prevention and management.

b. Actions that will be taken to reduce solid waste generation, including coordination with subcontractors to ensure awareness and participation.

c. Description of the regular meetings to be held to address waste management.

d. Description of the specific approaches to be used in recycling/reuse of the various materials generated, including the areas on site and equipment to be used for processing, sorting, and temporary storage of wastes.

e. Characterization, including estimated types and quantities, of the waste to be generated.

SECTION 01 74 19 Page 4

f. Name of landfill and/or incinerator to be used and the estimated costs for use, assuming that there would be no salvage or recycling on the project.

g. Identification of local and regional reuse programs, including non-profit organizations such as schools, local housing agencies, and organizations that accept used materials such as materials exchange networks and Habitat for Humanity. Include the name, location, and phone number for each reuse facility to be used, and provide a copy of the permit or license for each facility.

h. List of specific waste materials that will be salvaged for resale, salvaged and reused on the current project, salvaged and stored for reuse on a future project, or recycled. Identify the recycling facilities by name, location, and phone number, including a copy of the permit or license for each facility.

i. Identification of materials that cannot be recycled/reused with an explanation or justification, to be approved by the Contracting

Officer.

j. Description of the means by which any waste materials identified in item (h) above will be protected from contamination.

k. Description of the means of transportation of the recyclable materials

(whether materials will be site-separated and self-hauled to designated centers, or whether mixed materials will be collected by a waste hauler and removed from the site).

l. Anticipated net cost savings determined by subtracting Contractor program management costs and the cost of disposal from the revenue generated by sale of the materials and the incineration and/or landfill cost avoidance.

Revise and resubmit Plan as required by the Contracting Officer. Approval of Contractor's Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. Distribute copies of the Waste

Management Plan to each subcontractor, the Quality Control Manager, and the

Contracting Officer.

1.7 RECORDS

Maintain records to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration. Keep records in accordance with the LEED GBDC Ref Guide and using the LEED BD+C Letter Template. Quantities must be measured by weight. List each type of waste separately noting the disposal or diversion date. Identify the landfill, recycling center, waste processor, or other organization used to process or receive the solid waste. Provide explanations for any waste not recycled or reused. With each application for payment, submit updated documentation for solid waste disposal and diversion, and submit manifests, weight tickets, receipts, and invoices specifically identifying the project and waste material. Make the records available to the Contracting Officer during construction, and deliver to the Contracting Officer upon completion of the construction a copy of the records.

1.8 REPORTS

Provide quarterly reports and a final report to the Environmental Office, at Defense Supply Center Columbus. Include project name, information for

SP4702-18-R-0525

SECTION 01 74 19 Page 5 waste generated this quarter, and cumulative totals for the project in quarterly and final reports. Also include in each report, supporting documentation to include manifests, weight tickets, receipts, and invoices specifically identifying the project and waste material.

Include timber harvest and demolition information, if any.

1.9 COLLECTION

Separate, store, protect, and handle at the site identified recyclable and salvageable waste products in a manner that maximizes recyclability and salvagability of identified materials. Provide the necessary containers, bins and storage areas to facilitate effective waste management and clearly and appropriately identify them. Provide materials for barriers and enclosures around recyclable material storage areas which are nonhazardous and recyclable or reusable. Locate out of the way of construction traffic.

Provide adequate space for pick-up and delivery and convenience to subcontractors. Recycling and waste bin areas are to be kept neat and clean, and handle recyclable materials to prevent contamination of materials from incompatible products and materials. Clean contaminated materials prior to placing in collection containers. Use cleaning materials that are nonhazardous and biodegradable. Handle hazardous waste and hazardous materials in accordance with applicable regulations and coordinate with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

Separate materials by one of the following methods:

1.9.1 Source Separated Method.

Separate waste products and materials that are recyclable from trash and sorted as described below into appropriately marked separate containers and then transported to the respective recycling facility for further processing. Deliver materials in accordance with recycling or reuse facility requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process).

Separate materials into the following category types as appropriate to the project waste and to the available recycling and reuse programs in the project area:

a. Land clearing debris.

b. Asphalt.

c. Concrete and masonry.

d. Metal (e.g. banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized, stainless steel, aluminum, copper, zinc, lead brass, bronze).

(1) Ferrous.

(2) Non-ferrous.

e. Wood (nails and staples allowed).

SECTION 01 74 19 Page 6

f. Debris.

g. Glass (colored glass allowed).

h. Paper.

(1) Bond.

(2) Newsprint.

(3) Cardboard and paper packaging materials.

i. Plastic.

Type

1 Polyethylene Terephthalate (PET, PETE)

2 High Density Polyethylene (HDPE)

3 Vinyl (Polyvinyl Chloride or PVC)

4 Low Density Polyethylene (LDPE)

5 Polypropylene (PP)

6 Polystyrene (PS)

7 Other. Use of this code indicates that the package in question is made with a resin other than the six listed above, or is made of more than one resin listed above, and used in a multi-layer combination.

j. Gypsum.

k. Non-hazardous paint and paint cans.

l. Carpet.

m. Ceiling tiles.

n. Insulation.

o. Beverage containers.

1.9.2 Co-Mingled Method.

Place waste products and recyclable materials into a single container and then transport to a recycling facility where the recyclable materials are sorted and processed.

1.9.3 Other Methods.

Other proposed methods may be used when approved by the Contracting

Officer.

SP4702-18-R-0525

SECTION 01 74 19 Page 7

1.10 DISPOSAL

Control accumulation of waste materials and trash. Recycle or dispose of collected materials off-site at intervals approved by the

Contracting Officer and in compliance with waste management procedures.

Except as otherwise specified in other sections of the specifications, dispose of in accordance with the following:

1.10.1 Reuse.

Give first consideration to salvage for reuse since little or no re-processing is necessary for this method, and less pollution is created when items are reused in their original form. Coordinate reuse with the Contracting Officer. Consider sale or donation of waste suitable for reuse.

1.10.2 Recycle.

Recycle waste materials not suitable for reuse, but having value as being recyclable. Recycle all fluorescent lamps, HID lamps, and mercury-containing thermostats removed from the site. Arrange for timely pickups from the site or deliveries to recycling facilities in order to prevent contamination of recyclable materials.

1.10.4 Waste.

Dispose of materials with no practical use or economic benefit to waste-to-energy plants where available. As the last choice, dispose of materials at a landfill or incinerator.

1.10.5 Return

Set aside and protect misdelivered and substandard products and materials and return to supplier for credit.

Not used.

Not used. -- End of Section --

Section 09 65 00 Page 1

SECTION 09 65 00

RESILIENT FLOORING

08/10

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D4078 (2002; R 2008) Water Emulsion Floor Polish

ASTM E648 (2010e1) Standard Test Method for Critical

Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source

ASTM F1066 (2004e1; R 2010) Standard Specification for

Vinyl Composition Floor Tile

ASTM F1482 (2004; R 2009e1) Installation and Preparation of Panel Type Underlayments to Receive Resilient Flooring

ASTM F1861 (2008) Resilient Wall Base

ASTM F1869 (2011) Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride

ASTM F2170 (2011) Determining Relative Humidity in

Concrete Floor Slabs in situ Probes

ASTM F710 (2011) Standard Practice for Preparing

Concrete Floors to Receive Resilient Flooring

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED GBDC (2009) LEED Reference Guide for Green

Building Design and Construction

LEED NC (2009) Leadership in Energy and Environmental

Design(tm) New Construction Rating System

1.2 SYSTEM DESCRIPTION

1.2.1 Local/Regional Materials

Use materials or products extracted, harvested, or recovered, as well as manufactured, within a 500 mile radius from the project site, if available

SP4702-18-R-0525

Section 09 65 00 Page 2 from a minimum of three sources. Flooring and accessories may contain post-consumer or post-industrial recycled content.

1.2.2 Fire Resistance Requirements

Provide a minimum average critical radiant flux of 0.22 watts per square centimeter for flooring in corridors and exits when tested in accordance with ASTM E648.

1.2.3 Other Submittal Requirements

The following shall be submitted in accordance with LEED NC:

d. documentation relative to local/regional materials credit in accordance with LEED GBDC.

e. documentation relative to recycled content credit in accordance with

LEED GBDC.

f. documentation relative to low-emitting materials credit in accordance with LEED GBDC.

g. documentation relative to rapidly renewable materials credit in accordance with LEED GBDC.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Resilient Flooring and Accessories; G

SD-03 Product Data

Adhesives

SD-04 Samples

SD-06 Test Reports

Moisture, Alkalinity and Bond Tests; G

SD-08 Manufacturer's Instructions

Surface Preparation; G Installation; G

SD-10 Operation and Maintenance Data

Amendment 0002 file://USE.AD.DLA.MIL/DATA1/INSTSVCS/WB/WBC/SISGML/JOBS/CSC12794/prntdata/word/01%2033%2000.doc

Section 09 65 00 Page 3

SD-11 Closeout Submittals

Local/Regional Materials Resilient Flooring and Accessories Adhesives

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver materials to the building site in original unopened containers bearing the manufacturer's name, style name, pattern color name and number, production run, project identification, and handling instructions. Store materials in a clean, dry, secure, and well-ventilated area with ambient air temperature maintained above 68 degrees F and below 85 degrees F, stacked according to manufacturer's recommendations. Protect materials from the direct flow of heat from hot-air registers, radiators and other heating fixtures and appliances. Observe ventilation and safety procedures specified in the MSDS.

1.5 ENVIRONMENTAL REQUIREMENTS

Maintain areas to receive resilient flooring at a temperature above 68 degrees F and below 85 degrees F for 3 days before application, during application and 2 days after application, unless otherwise directed by the flooring manufacturer for the flooring being installed. Maintain a minimum temperature of 55 degrees F thereafter. Provide adequate ventilation to remove moisture from area and to comply with regulations limiting concentrations of hazardous vapors.

1.6 SCHEDULING

Schedule resilient flooring application after the completion of other work which would damage the finished surface of the flooring.

1.7 WARRANTY

Provide manufacturer's standard performance guarantees or warranties that extend beyond a one year period.

1.8 EXTRA MATERIALS

Provide extra flooring material of each color and pattern at the rate of 5 tiles for each 1000 tiles installed. Provide extra wall base material composed of 20 linear feet of each type, color and pattern. Package all extra materials in original properly marked containers bearing the manufacturer's name, brand name, pattern color name and number, production run, and handling instructions. Provide extra materials from the same lot as those installed. Leave extra stock at the site in location assigned by Contracting Officer.

Section 09 65 00 Page 4

2.1 VINYL COMPOSITION TILE

Conform to ASTM F1066 Class 1, (solid color tile), Class 2, (through pattern tile), Composition 1, asbestos-free, 12 inch square and 1/8 inch thick.

Provide color and pattern uniformly distributed throughout the thickness of the tile.

2.2 WALL BASE

Conform to ASTM F1861, Type TS (vulcanized thermoset rubber) or Type TP (thermoplastic rubber), or Type TV (thermoplastic vinyl), Style B (coved -installed with resilient flooring). Provide 6 inch high and a minimum 1/8 inch thick wall base. Provide preformed corners in matching height, shape, and color. Rubber shall contain a minimum of 90 percent post-consumer recycled material.

2.3 MOULDING

Provide tapered mouldings of vinyl or rubber and types as recommended by flooring manufacturer for both edges and transitions of flooring materials specified. Provide vertical lip on moulding of maximum 1/4 inch. Provide bevel change in level between 1/4 and 1/2 inch with a slope no greater than 1:2.

2.4 ADHESIVES

Provide adhesives for flooring, base and accessories as recommended by the manufacturer and comply with local indoor air quality standards. Interior adhesives shall meet the requirements of LEED low emitting materials credit.

Submit manufacturer's descriptive data, documentation stating physical characteristics, and mildew and germicidal characteristics. Provide Material Safety Data Sheets (MSDS) for all primers and adhesives to the Contracting Officer or designee. Highlight VOC emissions.

2.5 SURFACE PREPARATION MATERIALS

Provide surface preparation materials, such as panel type underlayment, lining felt, and floor crack fillers as recommended by the flooring manufacturer for the subfloor conditions. Comply with ASTM F1482 for panel type underlayment products.

2.6 POLISH/FINISH

Provide polish finish as recommended by the manufacturer and conform to ASTM D4078 for polish.

2.7 CAULKING AND SEALANTS

Provide caulking and sealants in accordance with Section 07 92 00 JOINT

SEALANTS.

2.8 MANUFACTURER'S COLOR, PATTERN AND TEXTURE

Provide color, pattern and texture for resilient flooring and accessories selected from manufacturer's standard colors. Provide flooring in any one continuous area or replacement of damaged flooring in continuous area from

SP4702-18-R-0525

Amendment 0002 file://USE.AD.DLA.MIL/DATA1/INSTSVCS/WB/WBC/SISGML/JOBS/CSC12794/prntdata/word/07%2092%2000.doc

Section 09 65 00 Page 5 same production run with same shade and pattern. Submit scaled drawings indicating patterns (including location of patterns and colors) and dimensions. Submit manufacturer's descriptive data and three samples of each indicated color and type of flooring, base, mouldings, and accessories sized a minimum 2-1/2 by 4 inch. Submit Data Package 1 in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA.

3.1 EXAMINATION

Examine and verify that site conditions are in agreement with the design package. Report all conditions that will prevent a proper installation. Do not take any corrective action without written permission from the Government. Work will proceed only when conditions have been corrected and accepted by the installer. Submit manufacturer's printed installation instructions for all flooring materials and accessories, including preparation of substrate, seaming techniques, and recommended adhesives.

3.2 SURFACE PREPARATION

Provide a smooth, true, level plane for surface preparation of the flooring, except where indicated as sloped. Floor to be flat to within 3/16 inch in 10 feet. Prepare subfloor in accordance with flooring manufacturer's recommended instructions. Prepare the surfaces of lightweight concrete slabs (as defined by the flooring manufacturer) as recommended by the flooring manufacturer. Comply with ASTM F710 for concrete subfloor preparation. Floor fills or toppings may be required as recommended by the flooring manufacturer. Install underlayments, when required by the flooring manufacturer, in accordance with manufacturer's recommended printed installation instructions. Comply with ASTM F1482 for panel type underlayments. Before any work under this section is begun, correct all defects such as rough or scaling concrete, chalk and dust, cracks, low spots, high spots, and uneven surfaces. Repair all damaged portions of concrete slabs as recommended by the flooring manufacturer. Remove concrete curing and sealer compounds from the slabs, other than the type that does not adversely affect adhesion. Remove paint, varnish, oils, release agents, sealers, waxes, and adhesives, as required by the flooring product in accordance with manufacturer's printed installation instructions.

3.3 MOISTURE, ALKALINITY AND BOND TESTS

Determine the suitability of the concrete subfloor for receiving the resilient flooring with regard to moisture content and pH level by moisture and alkalinity tests. Conduct moisture testing in accordance with ASTM F1869 or ASTM F2170, unless otherwise recommended by the flooring manufacturer. Conduct alkalinity testing as recommended by the flooring manufacturer. Determine the compatibility of the resilient flooring adhesives to the concrete floors by a bond test in accordance with the flooring manufacturer's recommendations. Submit copy of test reports for moisture and alkalinity content of concrete slab, and bond test stating date of test, person conducting the test, and the area tested.

3.4 PLACING VINYL COMPOSITION, LINOLEUM AND SOLID VINYL TILES

file://USE.AD.DLA.MIL/DATA1/INSTSVCS/WB/WBC/SISGML/JOBS/CSC12794/prntdata/word/01%2078%2023.doc

Section 09 65 00 Page 6

Install tile flooring and accessories in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's directions. Keep tile lines and joints square, symmetrical, tight, and even. Keep each floor in true, level plane, except where slope is indicated. Vary edge width as necessary to maintain full-size tiles in the field, no edge tile to be less than one-half the field tile size, except where irregular shaped rooms make it impossible.

Cut flooring to fit around all permanent fixtures, built-in furniture and cabinets, pipes, and outlets. Cut, fit, and scribe edge tile to walls and partitions after field flooring has been applied.

3.5 PLACING MOULDING

Provide moulding where flooring termination is higher than the adjacent finished flooring and at transitions between different flooring materials.

When required, locate moulding under door centerline. Moulding is not required at doorways where thresholds are provided. Secure moulding with adhesive as recommended by the manufacturer. Prepare and apply adhesives in accordance with manufacturer's printed directions.

3.6 PLACING WALL BASE

Install wall base in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's printed directions. Tighten base joints and make even with adjacent resilient flooring. Fill voids along the top edge of base at masonry walls with caulk. Roll entire vertical surface of base with hand roller, and press toe of base with a straight piece of wood to ensure proper alignment.

Avoid excess adhesive in corners.

3.7 CLEANING

Immediately upon completion of installation of flooring in a room or an area, dry/clean the flooring and adjacent surfaces to remove all surplus adhesive. Clean flooring as recommended in accordance with manufacturer's printed maintenance instructions. No sooner than 5 days after installation, wash flooring with a nonalkaline cleaning solution, rinse thoroughly with clear cold water, and, except for rubber flooring and stair treads, risers and stringers, vinyl and other flooring not requiring polish finish by manufacturer, apply the number of coats of polish in accordance with manufacturer's written instructions. Clean and maintain all other flooring as recommended by the manufacturer.

3.8 WASTE MANAGEMENT

Separate offcuts and waste materials and reuse or recycle in accordance with the Waste Management Plan, keeping sheet materials larger than 2 square feet and tiles larger than 1/2 tiles separate for reuse. Identify manufacturer's policy for collection or return of construction scrap, unused material, demolition scrap, and/or packaging material. Place materials defined as hazardous or toxic waste in designated containers and dispose of properly.

Close and seal tightly partly used sealant and adhesive containers and store protected in a well ventilated fire-safe area at moderate temperature.

Section 09 65 00 Page 7

3.9 PROTECTION

From the time of installation until acceptance, protect flooring from damage as recommended by the flooring manufacturer. Remove and replace flooring which becomes damaged, loose, broken, or curled and wall base which is not tight to wall or securely adhered.

-- End of Section --

img-906093307-0001
questions and responses
UFGS 01 74 19 Construction and Demolition Waste Management
09 65 00 Resilient Flooring
PART 1 GENERAL
1.1 REFERENCES
1.2 SYSTEM DESCRIPTION
1.2.1 Local/Regional Materials
1.2.2 Fire Resistance Requirements
1.2.3 Other Submittal Requirements
1.3 SUBMITTALS
1.4 DELIVERY, STORAGE, AND HANDLING
1.5 ENVIRONMENTAL REQUIREMENTS
1.6 SCHEDULING
1.7 WARRANTY
1.8 EXTRA MATERIALS
PART 2 PRODUCTS
2.1 VINYL COMPOSITION TILE
2.2 WALL BASE
2.3 MOULDING
2.4 ADHESIVES
2.5 SURFACE PREPARATION MATERIALS
2.6 POLISH/FINISH
2.7 CAULKING AND SEALANTS
2.8 MANUFACTURER'S COLOR, PATTERN AND TEXTURE
PART 3 EXECUTION
3.1 EXAMINATION
3.2 SURFACE PREPARATION
3.3 MOISTURE, ALKALINITY AND BOND TESTS
3.4 PLACING VINYL COMPOSITION, LINOLEUM AND SOLID VINYL TILES
3.5 PLACING MOULDING
3.6 PLACING WALL BASE
3.7 CLEANING
3.8 WASTE MANAGEMENT
3.9 PROTECTION