SP4702-21-R-0010.pdf

PDF 3 MB Posted

Attached to
Project: CSC-20001 Safety Improvements, FY21 Federal contract opportunity
Solicitation number
SP4702-21-R-0010
Issued by
Defense Logistics Agency

View the file

Other files for this federal contract opportunity

Other files attached to Project: CSC-20001 Safety Improvements, FY21, newest first.
File Type Posted
Continue sheet SF30 Amendment 01.pdf PDF
Questions Answers for CSC-20001.pdf PDF
Amendment 01-SP4702-21-R-0010-SF30.pdf PDF
Attachment 3-DSCC Excavation Permit.pdf PDF
Attachment 1-CSC-20001 Wage Rate.pdf PDF
Attachment 5-CSC-20001 BID FORM.xlsx XLSX spreadsheet
Attachment 2-ENG FORM 93.pdf PDF
Attachment 6-ENG FORM 4025-R.pdf PDF
Attachment 4-Drawings for CSC-20001 SAFETY IMPROVEMENTS 3-1699.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

CODE 8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

SP4702-21-R-0010

DLA CONTRACTING SERVICES OFFICE, COLUMBUS

ATTN: DCSO-C

P. O. Box 3990 Columbus, OH 43218-3990

SEE TABLE OF CONTENTS PAGE 3 0F 217

DEFENSE SUPPLY CENTER, COLUMBUS

ATTN: DCSO-C

P. O. Box 3990 Columbus, OH 43218-3990 For Courier Services, offers must be address to:

3990 East Broad Street, Columbus, OH 43213-1152.

5. REQUISITION/PURCHASE REQUEST NUMBER

88064377

SP4702

William M. Hurley 614-692-0439

6. PROJECT NUMBER

CSC-20001

1 21705/28/2021 local time 06/30/2021

1:00 PM

(See Clause (FAR 52.211-10

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

TABLE OF CONTENTS

SECTION A. . . . . . . . . . Solicitation/Table of Contents – STANDARD FORM 1442

SECTION B. . . . . . . . . . Supplies or Services and Prices

SECTION C. . . . . . . . . . Descriptions/Specifications/Performance Work Statement

SECTION D. . . . . . . . . . Packaging and Marking

SECTION E. . . . . . . . . . Inspection and Acceptance

SECTION F. . . . . . . . . . Deliveries or Performance

SECTION G. . . . . . . . . Contract Administration Data (Not Applicable). . . . . . . . . . . . . . . . . . N/A

SECTION H. . . . . . . . . Special Contract Requirements

SECTION I. . . . . . . . . . Contract Clauses

SECTION J. . . . . . . . . . List of Documents, Exhibits, and Other Attachments (Not Applicable).

SECTION K. . . . . . . . . Representations, Certifications, and Other Statements of Offerors. . 195

SECTION L. . . . . . . . . . Instructions, Conditions and Notices to Offerors

SECTION M. . . . . . . . . Evaluation Factors for Award

Attachment 1 DOL Wage Rate Determination

Attachment 2 Eng. Form 93 dated 2014 March (2 Pages)

Attachment 3 Excavation Permit

Attachment 4 Drawings Reference 3-1699, (15 Sheets)

Attachment 5 Construction Cost Estimate

Attachment 6 Eng. Form 4025-R

N/A

SP4702-21-R-0010 CSC-20001

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

DESCRIPTION OF SERVICES

The contractor shall furnish all plant, labor, equipment, materials, supplies, testing and supervision required in performing all operations in conjunction with this project in strict accordance with the specifications (CSC-20001 Safety Improvements), contract drawing Drawings 3-1699 (15 Sheets), complete and subject to the terms and provisions of this contract. Contractor shall perform the following work to complete this project.

TERM OF CONTRACT

The period of performance for this project is 120 calendar days after the issuance of the Notice to Proceed.

OFFER FOR SERVICES

CONRACT

LINE TEM

NO.(CLIN)

SUPPLIES/SERVICES QUANTITY UNIT TOTAL AMOUNT

0001 CSC-20001 Safety Improvements, FY21

1 JOB $

ALL CLIN PRICING SHALL BE INCLUSIVE OF OVERHEAD, PROFIT AND BONDING COSTS

Note 1: The offeror shall complete the following columns on this page: Unit Price and Total Amount.

All costs, including bid bond, overhead and profit shall be included in the Total Amount.

Note 2: The offeror shall accept any amendments generated from this solicitation and shall complete the Construction Cost Estimate Form as part of its proposal submission, in order to be considered complete. Incomplete proposals will not be considered technically acceptable.

Note 3: As stated in clause 52.236-27, there will be a site visit on June 08, 2021 at 09:00 AM local time. Attendance at this site visit is optional for any contractor wishing to submit an offer in response to this solicitation. Please see clause for details.

Note 4: Quantity and unit price (Section B) will be flipped at the award stage for invoicing purposes.

When invoicing in Wide Area Work Flow, reverse the quantity and unit price as shown above on each CLIN. Failure to do so will result in a delay in payment of the invoice as the invoice will have to be rejected and resubmitted. If you have any questions regarding this matter, contact your WAWF representative

Under the authority of FAR Part 16.2, the DLA Contracting Services Office – Columbus intends to award a Firm Fixed Price contract for construction services to repair and seal interior concrete floors within Buildings 9 and 30 on the Defense Supply Center Columbus (DSCC) in Columbus, Ohio.

FAR Part 36 “Construction and Architect – Engineer Contracts” and FAR Part 15 “Contracting by Negotiation” procedures and regulations will be utilized.

POINTS OF CONTACT FOR THIS PROJECT/ACQUISITION

Acquisition Specialist/Officer: William M. Hurley

BLDG 20,

3990 E Broad Street Columbus, OH 43218-3990

(614) 692-0439 william.hurley@dla.mil

Project Manager: M. Rustam Ali BLDG 308 3990 E Broad Street Columbus, OH 43218-3990 mohammad.ali@dla.mil

Contracting Officer Representative: John Patrick

BLDG 308

3990 E Broad Street Columbus, OH 43218-3990

(614) 692-3645 John.Patrick@dla.mil

ASSISTANCE IN SUBMITTING DOCUMENTS/INVOICES INTO THE WIDE AREA WORKFLOW

(WAWF)

If you need instruction on how to submit an invoice to the Government in WAWF, follow the below instructions. It is not necessary to log into WAWF to access the training.

1. Click on the Help/Training folder located on the top right hand corner WAWF home page.

https://wawf.eb.mil/xhtml/unauth/home/login.xhtml#

2. Go to Training

3. Click on Web based Training

4. Click on iRAPT

5. Go to Roles and click on vendor

6. Click Vendor creating documents in iRAPT

7. Under Document, Scroll down through the documents list and selected the document you wish to learn about. In this case the document you should select is The 2 in 1 (Services Only).

You find both a video and step by step instructions on how to complete any the form and be able to submit your invoice into WAWF.

After reviewing this information and you are still having problems, you can call the Defense Finance and Accounting Services (DFAS) Help Desk at 1-800-756-4571 Prompt 2. Their hours of operation are between 7:30 AM to 4:30 PM; Monday to Friday Eastern Standard Time.

Assistance may also be available to assist in the submission of the invoice by contacting the Procurement Technical Assistance Center (PTAC) office located in your State. There is an office for your county. Their website for further information is:

http://www.dla.mil/HQ/SmallBusiness/PTAC.aspx#DDL_Lines mailto:william.hurley@dla.mil mailto:mohammad.

mailto:ali@dla.mil mailto:matthew.foreman@dla.mil http://www.dla.mil/HQ/SmallBusiness/PTAC.aspx#DDL_Lines

(X) 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995), ALT I (FEB 1995) - FAR

(a) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Offerors are invited to attend an organized site visit by reporting to the Facilities Engineer, Building 308, Defense Supply Center (DSCC), Columbus, Ohio on 8th of June 2021(date), at 09:00 AM (time).

LIST OF ACCEPTABLE ID FOR VISITOR PROCESSING

The following forms of ID are acceptable for visitor processing and access to enter the DSCC. Any two forms below can be used to meet the new Visitor Policy for access.

1. Federally-issued Identification.

a. U.S. Passport.

b. U.S. Passport Card.

c. PIV or Federally-issued Personal Identification Verification – Interoperable (PIV-I) Cards.

d. Driver’s License issued by the U.S. Department of State.

e. Border Crossing Card (Form DSP-150).

f. DHS “Trusted Traveler” Cards (Global Entry, NEXUS, SENTRI, FAST).

g. U.S. Military ID (all members of the U.S. Armed Forces [including retirees and dependent ID card holders]) and veterans.

h. Veterans Health Identification Card issued by the U. S. Department of Veterans Affairs.

i. U.S. Permanent Resident Card (Form I-551).

j. U.S. Certificate of Naturalization or Certificate of Citizenship (Form N-550).

k. Employment Authorization Document issued by DHS (Form I-766).

l. U.S. Refugee Travel Document or other travel document or evidence of immigration status issued by DHS containing a photograph (Permit to Re-enter Form I-327 and Refugee Travel Document Form I-571).

m. Transportation Worker Identification Credential (TWIC).

n. Merchant Mariner Card issued by DHS/United States Coast Guard (USCG).

2. State-issued Identification.

a. A driver’s license or identification card issued by a state that meets the REAL ID standards or has an extension.

b. State-issued Enhanced Drivers Licenses (EDLs).

c. Interim Driver’s License6 issued by a state that meets the REAL ID standards or has an extension.

3. Other

a. Native American Tribal Photo ID.

b. Foreign government-issued passport.

c. PIV-I cards (issued by non-Federal Government entities).

REAL ID ACT

Information on the REAL ID Act of 2005 and a current compliance status list of States/Territories can be found at https://www.dhs.eov/current-status-states-territories.

All visitors and delivery truck drivers must be identity proofed in accordance with DSCCM 5720.003, Access Control, before they can access DSCC. The REAL ID Act identifies which driver licenses can be used for identity proofing individuals that are requesting access. Individuals from compliant States will be processed as normal. Individuals from non-compliant States will be processed as http://www.dhs.eov/current-status-states-territories normal if they can also produce one of the alternate forms of identification listed in the below section titled, “LIST OF ALTERNATE FORMS OF IDENTIFICATION.”

If a visitor or delivery truck driver presents a non-compliant driver license AND cannot produce an identifying document listed in the below section, then the following procedures will be followed:

1. Visitor: DSCC Visitor Control Center (VCC) personnel will conduct a law enforcement background check using the visitor's driver license. Visitors presenting a driver license from a non-compliant state, if not entered in Visitor Notification System (VNS), will be turned away. If entered into VNS and cleared, VCC personnel will contact the visitor's sponsor listed in VNS and the sponsor will meet them at the Visitor Control Center (VCC) Building 61 where they will verify the visitor to VCC personnel. At that time a visitor DBIDS pass will be issued. The sponsor escorts the visitor in buildings for the duration of time they are on DSCC.

2. Delivery Truck Driver: Delivery truck drivers will be processed IA W DSCCM 5730.003, Enclosure 9, Delivery Control at the James Road Gate inspection area. Truck drivers presenting a driver license from a non-compliant state, if not entered in VNS, will be turned away. If entered into VNS, DSCC Police will escort the delivery truck to the central receiving facility (CRF). The sponsor will be contacted and have responsibility for escorting the delivery truck for the duration of time they are on DSCC.

LIST OF ALTERNATE FORMS OF IDENTIFICATION

(Extract from DSCCM 5720.003, Appendix 2, to Enclosure 3)

1. ACCEPT ABLE IDENTIFICATION DOCUMENTS. Applicants shall provide a valid and original form of identification from those listed in Paragraph 2 for the purpose of proofing identity for issuance of a visitor pass or ID credential. Prior to acceptance, personnel processing an applicant will screen documents for evidence of tampering, counterfeiting, or other alteration. Documents that appear questionable (e.g., having damaged laminates) or otherwise altered will not be accepted. Altered documents will be held until appropriate authorities are notified, and disposition procedures are authorized.

2. ACCEPT ABLE IDENTITY SOURCE DOCUMENTS. All documents must be current.

a. U.S. Passport or U.S. Passport Card.

c. Permanent Resident Card or Alien Registration Receipt Card (INS Form 1-551).Foreign passport with a temporary (1-551) stamp or temporary (1-551) printed notation on a machine-readable immigrant visa.

d. Foreign passport with a current arrival-departure record (INS Form 1-94) bearing the same names as the passport and containing an endorsement of the alien's nonimmigrant status, if that status authorizes the alien to work for the employer.

e. Employment authorization document that contains a photograph (INS Form 1-766).

f. In the case of a non-immigrant alien authorized to work for a specific employer incident to status, a foreign passport with INS Form 1-94 or INS Form I-94A bearing the same name as the passport and containing an endorsement of the alien's non-immigrant status, as long as the endorsement has not yet expired and the proposed employment is not in conflict with any restrictions or limitations identified on the form.

g. Driver's license or identification card issued by a State or outlying possession of the United States, provided it contains a photograph and biographic information such as name, date of birth, gender, height, eye color, and address. A suspended license is still valid for identification purposes; a revoked or expired license is not.

h. Identification card issued by Federal, State, or local government agencies, provided it contains a photograph and biographic information such as name, date of birth, gender, height, eye color, and address.

i. School identification card with a photograph.

j. Voter's registration card.

k. U.S. Military ID card or draft record.

l. Military dependent's ID card.

m. U.S. Coast Guard Merchant Mariner Card.

n. Native American tribal document.

o. Driver's license issued by a Canadian government authority.

p. For persons under the age of 18 who are unable to present a document listed in subparagraphs 2.a. through p. may produce a current:

(1) School record or report card.

(2) Clinic, doctor, or hospital record.

(3) Day care or nursery school record.

GREEN PROCUREMENT

All products proposed for use in, or requisitioned under this contract must conform to federal Green Procurement regulations as they relate to the Environmental Protection Agency's (EPA) Comprehensive Procurement Guidelines. These products include Energy Star or Federal Energy Management Program designated electronics; United States Department of Agriculture bio-based designated products; Electronic Product Assessment Tool designated electronics; alternative fuels and fuel efficiency; and nonozone depleting substances. Such products must meet contract performance requirements, taking into consideration price, competition, and availability factors.

ANTITERRORISM TRAINING BY CONTRACTOR

(a) In accordance with DOD Instruction 2000.16 and DLA Instruction 6308, Level 1 Antiterrorism (AT Training must be completed on an annual basis by all employees of the contractor performing under this requirement and may be accomplished by one or two means:

1. Under the instruction of a qualified Level 1 AT Awareness Instructor

2. Competition of a DoD-sponsored certified computer or web-based distance learning instruction for Level 1 AT Awareness, which can be found at http://jko.jten.mil/courses/atl1/launch.html for non_CAC holders and https://jkodirect.jten.mil/Altas2/faces/page/login/Login.seams for CAC holders.

(b) Specifically, only those employees whose contract performance requires them to have routine access to federally-controlled facility and/or routine access to a federally-controlled information system must take the training. Also note that the contractor shall coordinate with the Contracting Officer for those employees that require access only intermittently or for a period of less than six months, to determine if the training is required.

(c) Upon initial hire the contractor will contact the onsite DLA Antiterrorism Officer (ATO) to schedule the initial training.

(d) The Certificates are valid for one year; therefore, training shall be completed every year for the duration of the contract.

http://jko.jten.mil/courses/atl1/launch.html

(e) The contractor shall maintain copies of all training certificates for the duration of the contract and may be required to supply copies of the training certificates to the Contracting Officer no more than biannually for submission to the ATO.

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

The text of any referenced FAR, DFARS, or DLAD clause/provision may be obtained electronically at http://farsite.hill.af.mil (DLA Procurement Regulations). The complete edition of Federal Acquisition Regulations (FAR) or DoD FAR Supplement (DFARS) may be obtained by purchase from the Superintendent of Documents, Government Printing Office, Washington, DC 20402.

The clauses/provisions incorporated by reference have the same force and effect as if they were in full text; however, those having no bearing on the instant acquisition become self-deleting.

MAGNITUDE OF THIS CONSTRUCTION PROJECT IN TERMS OF ESTIMATED COST:

( ) This Project is estimated less than $25,000.

(X) This Project is estimated between $25,000 and $100,000.

( ) This Project is estimated between $100,000 and $250,000.

( ) This Project is estimated between $250,000 and $500,000.

( ) This Project is estimated between $500,000 and $1,000,000.

( ) This Project is estimated between $1,000,000 and $5,000,000.

( ) This Project is estimated between $5,000,000 and $10,000,000.

( ) More than $10,000,000.

DESCRIPTION OF WORK:

The contractor shall furnish all plant, labor, equipment, materials, supplies, testing and supervision required in performing all operations in conjunction with this project in strict accordance with the specifications (CSC-20001 Safety Improvements, FY21), contract drawing No. 3-1699 (15 sheets), complete and subject to the terms and provisions of this contract. Contractor shall perform the following work to complete this project.

NOTE: While the Government currently intends to purchase the requirements sought in this solicitation, it may nevertheless be canceled in the event of spending cutbacks necessitated by passage of the Balanced Budget and Emergency Deficit Control Act of 1985, P.L.99-177.

NOTICE: Any contract awarded to a contractor who, at the time of award was suspended, debarred, and ineligible for receipt of contracts with government agencies or in receipt of a notice of proposed debarment from any government agency, is voidable at the option of the Government.

(The following is applicable when marked with an "X".)

(X) Wage Rate General Decision #: OH20210078 Modification number 2, 02/12/2021 attached.

Common Access Card (CAC) Procedures

Performance under this contract may require the contractor to obtain a Common Access Card (CAC). If CACs are issued under this contract, the contractor shall complete and comply with the following steps to obtain, control, and turn-in Government-issued CACs, as well as establish procedures to control and account for contractor CACs at all times. This process is only for the issuance and accountability of CACs. Contractors may be required to provide additional forms and follow additional procedures for other forms of access and/or background/security checks depending on local site/installation requirements.

1. The contractor has each contractor employee requiring a CAC complete and sign Sections I and II of the DD Form 1172-2. The instructions for completing the DD Form 1172-2 are located at http://www.cac.mil/docs/1172-2-Instructions.pdf.

o For Section II, Block 22 - If the contractor employee signs and the DD Form 1172-2 it is then forwarded by the contractor. This provides verification for the employee information. If the contractor is submitting a DD Form 1172-2 for him/herself (e.g., the owner), with no higher authority above them for verification, then the signature in Block 22 must be notarized to verify identity.

2. The contractor forwards the DD Form(s) 1172-2 via hand-carry, secure mail, or encrypted email to (NOTE: The contractor may forward these forms individually or as a group):

O The Contracting Officer’s Representative (COR) for the contract, if a COR was designated.

O The Contracting Officer (CO) for the contract, if no COR was designated.

3. Each contractor employee must verify his/her account information upon receipt of an email from the Government containing a username and password for the Trusted Associate Sponsorship System (TASS). The web link for TASS is included in the email.

4. Each contractor employee will receive an email via TASS when his/her account has been approved. The email will notify the employee to obtain a Government-issued CAC from the nearest Real-Time Automated Personnel Identification System (RAPIDS) office. The email will also provide a link that identifies the locations of RAPIDS offices.

5. Each contractor employee shall obtain his/her issued CAC from the RAPIDS office.

6. The contractor, within one (1) business day of issuance, provides written notice via email to the COR (or the CO, if no COR was designated) for each contractor CAC issued identifying the contractor employee’s name, the date of issuance, and the date of expiration of the CAC. This notification may be made individually for each contractor employee or together for a group of contractor employees.

7. The contractor establishes procedures to control and account for Government-issued contractor CACs at all times, to include the following:

O Ensure contractor CACs issued for this contract are only used for the purpose of performing under this contract.

O Ensure contractor CACs are secured in a manner that precludes unauthorized use and that recognizes the CAC is the property of the U.S. Government.

O Ensure contractor employees do not abuse or place holes in their CACs.

O Ensure contractor employees do not display their CACs in public.

8. If a contractor CAC is lost or stolen:

o The contractor employee shall immediately notify the contractor that the contractor CAC has been lost or stolen.

o The contractor shall immediately notify the COR (or the CO, if no COR was designated), detailing the circumstances regarding the lost or stolen contractor CAC, as follows:

• In person, followed within one (1) business day by a written notice via email, or

• In writing, via email, or

• By telephone, followed within one (1) business day by a written notice via email.

o The contractor shall report the lost or stolen CAC card to the local DLA Police/host installation police, who will provide the contractor a police report. If there is no local DLA Police/host installation police, or no police report is provided, the contractor shall provide information to the COR/CO, as applicable, detailing the circumstances of how the CAC was lost or stolen. The COR/CO will provide a memorandum for the contractor employee to support issuance of new CAC.

o The contractor has the contractor employee bring the report/memorandum to the nearest RAPIDS office. If the CAC can be reissued within 24 hours, bring the report/memorandum to the nearest CAC office for reissue. If the CAC cannot be reissued in 24 hours, follow the steps for a new CAC, beginning at Step 1.

9. If the expiration date for a contractor CAC is prior to completion of the contract and the contractor employee is to continue working under the contract and still requires a CAC, the contractor:

o Notifies the COR as follows:

• In person, followed within one (1) business day by a written notice via email, or

• In writing, via email, or

• By telephone, followed within one (1) business day by a written notice via email o No less than two (2) weeks prior to the current CAC’s expiration date, completes and complies with the steps above beginning with Step 2 for issuance of a new contractor CAC for the employee.

o Brings the expiring CAC to the RAPIDS office for turn-in and receives new CAC.

o Notifies the COR once a new CAC has been issued.

10. The contractor/contractor employee turns in any found CACs immediately, via hand carry, to the nearest Federal law enforcement office.

11. The contractor immediately collects all contractor CAC(s) from the contractor employee(s) at:

o Contract completion or termination o Termination/Reassignment of an employee (this includes any reason the employee is no longer working for the contractor under the contract or otherwise no longer requires a

CAC)

12. The contractor:

o For contract completion or termination – within one (1) business day after collecting the contractor CAC(s), arranges for turn-in via one of the below methods:

i. If the COR/CO is co-located or near enough that in-person transfer of CACs can be arranged, the contractor:

• Arranges to meet the COR (or the CO, if no COR was designated) to turn-in the collected contractor CAC(s).

• Hand-carries all collected contractor CACs for turn-in to meet the COR (or the CO, if no COR was designated).

• Completes and signs the Government-Issued Contractor CAC Turn-In Receipt with the COR (or the CO, if no COR was designated). The contractor is provided a copy of the receipt.

ii. If in-person transfer of CAC cannot be arranged, the contractor:

• Sends, via certified mail, the CACs to the COR/CO. The contractor includes in the package the Government-Issued Contractor CAC Turn-In Receipt, with signed acknowledgement of contractor turn-in.

• Notifies COR/CO that CACs have been sent via certified mail.

• Receives a completed copy of the receipt from the COR/CO once the COR/CO has received the CACs.

o For termination/reassignment of an employee:

i. Immediately notifies the COR (or the CO, if no COR was designated) that the employee is no longer working for the contractor under the contract or otherwise no longer requires a CAC, as follows:

• In person, followed within one (1) business day by a written notice via email, or

• In writing, via email, or

• By telephone, followed within one (1) business day by a written notice via email.

ii. Follows the turn-in procedures above for contract completion or termination, as applicable.

Contractor Reporting Requirements: The contractor is required to submit, on a monthly basis, to the COR (or the CO, if no COR was designated) a report of all employees working on the contract who have been issued CAC cards and a verification of whether each listed employee still requires a CAC. The report must note where changes have occurred (additions or deletions) since the previous month.

Contractor employees who already have a CAC related to another DLA or DoD contract must be included in the monthly report. Contractor shall note the issuing organization and the CAC expiration date. Contractor is still responsible for notifying the COR/CO when the individual is no longer working under the subject contract.

The above procedures have been established as a DLA security measure. Contractors are advised that failure to comply with any of the above requirements will be considered a violation of the terms and conditions of the contract and the Contracting Officer may take action to remedy such violations.

Specifically, failure to safeguard, follow these procedures, including reporting requirements, or turn-in CACs within the established timeframes may result in the following actions, which are in addition to other actions the Contracting Officer may take under governing law and regulation and the terms and conditions of the contract:

• Immediate work stoppage (issuance of a stop work order), not to be lifted until resolution of CAC issue

• Disapproval of invoices and delay of payment

• Withholding of final payment (in accordance with FAR 52.204-9)

• Documentation of CAC Non-Compliance in the Contractor Performance Assessment Reporting

System (CPARS)

Section 01 20 00.00 20 Section 01 33 00

PAGES

Section 01 35 26 Section 01 35 31 Section 01 42 00 Section 01 45 00.1020 Section 01 50 03 Section 01 57 19 Section 01 62 35

Section 01 74 19 Section 01 78 00 Section 01 78 23

Section 01 93 00 Section 02 41 00

SCOPE OF WORK

FOR

SAFETY IMPROVEMENTS, SITE WIDE, FY21

PROJECT CSC-20001

DEFENSE SUPPLY CENTER COLUMBUS

3990 EAST BROAD STREET

COLUMBUS, OHIO 43216-5000

February 2021

TABLE OF CONTENTS

Price and Payment Procedures Submittal Procedures Governmental Safety Requirements Safety, Security, and Fire Provisions Sources for Reference Publications Quality Control for Minor Construction General Statement of Work Temporary Environmental Controls Recycled Recovered Materials Construction and Demolition Waste Management Closeout Submittals Operation and Maintenance Data Submittals Demolition & Deconstruction

UFGS 01 20.00 20 For Compliance with 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

UFGS 01 78 23 Operation & Maintenance Data

Section 01 33 00 Page 1 of 19 5/28/2021

SECTION TABLE OF CONTENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

02/16

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (GA)

1.4.2 For Information Only

1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL

1.5.1 Submittals Required from the Contractor

1.5.1.1 O&M Data

1.6 PREPARATION

1.6.1 Transmittal Form

1.6.2 Identifying Submittals

1.6.3 Format for SD-02 Shop Drawings

1.6.4 Format of SD-03 Product Data and SD-08 Manufacturer's

Instructions

1.6.5 Format of SD-04 Samples

1.6.6 Format of SD-05 Design Data and SD-07 Certificates

1.6.7 Format of SD-06 Test Reports and SD-09 Manufacturer's Field

Reports

1.6.8 Format of SD-10 Operation and Maintenance Data (O&M)

1.6.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout

Submittals

1.6.10 Source Drawings for Shop Drawings

1.6.10.1 Terms and Conditions

1.6.11 Electronic File Format

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of Copies of SD-02 Shop Drawings

1.7.2 Number of Copies of SD-03 Product Data and SD-08

Manufacturer's Instructions

1.7.3 Number of Samples SD-04 Samples

1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates

1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's

Field Reports

1.7.6 Number of Copies of SD-10 Operation and Maintenance Data

1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11

Closeout Submittals

1.8 INFORMATION ONLY SUBMITTALS

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting that Variations are Compatible

1.9.4 Review Schedule is Modified

1.10 SUBMITTAL REGISTER AND DATABASE

1.10.1 Use of Submittal Register

1.10.2 Contractor Use of Submittal Register

1.10.3 Action Codes

1.10.3.1 Government Review Action Codes

1.10.3.2 Contractor Action Codes

Section 01 33 00 Page 2 of 19 5/28/2021

1.10.4 Copies Delivered to the Government

1.11 SCHEDULING

1.11.1 Constraints

1.12 GOVERNMENT APPROVING AUTHORITY

1.12.1 Review Notations

1.13 DISAPPROVED SUBMITTALS

1.14 APPROVED SUBMITTALS

1.15 APPROVED SAMPLES

1.16 WITHHOLDING OF PAYMENT

1.17 PROGRESS SCHEDULE

1.17.1 Bar Chart

1.18 STATUS REPORT ON MATERIALS ORDERS

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

-- End of Section Table of Contents --

Section 01 33 00 Page 3 of 19 5/28/2021

SECTION 01 33 00

SUBMITTAL PROCEDURES

02/16

1.1 SUMMARY

The engineering representative may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited

to) catalog cuts, diagrams, operating charts or curves; test reports;

test cylinders; samples; O&M manuals (including parts list);

certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.

Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A

- Submittal Register".

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to start of construction (work), commencing work on site or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

Surety bonds

Section 01 33 00 Page 4 of 19 5/28/2021

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Submittal register

Schedule of values

Health and safety plan

Work plan Contractor Quality Control (CQC) plan Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

Design submittals, design substantiation submittals and extensions of design submittals.

Section 01 33 00 Page 5 of 19 5/28/2021

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (MSDS) concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

Section 01 33 00 Page 6 of 19 5/28/2021

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with this section.

Submittal Register; G

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved (GA)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be

Section 01 33 00 Page 7 of 19 5/28/2021

"shop drawings."

1.4.2 For Information Only (FIO)

Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL

1.5.1 Submittals Required from the Contractor

As soon as practicable after award of contract, and before procurement of fabrication, forward to the engineering and the contracting offices submittals required in the technical sections of this specification, including shop drawings, product data and samples.

The engineering representative will review and approve for the Contracting Officer those submittals reserved for Contracting Officer approval to verify submittals comply with the contract requirements.

1.5.1.1 O&M Data

The Facility Engineering Representative will review and approve for the Contracting Officer O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.

In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.

1.6 PREPARATION

1.6.1 Transmittal Form

Use the transmittal form ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. This form may be provided upon request or is available at the USACE Publications website:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerF orms/Eng_Form_4025-R.pdf

Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.6.2 Identifying Submittals

When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.

Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_4025-R.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_4025-R.pdf

Section 01 33 00 Page 8 of 19 5/28/2021

a. Project title and location.

b. Construction contract number.

c. Date of the drawings and revisions.

d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other subcontractor associated with the submittal.

e. Section number of the specification section by which submittal is required.

f. Submittal description (SD) number of each component of submittal.

g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.

h. Product identification and location in project.

1.6.3 Format for SD-02 Shop Drawings

Shop drawings are not to be less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless other form is required.

Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.

Present 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.

Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph

IDENTIFYING SUBMITTALS.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.

Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings.

Identify materials and products for work shown. Include the nameplate data, size and capacity on drawings. Also include applicable federal, military, industry and technical society publication references.

Submit drawings PDF format.

1.6.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions

Present product data submittals for each section as a complete, bound volume. Include table of contents, listing page and catalog item numbers for product data.

Indicate, by prominent notation, each product which is being submitted;

indicate specification section number and paragraph number to which it

Section 01 33 00 Page 9 of 19 5/28/2021 pertains. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist.

Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.

Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates.

Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the engineering representative. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .