Switchgear Replacement Building 30 at DLA Distribution San Joaquin CA DDJC Federal contract opportunity
Solicitation number
SP3300-23-B-0004
Issued by
Defense Logistics Agency Distribution

About this file

This amendment modifies solicitation SP3300-23-B-0004 for switchgear replacement services at the Defense Logistics Agency Distribution facility in San Joaquin, California. The amendment answers a vendor question by clarifying that the site safety and health officer and quality control manager roles may be dual hatted with the superintendent role, but a minimum of two people are still required on-site to fulfill those responsibilities. The amendment also changes the opening and closing dates of the solicitation to August 1, 2023 through August 31, 2023 with proposals due by 3:00 PM. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO.

See Block 14

4. REQUISITION/PURCHASE REQ. NO.

P.2023.00668

5. PROJECT NO. (If applicable)

6. ISSUED BY CODE SP3300 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE FACILITY CODE

SP330023B0004

X

2023 AUG 01

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

12. ACCOUNTING AND APPROPRIATION DATA (If required)

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A NAME AND TITLE OF SIGNER (Type or print)

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

(a) By completing Items 8 and 15, and returning

DLA DISTRIBUTION

ACQUISITION OPERATIONS (J7)

430 MIFFLIN AVENUE SUITE 3102A

NEW CUMBERLAND PA 17070-5008

15C. DATE SIGNED 16C. DATE SIGNED

D. OTHER (Specify type of modification and authority)

3. EFFECTIVE DATE

Opening/Closing Date Changed to:

2023 AUG 01 / 2023 AUG 31

TIME 3:00 PM

See Attached Continuation Sheet(s).

(X)

CHECK ONE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 2 OF 2 PAGES

SP330023B0004 - 0001

Amendment 0001 is incorporated into this Invitation For Bid (IFB) for the project “Switchgear Replacement Building 30” DLA Distribution San Joaquin and shall become part of any resulting Contract issued.

Amendment 0001 is being issued to answer a Vendor Question.

Vendor Question:

Question 1: Specification section 01 35 29 paragraph 1.5.1.1 and 01 45 00 paragraph 3.4.2 state the SSHO and QCM must be full time individuals in addition to the Superintendent. Will consideration be given to dual hat any of these roles or will 3 full time individuals be required to be on site at all times?

Answer 1: Yes, One person can be SSHO and Superintendent or QC and Superintendent. A minimum of two people are required to comply with Specification section 01 35 29 paragraph 1.5.1.1 and 01 45 00 paragraph 3.4.2.

All other terms and conditions remain unchanged.

END OF AMENDMENT 0001