16B0013AMDP0002_PG_2.pdf
PDF 14 KB Posted
- Attached to
- Wastewater Plant Repair Federal contract opportunity
- Solicitation number
- SP3300-16-B-0013
- Issued by
- Defense Logistics Agency Distribution
About this file
Page 2 of Amendment 00002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Tab_E-17_Public_Notice_of_Award.pdf | ||
| Bid_Results_-_SP330016B0013.pdf | ||
| 16B0013_SF30_AMENDMENT_0003.pdf | ||
| 16B0013AMDP0003_PG_2.pdf | ||
| 16B0013_SF30_AMENDMENT_0002.pdf | ||
| Attachment_13_Plate_Image.pdf | ||
| Attachment_12_Site_Visit_Roster.pdf | ||
| Amendment_0001.pdf | ||
| Attachment_4_Schedule_of_Supplies.pdf | ||
| Attachment_9_SF25_(Performance_Bond).pdf | ||
| Solicitation.pdf | ||
| Attachment_5_Submittal_Reg.pdf | ||
| Attachment_6_Transmittal_of_Shop_Drawings.pdf | ||
| Attachment_8_SF24_-_Bid_Bond.pdf | ||
| Attachment_3_Drawing_and_Photos.pdf | ||
| Attachment_11_Standard_Form_1442.pdf | ||
| Attachment_7_Davis_Bacon.pdf | ||
| Attachment_1_SoW _Gen_Specs _and_Checklists.pdf | ||
| Attachment_2_Site_Map.pdf | ||
| Attachment_10_SF25A_Payment_Bond.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP3300-16-B-0013
AMD 00002
I. The purpose of this amendment is to provide answers to vendor questions.
II. The following Vendor Questions are hereby answered.
Question 1:
What are the Liquidated Damages?
Answer 1: $500 per day
Question 2:
Is there Good Faith Outreach requirements?
Answer 2: There are no Good Faith Outreach Requirements for this acquisition.
Question 3:
Was the pre-bid meeting mandatory?
Answer 3: No
Question 4:
M001 calls out Detail 5 on M003 for the BFV installation detail … this detail cannot be found. Can you please provide.
Answer 4: This a typo detail 5 is not required.
Question 5:
What size is the BFV?
Answer 5: 10 inches
Question 6:
What is the scope of electrical? Can you provide any more detail/drawings on what the scope of work will be?
Answer 6: Electrical work is minimal. New pumps can use existing disconnect switches located next to them. No need to run wires or conduits to exiting panel.
Question 7:
What is the scope of instrumentation/SCADA?
Answer 7: None
Question 8:
Can you additionally get me the serial numbers for the sludge pumps per scope item 2.
Answer 8: CL287
Question 9:
Please do the same for the pumps per scope item 3 Answer 9: Circulating pump name plate is provided on Attachment 13 Plate Image. No other information is available.
Contractor must verify all the field information. Govt. shall not be liable for any discrepancies found later.
Question 10: We are wondering if you could kindly provide access to e-copies of the aforementioned project?
Answer 10: See section B.2 Electronic Solicitation
III. Attachment 13 Plate Image is hereby added to this solicitation
IV. All other terms and conditions remain unchanged.