Text version

STATEMENT OF WORK

Base Wide Urinal Replacement

PROJECT # XHZG20200733

11 December 2020

1. The contractor shall provide all labor, material, tools, equipment and transportation necessary to complete the work identified in this Statement of Work.

2. All debris is to be disposed of off Base with proper documentation in accordance with the waste plan generated by the contractor after the project is awarded contractor.

3. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

a. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

4. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative.

5. This project is to be in accordance with the current version of the EMS Environmental Protection Statement. A copy of this document will be provided to bidding contractors via beta.sam.gov as an attachment.

6. This project is to be in accordance with the current version of the 138FW Safety and Accident Prevention Guide. A copy of this document will be provided to bidding contractors via beta.sam.gov as an attachment.

Continued on Next Page

7. The contractor shall apply all environmental health and safety procedures required by local, state and federal regulations.

8. All work to be performed 7:00 AM to 5:30 PM Monday thru Thursday. If alternate work schedule is desired, it must be requested in writing and approved by CE and Security 48 hours prior to the desired schedule.

9. Prior to any work, the contractor shall submit for approval by CE, one electronic copy of technical literature for all products to be used. Provide Safety Data Sheets for all appropriate products.

10. All DBIDS Contractor passes will be approved by the BCE and issued by SFS after completion of required background checks. Final payment to the general contractor will not be made at the completion of the construction project until all contractor badges have been returned or the continuing need is validated and documented in writing by SFS and BCE personnel.

DEMOLITION

1. Remove 23 existing urinals in varies building on base. Refer to photos attached.

2. Demolish minimum wall area to complete the work.

PROVIDE AND INSTALL

1. Install 23 Zurn Top Spud Urinal Z5755-U with Zurn Z6003AV-ULF flush valve and all fittings and mounting brackets to complete this work.

2. Install new concrete backer board, wall tile and grout to match existing.

3. Install 2 new urinal dividers to match existing partitions in Building 314.

4. Inspect plumbing drain lines with camera prior to installation of new urinals, first 15 only. Video will need to be provided if any damage is found.

5. Contractor is to assume water is available since flushable/watered urinals were previously installed.