United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
GH 398A: Replace Glazing System
Plant Science Research Unit (PSRU)
USDA-ARS, St. Paul, MN
DATE: March 2, 2022
USDA-ARS, St. Paul, MN
TABLE OF CONTENTS
SOW Description
Project Specifications:
DIVISION 01 – GENERAL REQUIREMENTS
01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 08 80 10 Greenhouse Reglazing General Notes and Requirements
Attachments Material Approval Submittal form Schedule of Material Submittals Recently Replaced Component Form AD-700 form
General Notes and Requirements
Photographs of Existing GH398A
Project Drawings Sheet 1 – Floor Plan and Elevations
END OF TABLE OF CONTENTS
Scope of Work Description
Scope of Work Description:
1. Project Location: Greenhouse (GH) 398A
USDA-ARS-Plant Science Research Unit (PSRU) 1535 Lindig Street St. Paul, MN 55108
2. Point of Contact at Location: Randy Kiehne
(651) – 649 - 5046 Randy.Kiehne@usda.gov
3. The scope of the project shall be, generally, the removal of the existing glazing system of the GH 398A (greenhouse of PSRU) and the replacement with new glazing system along miscellaneous work components in accordance with this Statement of Work, project specifications and project drawings.
Replacement of the glazing system and associated project components shall be performed in a neat, workmanlike manner and shall be sequenced to minimize the downtime of the greenhouse. All new materials for the complete and proper glazing replacement shall be on-site and ready for installation before proceeding with any demolition of the existing greenhouse glazing system. Once “on-site” work commences, the work shall be completed without interruption to avoid jeopardizing ongoing research and impacting ongoing plant growth.
The greenhouse glazing system shall consist of acrylic glazing panels with gasketed aluminum caps that are approved by the acrylic manufacturer. The completed glazing system shall provide closure for all edges of acrylic glazing panels. Provisions shall be made within the glazing system to handle expansion and contraction as required by the acrylic manufacturer. The completed glazing system shall provide a water / weather tight building and prevent condensation and moisture.
The replacement of the greenhouse’s glazing system shall be completed in phases such that ongoing research and plant growth is not interrupted. The Contractor shall coordinate thoroughly with the Owner such that plants, research equipment, etc. are relocated from phase to phase in a timely manner. Relocation of plants, research equipment, etc will be by Owner. See project drawings for additional information.
o Phase 1 shall be Link, GH Room 01, GH Room 02, and GH Room 03.
o Phase 2 shall be GH Room 04, GH Room 05, and Vestibule
4. Where “Approved Equal” is indicated in the specification of equipment, material or installation; the Owner shall approve all alternate equipment, materials, manufacturers or installation. It shall be the Contractor’s burden to furnish all documentation and / or samples to show equality with specified items. Owner’s decision is final.
5. Shop Drawings shall be submitted as indicated in the project specification sections.
Shop drawings shall be reviewed for general conformance with the Contract Documents; and approval by the Owner does not relieve the Contractor of complying with the requirements of the Contract Documents.
6. The Contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, supervision and incidentals for all elements of the work to provide a complete and properly functioning installation in accordance with this Statement of Work, project specifications and project drawings.
7. Contractor shall coordinate all work activities with the Owner prior to beginning any work. All work shall be scheduled in a manner such that ongoing research is not jeopardized.
8. Photographs of the existing greenhouse are provided in the project’s solicitation package. The Contractor may use the photographs as a reference / resource in developing their bid / proposal. The Contractor shall confirm all existing conditions and dimensions prior to proceeding with any project activities
Plant Science Research (PSRU)
Project Specifications
01 32 00 - 1 Construction Progress Documentation
DIVISION 01 – GENERAL REQUIREMENTS
01 32 00 – CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract including other Division 01 Specification Sections apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's construction schedule.
2. Daily construction reports.
B. Related Requirements:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
1.3 INFORMATIONAL SUBMITTALS
A. Contractor's Construction Schedule: Submit size required to display entire schedule for entire construction period. Submit via email.
1. Submit a working electronic copy of schedule in “pdf” format and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.
B. Construction Schedule Updating Reports: Submit upon request by Owner.
C. Daily Construction Reports: Submit at weekly intervals.
1.4 QUALITY ASSURANCE
A. Scheduling Qualifications: Contractor shall have the capability of updated construction schedule within 24 hours.
B. Contractor’s Construction Schedule: The Contractor shall secure time commitments for performing construction activities from his subcontractors and suppliers. The Contractor shall prepare a combined construction schedule for the entire project. The schedule shall be a comprehensive, integrated, and fully developed.
01 32 00 - 2 Construction Progress Documentation
1.5 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording events at Project site.
An electronic copy (pdf format) of the daily reports shall be submitted daily to the COR/EPM.
A copy of the daily reports shall be sent weekly to the CO along with certified payrolls (coordinate submission requirements with CO). The daily construction report must be dated and signed and should including the following:
1. List of subcontractors.
2. High and low temperatures and general weather conditions.
3. Accidents.
4. Stoppages, delays, shortages, and losses.
5. Meter readings and similar recordings.
6. Orders and requests of authorities having jurisdiction.
7. Services connected and disconnected.
8. Equipment or system tests and startups.
PART 2 - EXECUTION
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: Upon request by Owner, update schedule to reflect actual construction progress and activities.
B. Distribution: Distribute copies of approved schedule to CO/ACO/COR/EPM.
END OF SECTION 01 32 00
01 33 00 - 1 Submittal Procedures
01 33 00 – SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract including other Division 01 Specification Sections, apply to this Section.
B. See “Attachments” section of the SOW for “Material Approved Submittal” form
C. See “Attachments” section of the SOW for “Schedule of Materials Submittals” form.
D. See “Attachments” section of the SOW for “Recently Replaced Component” form.
E. See “Attachments” section of the SOW for “AD-700” form.
1.2 SUMMARY
A. Section includes requirements for the administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.3 DEFINITIONS
A. Submittals: Written and graphic information.
B. Portable Document Format (pdf): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.4 SUBMITTALS
A. Submittal Format:
1. Arrange the following information in a tabular format:
a. Name of subcontractor if applicable.
b. Description of the Work covered.
1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
01 33 00 - 2 Submittal Procedures
B. Processing Time: Allow time for submittal review, including time for re-submittals. Time for review shall commence on Owner's receipt of submittal. No extension of the Contract Time will be authorized because of failure to permit the processing of submittals, including re-submittals.
1. Initial Review: Allow calendar 15 days for initial review of each submittal.
2. Re-submittal Review: Allow calendar 15 days for review of each re-submittal.
C. Electronic Submittals: All submittals shall be submitted electronically in “pdf” format, via email. Identify and incorporate information in each electronic submittal file as follows:
1. Transmittal Form for Electronic Submittals: Format acceptable to Government, containing the following information:
a. Project name.
b. Date.
c. Name of Contractor.
d. Name of firm or entity that prepared submittal.
e. Names of subcontractor, manufacturer, and supplier.
D. Identify features, accessories and finishes requiring selection by CO/ACO/COR/ EPM.
E. Use for Construction: Retain complete approved copies of submittals on Project site. Use only final action submittals that are marked with approval notation from CO/ACO/COR/ EPM.
PART 2 - PRODUCTS
2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements: Prepare and transmit submittals for material and products proposed for the project.
1. Submit via email with electronic submittal files attached.
2. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the submittal / shop drawing process and not prior to bidding. Contractor shall be responsible for submitting information to show equivalence. Determination by CO/ACO/COR/EPM on equivalence is final.
3. Each submittal shall include a completed “Material Approval Submittal” form. See “Attachments” section of the SOW for this form.
B. Include one hard copy of each approved shop drawing in the Operations and Maintenance Manual submitted to the Government during Closeout Procedures.
C. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Mark each submittal to show which products (manufacturer, model, type, size, options, etc.) are proposed.
01 33 00 - 3 Submittal Procedures
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to
CO/ACO/COR/ EPM.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 CO/COR ACTION
A. General: CO/ACO/COR/EPM will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Submittals: CO/ACO/COR/EPM will review each submittal, make marks to indicate corrections or modifications required, and return it. CO/ACO/COR/EPM will provide notation on each submittal to indicate the appropriate determination from their review:
1. Reviewed - Approved with No Exceptions Noted.
2. Reviewed - Approved with Notes - Make Corrections Noted
3. Reviewed - Revise and Resubmit.
4. Reviewed - Rejected.
3.3 REQUIRED SHOP DRAWINGS AND PRODUCT DATA
A. See individual specification sections and Drawings.
END OF SECTION 01 33 00
USDA, St. Paul, MN
01 42 00 - 1 References
01 42 00 – REFERENCES
PART 1 - GENERAL
1.1 DEFINITIONS
A. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."
B. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.
1.2 INDUSTRY STANDARDS
A. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.
B. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.
1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.
1.3 ABBREVIATIONS AND ACRONYMS
A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Thomson Gale's "Encyclopedia of Associations" or in Columbia Books' "National Trade & Professional Associations of the U.S."
B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
IAPMO International Association of Plumbing and Mechanical Officials
ICC International Code Council www.iccsafe.org
ICC-ES ICC Evaluation Service, Inc.
01 42 00 - 2 References
C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
DOE Department of Energy
EPA Environmental Protection Agency
FCC Federal Communications Commission
FDA Food and Drug Administration
LBL Lawrence Berkeley National Laboratory
NIST National Institute of Standards and Technology
OSHA Occupational Safety & Health Administration
PHS Office of Public Health and Science
SD State Department
USDA Department of Agriculture
USPS Postal Service
01 42 00 - 3 References
D. Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
ADAAG American with Disabilities Act Accessibility Guidelines
Americans with Disabilities Act (ADA)
Architectural Barriers Act (ABA) Accessibility Guidelines for Buildings and Facilities
CFR Code of Federal Regulations
FED-STD Federal Standard
FTMS Federal Test Method Standard
UFAS Uniform Federal Accessibility Standards Available from Access Board
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 42 00
01 50 00 - 1
Temporary Facilities and Controls
01 50 00 – Temporary Facilities and Controls
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
1.2 USE CHARGES
A. Water Service from Existing System: Water from Government's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
B. Electric Power Service from Existing System: Electric power from Government's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
1.3 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Contractor to obtain required certifications and permits.
C. Accessible Temporary Egress: Comply with applicable provisions in ICC/ANSI A117.1 and OSHA regulations and standards.
1.4 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Contractor to assume responsibility for operation, maintenance, and protection of each permanent service during its use.
PART 2 - PRODUCTS
2.1 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
01 50 00 - 2
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Connect to existing service.
1. Arrange with COR / COTR for time when service can be interrupted, if necessary, to make connections for temporary facilities.
B. Water Service: Connect to Government's existing water service facilities.
C. Sanitary Facilities: Contractor shall furnish toilets, wash facilities, and drinking water at the facility for use of construction personnel.
D. Telephone Service: Provide superintendent with cellular telephone for use.
E. Electric Power Service: Connect to Government's existing electric power service.
F. While Contractor is using existing installations for temporary facility purposes; Contractor shall maintain existing installations in condition acceptable to the Government. At Substantial Completion, Contractor shall restore existing installations used for temporary facilities to their original, properly operating condition prior to its initial use.
3.3 SUPPORT FACILITIES INSTALLATION
A. Maintain access for fire-fighting equipment and access to fire hydrants.
B. Parking: Use designated areas of Government's existing parking areas for construction personnel.
C. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.
D. Waste Disposal: Contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of project waste diverted to recycle. The Contractor shall submit diversion documentation as part of project closeout. If no project waste is diverted to recycle, the Contractor shall submit a letter stating this and why diversion was not practical.
01 50 00 - 3
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other installations and improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
C. Barricades, Warning Signs, and Lights: Provide and maintain all safeguards in accordance with OSHA regulations and standards and to provide adequate protection to pedestrians and building occupants. Comply with OSHA requirements for erecting structurally adequate barricades, including warning signs and lighting.
D. Temporary Egress: Maintain temporary egress from existing occupied facilities as required by
OSHA.
E. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses, comply with
NFPA 241.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
C. Termination and Removal: Remove each temporary facility when need for its service has ended or no later than Substantial Completion. Restore permanent construction that may have been disturbed due to the temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
END OF SECTION 01 50 00
01 73 00 - 1 Execution
01 73 00 – EXECUTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:
1. Installation of the Work.
2. Cutting and patching.
3. Progress cleaning.
4. Protection of installed construction.
1.2 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of other work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of other work.
1.3 QUALITY ASSURANCE
A. Cutting and Patching: Cut and patch elements in a manner that will not change:
1. Load-carrying capacity or increase deflection.
2. Reduce their capacity to perform as intended.
3. Increase maintenance.
4. Decrease operational life or safety.
5. Reduce building’s aesthetic qualities.
B. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.
C. All phases of the Work shall be executed while maintaining full compliance with applicable EPA regulations and OSHA standards including, but not limited to, 29 CFR 1926 Safety and Health Regulations for Construction and 29 CFR 1910 Occupational Safety and Health Standards.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Comply with requirements specified in other Sections and Drawings.
01 73 00 - 2 Execution
B. In-Place Materials: Use materials for patching identical to in-place materials and that visually match in-place adjacent surfaces to the fullest extent possible.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions for all other conditions affecting installation and performance. If conditions detrimental to that installation and performance are identified, submit report to CO/COR/COTR/EPM. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly. Verify dimensions of existing conditions and related Work elements before fabrication.
B. Space Requirements: Verify space requirements and dimensions of items.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to CO/COR/EPM according to requirements in Contract.
3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment, elevation, and as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Conduct construction operations so no part of the Work is subjected to damaging operations or loading.
D. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels (85 db or greater) to the public or Government staff without prior approval by COR / COTR.
E. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned.
1. Allow for building movement, including thermal expansion and contraction.
01 73 00 - 3 Execution
F. Joints: Make joints of uniform width. Arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.
G. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
3.4 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.
B. Existing Warranties: Remove, replace, patch, and repair by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of work to be cut.
D. Protection: Protect in-place construction during cutting and patching to prevent damage.
Provide protection from adverse weather conditions.
E. Cutting: Cut in-place construction using methods least likely to damage elements retained or adjoining construction.
F. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations. Patch with durable seams that are as invisible as practicable.
G. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.5 PROGRESS CLEANING
A. General: Maintain clean Project site and work areas, free of waste materials and debris.
Dispose of materials lawfully.
B. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
3.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
END OF SECTION 01 73 00
01 77 00 - 1
Closeout Procedures
01 77 00 – CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Final completion procedures.
2. Submission of Documentation on Diverting Project Waste to Recycle
3. Warranties.
4. Final cleaning.
B. Related Requirements:
1. Division 01 Section "Execution" for progress cleaning of Project site.
2. Division 01 Section “Operating and Maintenance Data” for operating and maintenance manual.
1.2 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion:
1. Submit project record documents in accordance with Government’s solicitation package and paragraph 1.3.
2. Submit Documentation on Diverting Project Waste to recycle in accordance with
Government’s solicitation package and paragraph 1.4.
3. Submit Project Warranties in accordance with Government’s solicitation package and paragraph 1.5.
B. Final Site Inspection: Submit a written request for final inspection. On receipt of request, CO/COR/COTR/EPM will either proceed with site inspection or notify Contractor of unfulfilled requirements.
1.3 SUBMISSION OF PROJECT RECORD DOCUMENTS
A. Submit electronic copy (scan) of project record documents along with three (3) hard copies of project record documents to the CO/ACO/COR/EPM.
1.4 SUBMISSION OF DOCUMENTATION ON DIVERTING PROJECT WASTE TO RECYCLE
A. See Section 01 50 00 for additional information.
01 77 00 - 2
B. The Contractor shall submit documentation on the amount of project waste diverted to recycle as part of project closeout. Contractor shall submit the type and amount of waste that was diverted to recycle, present information in a clear, typewritten format. If no project waste is diverted to recycle, the Contractor shall submit a letter stating this and why diversion was not practical. Submit this documentation in accordance with the procedures indicated in Section 01 33 00.
1.5 SUBMITTAL OF PROJECT WARRANTIES
A. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual. Submit electronic copy of the warranty manual along with three (3) hard copies of warranty manual to the CO/ACO/COR/EPM. Hard copy of the warranty manual shall be a bound and indexed three ring binder containing written warranties for equipment/products furnished under the contract with a complete listing of such equipment/products.
1. The equipment/products warranty list shall:
a. Identify the product / equipment.
b. Include the duration of the warranty
c. Indicate the start date of the warranty
d. Indicate the ending date of the warranty
e. List the point of contact and contact information (name, address and telephone number) for fulfillment of the warranty.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
3.1 PROJECT RECORD DOCUMENTS
A. Maintain, at project site, one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Approved shop drawings, product data, and samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Government.
01 77 00 - 3
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Legibly mark to record actual construction.
3.2 WARRANTIES
A. Verify that documents are in proper form, contain full information.
B. Retain warranties until time specified for submittal.
3.3 CLEANUP
A. Provide final cleaning in accordance with ASTM E 1971. Remove waste and surplus materials, rubbish, and construction facilities from the site.
END OF SECTION 01 77 00
01 78 23 - 1 Operation and Maintenance Data
01 78 23 - Operation and Maintenance Data
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for operation and maintenance manuals.
1.2 CLOSEOUT SUBMITTALS
A. Manual Content: Submit manual content formatted and organized as required by this Section.
B. Format: Submit electronic copy of the operation and maintenance manual (pdf format) along with three (3) hard copies of operation and maintenance manual to the CO/COR/COTR/EPM.
PART 2 - PRODUCTS
2.1 REQUIREMENTS FOR OPERATION AND MAINTENANCE MANUALS
A. Organization: Each manual shall contain the following materials. Organize each manual with a separate section for each of the following materials in the order listed.
1. Title page.
2. Table of contents.
3. Manual contents for glazing and associated components.
4. Manual contents for aluminum glazing caps and associated components.
5. Manual contents for sealants
B. Title Page: Include the following information:
1. Name and address of Project.
2. Government contract number.
3. Date of submittal.
4. Name and contact information for Contractor.
C. Table of Contents: List each product and system included in manual, identified by product name.
D. Manuals, Paper Copy: Submit manuals in bound and labeled volumes.
1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual.
Mark each tab to indicate contents.
01 78 23 - 2 Operation and Maintenance Data
2.2 OPERATIONAL AND MAINTENANCE INFORMATION
A. Content: Include the following information:
1. Maintenance and cleaning procedures.
B. Descriptions: Include the following:
1. Product name and model number.
2. Manufacturer's name.
C. Maintenance Procedures: Include manufacturer's written recommendations and the following, as applicable:
1. Manufacturer’s standard maintenance instructions and bulletins.
2. Drawings, diagrams, and instructions required for maintenance including disassembly, removal, replacement and reassembly instructions.
3. Identification and nomenclature of parts and components.
4. List of items recommended to be stocked as spare parts and local sources for parts and components.
5. Types of cleaning agents to be used and methods of cleaning.
6. List of cleaning agents and methods of cleaning detrimental to product.
7. Schedule for routine cleaning and maintenance.
PART 3 - EXECUTION
3.1 MANUAL PREPARATION
A. Manufacturers' Data: Data shall be marked to identify each product or component incorporated into the Work.
B. Include copy of approved submittals from shop drawing submission(s) in manual.
END OF SECTION 01 78 23
GH 398A – Replace Glazing System
08 80 10-1
DIVISION 8 - DOORS & WINDOWS
Section 08 80 10 – Greenhouse Re-glazing
1. GENERAL
1.1 WORK INCLUDES
A. Description:
1. Unless noted otherwise on the Drawings, remove / dispose all existing acrylic glazing at greenhouse and replace with new glazing as specified herein and as shown on the Drawings.
2. Unless noted otherwise on the Drawings, remove / dispose all existing aluminum caps associated with greenhouse glazing system and replace with new aluminum glazing caps as specified herein and as shown on the Drawings.
1.2 GENERAL
A. Conduct demolition to minimize interference with adjacent building areas. See Section 01 33 00 for additional information regarding diverting project waste to recycle.
B. Replacement of the glazing system and associated project components shall be performed in a neat, workmanlike manner and shall be sequenced to minimize the downtime of the greenhouse. All new materials for the complete and proper glazing replacement shall be on-site and ready for installation before proceeding with any demolition of the existing greenhouse glazing system.
C. Replacement of the glazing system and associated project components shall be performed in a neat, workmanlike manner and shall be sequenced to minimize the downtime of the greenhouse. All new materials for the complete and proper glazing replacement shall be on site and ready for installation before proceeding with any demolition of the existing greenhouse glazing system.
D. The greenhouse glazing system shall consist of acrylic glazing panels with gasketed aluminum caps that are approved by the acrylic manufacturer. The completed glazing system shall provide closure for all edges of acrylic glazing panels. Provisions shall be made within the glazing system to handle expansion and contraction as required by the acrylic manufacturer. The completed glazing system shall provide a rain tight building and to prevent condensation and moisture.
E. Maintain protected egress and access at all times.
F. Provide all such security devices as necessary to protect against accidental trespass or accident by falling.
08 80 10-2
1.3 QUALITY ASSURANCE
A. Manufacturers of glazing, glazing caps and associated products furnished in this project shall be a member of the National Greenhouse Manufacturers Association (located in United States).
B. All manufactured products shall be manufactured and installed in accordance with the respective manufacturer’s published product specifications and installation instructions except as exceeded or otherwise modified herein.
B. Qualifications of installers: Provide at least one person who shall be thoroughly trained and experienced in the skills required, who shall be completely familiar with the referenced standards and the requirements of this work, and who shall personally direct all installations performed under this Section of these Specifications.
C. All work to be carefully executed as to not damage the plants, furnishings, equipment, or any other existing item. Remove and dispose of any debris in and around the greenhouse.
1.4 REFERENCES
A. Manufacturer's product data: The manufacturer’s product data on approved products indicated this specification, current at date of bidding documents, are incorporated by reference to the same force and effect as if repeated herein at length.
1.5 PRODUCT HANDLING
A. Protection:
1. Use adequate means to protect aluminum glazing caps and acrylic glazing panels and accessory items from deformation, defacements or other damage during fabrication, delivery, storage, handling and installation.
2. Store all materials as per manufacturer’s written instructions.
3. Scratches, gouges, and defacements will be cause for rejection of the installed system and replacement shall be the full responsibility of the Contractor at no additional cost to the Owner.
1.6 SUBMITTALS
A. See Section 01 33 00 for additional information.
B. Submit product data for the following items:
1. Acrylic glazing panels
2. Each type of sealant required
3. Aluminum glazing cap
4. Each type of fastener required
08 80 10-3
C. Provide samples for the following items:
1. Two 12” x 12” samples of acrylic glazing panel
2. Two 12” long samples of aluminum glazing cap
D. Provide submittal on Contractor’s plan to divert project waste to recycle (i.e.
provide listing of identified materials that will be demolished and diverted to recycle).
E. Provide submittal indicating the locations where sealant is recommended to be applied by the acrylic manufacturer.
F. Provide a submittal indicating / documenting the existing conditions and the snow load capacity of the glazing panels (provide indication of snow load capacity of glazing panels with support system of existing greenhouse).
1.7 ENVIRONMENTAL AND HEALTH REQUIREMENTS
A. Do not demolish or install work during rainy or other adverse weather conditions.
B. Do not install materials at temperatures lower than recommended by respective material manufacturer for the product used.
C. Do not install any Asbestos Containing Products. Verify with manufacturers that no supplied products (whether listed or otherwise) contain asbestos.
D. Contractor shall provide temporary barriers or warning signs announcing construction activity in any adjacent traffic patterns.
1.8 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and antipollution laws.
1. Do not allow debris to accumulate. Any debris that will be windblown to neighboring sites shall be disposed of immediately and in manner that prevent this.
2. Enforce reduce/reuse/recycle to meet the EPA’s Pollution Prevention and Waste Minimization programs.
3. Burning of any wrapping or cartons on-site is strictly prohibited.
2. PRODUCTS
2.1 ACRYLIC GLAZING
A. All glazing panels shall bear the label of its manufacturer indicating quality and thickness and compliance to codes and standards where applicable.
B. All glazing to be relatively distortion-free with any distortion wave in the horizontal direction.
08 80 10-4
C. Unless noted otherwise, all glazing panels shall be multi-skinned, clear, all acrylic type, ultraviolet filtering, 16 mm thick with 32 mm rib spacing, and shall have nominal 86% light transmission at installation.
1. Roof glazing panels for “Link” connecting Greenhouse to Headhouse (see
Drawings) shall be multi-skinned, all acrylic type, UV blocking, IR reflecting, 16 mm thick with 32 mm rib spacing, and shall have nominal 28% light transmission at installation. Color shall be cool blue.
D. Glazing panels shall incorporate a self-cleaning, anti-condensate technology
(coating) on all surfaces of the panel that spreads water to minimize light scattering, to minimize algae growth, and to assist in cleaning.
E. Glazing panels shall have a 30 year manufacturer’s non-yellowing warranty, 10 year light transmission warranty (light transmission after 10 years shall not be less than 80%), and a 10 year manufacturer’s warranty on hail.
F. Approved Products:
1. Unless noted otherwise, all glazing panels shall be Acrylite “Resist” Series manufactured by Roehm America LLC or approved equal
2. Roof glazing panels for “Link” connecting Greenhouse to Head House shall be Acrylite “Heatstop” Series manufactured by Roehm America LLC or approved equal.
2.2 ALUMINUM GLAZING CAPS
G. All aluminum glazing caps shall be mill finish extruded with appropriate heat treatment. All extrusions shall have a high inherent resistance to corrosion with a top rating of “A” in corrosion resistance. No castings shall be permitted for joining members at joints subject to stress in which tensile strength is a factor.
H. Aluminum shall be of alloy 6063-T6 or 6063-T5.
I. All fasteners shall be stainless steel hex head screws to match existing gauge.
J. Caps shall extend in one piece from the eave to the ridge and shall be fastened to all existing extrusions.
K. All glazing caps shall be of a “gasketed” type.
2. All glazing gaskets shall be EPDM rubber or other compatible material used in conjunction with the above mentioned acrylic glazing panels.
2.3 SEALANT
A. All “caulking” or “sealant” for glazing system.
1. Sealant shall be medium modulus, one part, high performance, neutral cure silicone sealant, color “clear”
a. Acceptable manufacturer:
1. Tremco Spectrum 2
2. Approved equal
08 80 10-5
B. Primers:
1. If a primer is recommended by the manufacturer of the caulk or sealant for the various surfaces and conditions involved, provide primer recommended by the manufacturer. If the manufacturer’s specifications for a specific material state that a primer is not needed, no primer shall be required.
3. EXECUTION
3.1 DEMOLITION
A. Removal of aluminum caps and existing panels to be performed from the exterior of the building.
B. Remove materials to be reinstalled or retained in manner to prevent damage.
Store and protect.
C. Do not burn or bury materials on-site.
D. At a minimum, execute daily cleaning to keep the work, the site, and adjacent properties free from accumulation of waste materials, rubbish, and debris.
3.2 INSTALLATION OF ACRYLIC GLAZING
A. Setting of glazing
1. Set glazing in accordance with manufacturer's recommendations.
2. Maintain manufacturer’s setting tolerance and clearances.
A. Protect aluminum finishes from marring or disfigurement during construction.
B. Apply any foil tape and/or mesh tape as per manufacturer’s guidelines and the
National Greenhouse Glazing Manufacturer’s (NGMA) glazing recommendations.
C. Sealants
1. Install sealant at locations indicated on Drawings and at locations recommended by glazing manufacturer.
2. Surfaces to receive the sealant shall be dry, clean, free of loose dirt, dust, oil, grease, or other foreign material before application.
3. Install sealant and any associated primers in strict accordance with the manufacturer’s application instructions, including depth-to-width ratio of joints. Verify with manufacturer the appropriate sealant for installation.
Use nozzles sizes which can enter the joints. Apply the material under pressure such as to densely compact the joints continuously and completely fill joints without voids.
4. The installations shall be neat and uniform with no caulking or sealant smeared on adjacent surfaces.
08 80 10-6
D. All roof sheets shall be free of seams and continuous along the entire roof slope from peak to bottom edge of roof (see Drawings for approximate length, verify dimensions with existing conditions).
E. All sheets on gable ends and sidewalls shall be free of seams and continuous along the entire length.
3.3 CLEANUP
A. Coordinate inspection of completed glazing replacement with COR and correct / address any defects / issues identified.
B. After approval by COR, Contractor shall remove all labels on the glazing system and shall thoroughly clean all acrylic surfaces.
C. See Section 01 77 00 for additional information on final project cleaning.
END OF SECTION 08801
Attachments
Notes:
1. The following attachments follow:
a. Material Approval Submittal form
b. Schedule of Material Submittals
c. Recently Replaced Component form
d. AD-107 form
2. Regarding “Material Approval Submittal” form; Contractor shall complete and include this form on each material submittal provided in this project. See “Schedule of Material Submittals” for additional information.
3. Regarding “Schedule of Material Submittals”; schedule indicates a listing of material and information submittals required in the project.
4. Regarding “Recently Replaced Component Form”; Contractor shall complete (with Government assistance) this form and submit to the Government as part of project closeout.
5. Regarding “AD-107” form; Contractor shall complete (with Government assistance) this form and submit to the Government as part of project closeout.
M A
T E
R
IA
L A
P P
R O
V A
L S
U B
M
IT
T A
L T
O : U
S D
A /A
R S
C O
: A
E , C
R
F
O
M : (C o n tra cto
r) P
R O
J E
C T
T
IT
L E
C
O N
T R
A C
T N
U M
B E
R
(T o b e co m p leted b y th e C o n tr a cto r)
G o v er n m en t U se O n ly S
U B
M
IT
T
L
N U
M B
E
P
E V
IO
U
S S
U B
M
IT
T A
L N
U M
B E
(o n ly if item s listed w ere su b m itted p rev io u sly
A eco m m en d a tio
R /E eco m m en d a tio o n tra ctin g O ffic er p p ro v a l/D isa p p ro v a l
L in e
N o
S p ecifica tio n S ect.
P a ra N o
D ra w N o
D escrip tio n o f M a teria l
(In clu d e ty p e, m o d el, m fg
A
P P
S ee
C o m m en ts o n R ev erse
A P
P D
IS
A
P
S ee
C o m m en ts o n R ev erse
A P
P D
IS
A
P
S ee
C o m m en ts o ev erse
If a item is d isa p p ro v ed
, a resu b m itta l is d u e w ith in ca len d a r d a y s o f th e C o n tra c tin g O fficer’s sig n a tu re b elo w
C o n tra cto r A
R
/E o n tra ctin g O ffic er
T Y
P E o r P
R
IN
T N
A M
E
T
IT
T
Y P
E o r P R
IN
T
N A
M E
T
IT
P E o r P
R
IN
T N
A M
E
T
IT
P
E o r P R
IN
T
N A
M E
T
IT
S
IG
N A
T U
R E
S
IG
N
A T
U R
E
S
IG
N A
T U
R E
S
IG
N
A T
U R
E
D A
T E
D
A T
E
D A
T E
D
A T
E
B y co m p letin g th is fo rm
, th e ab o v e sig n ed co n tracto r certifies th at th e m aterial co m p lies w ith all sp ecificatio n s o f th e su b ject co n tract.
D A
T E
R E
C E
IV
E
D F
R O
M K
T R
D
A T
E R
E C
E
IV
E D
F R
O M
A
E
D A
T E
R E
C E
IV
E
D F
R O
M C
O R
M aterial A p p ro v al S u b m ittal C o v er S h eet (1
/2
G H
398A : R eplace G lazing System
, St. Paul, M N
N -A
N -A
N -A
-A
N T
R A
C T
S U
B M
IT
T
A L
C O
M M
E N
In stru ctio n s: E n ter th e in itials o f th e in d iv id u al m ak in g th e co m m en t, th e L in e N u m b er o f th e item fo r w h ich th e co m m en t is b ein g m ad e, an d th e co m m en t.
M aterial A p p ro v al S u b m ittal C o v er S h eet (1
/2
) (R ev erse)
H E
D U
L E
O F
M A
T E
R
IA
L S
U B
M
IT
T A
L S
P R
O
JE
C T
N U
M B
E R
P R
O
JE
C T
T
IT
LE
S O
LIC
IT
A T
IO
N
/C O
N R
T A
C T
N U
M B
E R
T O
B E
C O
M P
LE
T
E D
B Y
C O
R
TO
BE CO
M
PLETED BY CO
N
TRACT ADM
IN
ISTRATO
R
LIN
E N
O
S O
W /P
W S
S
P E
C
IF
IC
A
T
IO
N N
O
ITEM
CERTIFICATE OF COMPLIANCE
SHOP DRAWINGS
SAMPLES
COLOR SELECTION
MANUFACTURER'S RECOMMENDATIONS
MANUFACTURER'S WARRENTY
CATALOG / PRODUCT DATA
OPERATING INSTRUCTIONS
TEST REPORTS
OTHER(SEE SPECIFICATION)
REQ
U
IRED
SU
BM
ISSIO
DATE
D
A T
E
R
D A
N
T R
A C
T
IN
G
F
F
IC
C
E
IV
RETU
RN
SU
SPEN
SE DATE
D A
N
T R
A C
T
T
IF
IE
P R
O V
(IN
E
B
M
IT
T A
L N
U M
B E
R
D
IS
A P
P R
O V
(IN
E
B
M
IT
T A
L N
U M
B E
R
CO
N
TRACTO
R
RESU
BM
ITTAL
FIN
AL APPRO
VAL
REM
ARKS
Specification Section
01 32 00 Construction Schedule
X
Specification Section
01 32 00 Daily Construction Reports
X
Specification Section
01 77 00 Project Record Docum ents X
Specification Section
01 77 00 Docum entation on Diverting Project W aste to Recycle X
Specification Section
01 77 00 Project W arranties X
Specification Section
01 78 00 Project O
M M anual X
Specification Section
08 80 10 Acrylic G lazing Panels X
X
Specification Section
08 80 10 Each Type of Sealant
X
Specification Section
08 80 10 Alum im um
G lazing Cap
X X
Specification Section
08 80 10 Each Type of Fastener
X
Specification Section
08 80 10 Plan on diverting project w aste to recycle X
Specification Section
08 80 10 Docum entation indicating w here sealant is to be applied to glazing system X
Specification Section
08 80 10 Docum entation indicating snow load capacity of new glazing system
X
Attachm ents Recently Replaced Com ponent Form X
Attachm ents
AD‐107
X
SO
W Draw ing ‐ Sheet
Draw ing indicating proposed flashing installation betw een G reenhouse and Link X
SO
W Draw ing ‐ Sheet
Draw ing indicating proposed flashing installation betw een Head House and Link
X
SO
W Draw ing ‐ Sheet
Draw ing indicating proposed transition betw een existing glazing w ith m echanical / electrical penetrations and new glazing system
X
SO
W Draw ing ‐ Sheet
Draw ing indicating proposed installation of piping penetrations at Link roof X
SO
W Draw ing ‐ Sheet
Draw ing indicating proposed installation at transition betw een original G reenhouse and existing G reenhouse addition X
212223
BU
ILDER Facility Condition Assessm ents Recently Replaced Com ponent Form (N ot Repairs)
Location/Site nam e:
Building (CPAIS Asset ID):
Subm itted by:
Contact inform ation:
System
Equipm ent
Year Installed
Location/Room
Q uantity/Area
Serial N um ber
M odel
M anufacturer
Com m ents Attachm ents ld item ew item otes:
1.
If the equipm ent is not replacing another piece of equipm ent please use the new installation form 2.
Please use this form for equipm ent replacem ents as w ell as building im provem ents (i.e. roofing, w indow
, or facade replacem ent projects) greater then $75,000 3.
Please provide a PDF of any docum ents associated w ith the new install
4.
Som e colum ns m ay not be applicable depending on w hat is being added
5.
If you have suggestions on im provem ents/questions regarding this form em ail them to Joshua.N ye@
U
SDA.GO
V or call 301-504-1173
Date: ______________________ mailto:Joshua.Nye@ARS.USDA.GOV Joshua.Nye Stamp
Joshua.Nye Stamp
Joshua.Nye Stamp
Here is an example of an attached Word Doc converted into adobe where we can add details and additional information. PDF items can be attached, other formats will need to be converted to adobe.
Joshua.Nye File Attachment Example attachement.pdf
United States Department of Agriculture
Report of Transfer or Other Disposition or Construction of Property
Report No.
Date
3. Proceeds Received
1. Type of Transaction (Report each type separately)
Transfer Sale Trade In Donation
Construction Rehab As-Is
2. Authorization…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .