SOW-Replace Boilers and DHWH 06 Aug 21.docx

DOCX document 71 KB Posted

Attached to
Replace Boilers Federal contract opportunity
Solicitation number
W911S821B0007
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Joint Base Lewis-McChord

About this file

This statement of work outlines requirements for a construction contract to replace boilers and repair domestic hot water heaters at multiple buildings on Joint Base Lewis-McChord in Washington state. The contractor will be responsible for removing underground storage tanks, installing new boilers and associated piping and controls in five buildings, repairing the energy management control system in four buildings, and replacing domestic hot water heaters in three buildings. The work includes demolition, disposal, and installation of new mechanical equipment, piping, controls, electrical work, and commissioning. The contractor must follow all applicable codes and regulations, coordinate work with the base, and obtain necessary permits.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00

STATEMENT OF WORK

CONSTRUCTION

IFB Final 06 Aug 2021

1. GENERAL DISCUSSION

1.1. Project Identification

1.1.1. Project Title: Replace Boilers (BLDG 12731, 12734, 12737, 12741, 1401) and Repair Domestic Hot Water Heaters (11671, 11672, 11674, 12630).

1.1.2. IJO Number(s): DEJ176617J - Replace Boilers 12731, 12734, 12737, 12741, 1401 DEJ185848J - Replace DHWH BLDG 11671, 11672, 11674 DEJ176397J - Repair DHWH 12630

1.1.3. Project Package Number(s): PS2125

1.2. Description of Work

1.2.1. The contractor shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with the contract, this statement of work, and identified drawings to replace heating boilers and domestic hot water heaters (DHWH) in buildings identified below.

1.3. Area Description

1.3.1. Location: Buildings are located on JBLM-Main and JBLM-North.

1.3.1.1. Buildings 12731, 12734, 12737 and 12741 are Company Operations Facility (COF) are located between 10th and 12th Street, JBLM-North

1.3.1.2. Building 1401 is a Training Support Center located on West 6th Street JBLM-Main near DuPont Gate and I-5.

1.3.1.3. Buildings 11671, 11672, 11674 are Army barracks and located on 41st Division Drive and C Street.

1.3.1.4. Building 12630 is a Barracks located on 41st Division Drive and D Street JBLM-North.

1.3.2. Known Existing Site Conditions

1.3.2.1. The heating boilers in buildings 12731, 12734, 12737, 12741 & 1401 have failed or failing and require replacement. All heating boilers are located in the building mechanical room.

1.3.2.2. The DHWH in buildings 11671, 11672, 11674 are either failed or failing and require replacement.

1.3.2.3. The DHWHs in building 12630 are short cycling and require both piping and control changes to reduce the short cycling of the heaters.

1.4. Principal Items To Be Accomplished:

1.4.1. CLIN 0001 –Replace five (5) boilers in Buildings 12731, 12734, 12737, 12741, 1401, DEJ176617J, Repair

1.4.1.1. Clean and flush existing heating piping using a product similar to CH2O Clean-N-Flush. The existing boiler shall remain connected. Follow manufacturer’s instructions for cleaning and length of time. Clean strainers as required. Flush the system to the floor drain until the discharge water is running clear. Attach fittings as required to perform the flushing and obtain a DPW discharge permit prior to cleaning. The application may be obtained at https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/wastewater

1.4.1.2. Remove and properly dispose of the following items: Note, all construction and demolition waste shall be documented and submitted to the Government per the DPW CD Diversion and Disposal Reporting Instructions 032612.

a. Demolish all material on Boiler loop to include existing boiler, piping, drains, boiler pump, valves, unions fittings, flue, electrical, gas piping as required to install new boiler per Attachment #3 Boiler Schematic and manufacturer’s installation instructions. See Attachment #1 COF Mechanical As-Built and Attachment #2 BDLG 1401 As-built for existing configurations.

b. For buildings 12731, 12734, 12741, demolish 3-way valve, expansion tank, building pump on building loop

c. For building 1401, drain fuel oil lines back to tank and pump tank. Remove all fuel lines, supports and above ground tank and properly dispose of IAW state laws.

1.4.1.3. Install or add to existing concrete equipment pad. Pad shall be larger than equipment with chamfered or finished edges. Equipment shall be securely anchored to the pad.

1.4.1.4. Provide and install boiler in accordance with this SOW, Attachment #3 Boiler Schematic, and manufacturer’s instructions with all required additional piping, fittings, flue, and electrical for a complete and usable heating water system. Maintain clearances around and over equipment and arrange all electrical conduit, piping, exhaust vent, and air intake with clearances for service of all equipment.

a. Boiler specifications shall include: (an example of a boiler meeting these specifications is the Thermal Solutions EVS with the TSBC Control System):

(1) 500 MBH input / 431 MBH output, 6.1 gallon non-condensing heating boiler. Shall be a factory assembled, wired, and fire tested, complete with a natural gas manifold, burner, blower, heat exchanger, and controls all mounted in a steel exterior jacket cabinet. The exterior jacket cabinet shall be made of 16 gauge steel protected with a powder-coat finish. Include factory fire test with each unit.

(2) Minimum thermal efficiency of 87% operating on natural gas.

(3) The gas train manifold shall be UL/FM/CSD-1 compliant and certified to take a maximum of 5 psi Natural Gas. The manifold shall also have a pilot and main gas pressure regulator and automatic main and redundant gas valves and a normally open vent valve in between (i.e. double block and bleed).

(4) The burner shall be a radiant non-corroding ceramic burner, with no moving parts. Burner operation shall be Full Modulation utilizing a VFD and an air-fuel ratio valve. The burner shall emit no more than 9 ppm NOx and 50 ppm CO (corrected to 3% O2) at all firing rates.

(5) The blower shall be equipped with a replaceable combustion air filter. The unit shall have the capability of sealed, direct, or conventional venting.

(6) The heat exchanger shall be constructed with straight, integral copper-finned tube and gastketless header at the top and bottom of exchanger. A stainless steel “V” baffles shall be used between each tube to provide uniform heat distribution of the flue gases across the entire heat exchanger.

(7) The control sequence shall be monitored by a UL approved, commercial-type microprocessor control system with integrated operator interface on the front of the unit. The controls shall shut down the burner in the event of ignition pilot and/or main flame failure with a manual reset. A back-lit display to monitor boiler inlet and outlet temperature, system temperature, outside air temperature, fire rate set point, modulating percent, and mixing valves demand. The display shall include alarm messages, hold and lockout messages, and boiler inlet temperature history.

(8) A 120v/1ph transformer will be required for each control system. Transformers shall be factory mounted.

(9) Water trim and controls shall include 125 psig relief valve, a combined water pressure and temperature gauge, a water flow switch to prevent burner operation during low water flow conditions on the boiler outlet piping. An adjustable high limit temperature controller with manual reset to prevent water temperature from exceeding a safe system temperature and an Auxiliary Low Water Cutoff with manual reset and an alarm bell.

(10) A secondary external mechanical float type low water cut off with “test and check” on boiler supply with automatic reset. The valve shall have an adjustable built-in vacuum breaker in the upper valve to allow for the rapid evacuation of the water from the float chamber without draining the building pipe drain to floor drain.

(11) Install new AL 29-4C, UL listed stainless steel flue with built in mechanical locking band and gasket. Install condensate drain, chimney pass through, flashing, and supports.

(12) Boiler controls shall be digital and designed for stand-alone or easily integrated into EMCS. Features shall include advance boiler modulation, outdoor air temperature reset, warm weather shutdown, multiple auxiliary device control (pump, 3-way valve). Controls shall have Modbus interface included to allow for future EMCS connection for monitoring and control of both heating boilers and domestic HW heater.

1.4.1.5. Heating piping shall be configured in a boiler / building loop connected by a close-couple tee as depicted in Attachment #3 Boiler Piping Schematic.

a. On the boiler loop install all new piping, valves, pump, MLWC, gauges, and fittings as depicted in Attachment #3. Balance boiler circuit setter to maintain constant flow to the boiler. Boiler Pump GPM shall be less than Building Pump GPM.

b. On building loop install new piping, fittings, pump(s), and expansion tank matching existing building as-built. Install new air separator, chemical feed tank. Existing pump(s) shall be provided to DPW. Expansion tank shall be ASME certified, heavy duty butyl diaphragm, 125 psi working pressure, with bladder monitor and pressure gauges. Install new isolation valves.

c. Piping shall be full size schedule 40 black piping conforming to ASME A53/A53M or Type L copper pipe to match existing. Fittings conforming to ASME B16.3.

d. All fittings (elbows, tees, unions, circuit setters, and balancing valves, etc), shall be brass, bronze, or match existing pipping.

e. Isolation valves shall be full port ball valves for 3” pipe size and smaller. Use butterfly valve for greater than 3”. Butterfly valves are acceptable if groove piping is used.

f. Drain lines shall be full size Type L copper pipe unless otherwise specified.

g. Copper soldered joints shall be made with flux for lines 2 inches or smaller.

h. Piping and conduit shall be properly supported and fixed.

1.4.1.6. Connect existing natural gas (NG) piping to unit’s gas train inlet to include; low point drain, main gas and pilot light regulators, isolation ball valves. Use full size black gas piping. Label each pipe (supply, vent). Use full size schedule 40 black gas piping conforming to ASME A53/A53M. Fittings conforming to ASME B16.3.

1.4.1.7. Install new AL 29-4C, UL listed, stainless steel flue with built in mechanical locking band and gasket for Category 2 or 4 venting per National Fuel Gas Code / NFPA 54 ANSI Z223.1 and by boiler’s manufacturer instructions. Develop a positive flow adequate to vent gasses to the outdoors. Support at intervals no less than 5’ apart. Install condensate drain with clear silicone tube (an example is Silbrade tubing) reinforced with braided mesh and piped to the floor drain. Roof penetration shall be sealed from weather.

1.4.1.8. Install new electrical wire, conduit, disconnects, and circuit breakers as required powering all equipment. Set screw connectors shall not be used on new conduit.

1.4.1.9. Install line voltage carbon monoxide detector in mechanical room.

1.4.1.10. Install new pipe insulation. Piping shall be insulated with 1” mineral fiber insulation (ASTM C574) or 1.5” cellular glass (ASTM C552) with factory applied protective jacket. Corners shall have PVC jacket. Seal the ends of pipe insulation with brush coat of low emission waterproof vapor barrier coating. Install name and directional labeling on each type of piping for heating water (Supply, Return). See section 14.4 Stainable Acquisition.

1.4.1.11. Label all mechanical equipment and each zone with durable identification tags.

1.4.1.12. Flush the entire piping system and boiler per manufacturer’s recommendations and clean strainer. Add makeup water and provide water testing. Per test results, add required chemicals per boiler manufacturer’s requirements.

1.4.1.13. Install factory outside air (OSA) temperature sensor on north wall and program boiler for startup, modulation, pump startup, 3-way valve operation, OSA reset, and boiler shutdown. On a call for heating DDC shall enable boiler. Boiler shall enable pump and modulate 3-way mixing valve to maintain return water temperature above 140ºF. Set boiler supply temperature range from 140°F at 65°F OSA to 180°F at 35°F OSA. DDC shall disable boiler above 65°F OSA.

1.4.1.14. For BLDG 1401 integrate new boiler into the existing building EMCS per JBLM 230923 specification.

1.4.1.15. Install Boiler Emergency Stop at entrance to mechanical room. Stop shall remove power from the boiler.

1.4.1.16. Perform boiler start up by manufacturer’s representative with DPW present for safety checks.in accordance with the manufacturer’s documentation.

1.4.1.17. The boiler shall be inspected and tested by a Washington State Boiler Inspector with Washington State boiler inspection certificate.

1.4.1.18. Install a laminated warranty tag; stating contractor’s name, point of contact with phone number, Government point of contract, date of installation, and warranty dates. Attach with zip tie on equipment in noticeable location and completed before Government final inspection.

1.4.1.19. Install an O&M clear plastic tote on or near boiler, properly labeled “BLDG ---- Boiler O&M”.

1.4.2. CLIN 0002 – Repair HVAC DDC Energy Management Control System (EMCS) in BLDGs 12731, 12734, 12737 and 12741, Repair work (“K”).

1.4.2.1. Replace existing EMCS - HVAC control system with new Direct Digital Controls (DDC) for a complete and operational HVAC system. The DDC shall integrate into the JBLM’s Tridium N4 based Energy Monitoring System (EMCS) to achieve full operational control of the HVAC system per the revised control shop drawings. Buildings 12734 and 12741 have a new N4 JACE installed at the building and shall be incorporated. The new DDC system shall allow for maintenance by Government personnel. The HVAC system’s performance shall conform to the JBLM DDC Standard SECTION 23 09 23, “DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING SYSTEMS.”

1.4.2.2. Update DDC Shop Drawings based on Attachment #4. Drawings shall include: table of contents, equipment schedule list, bill of materials, panels, system architecture, communication floor plan, line drawings of equipment, sequence of operations for equipment, and controller wiring schematics. Contractor to assume a new control system will be installed replacing all control components as listed in Attachment #4 (controllers, actuators, temperature sensors, current sensors, relays, controlled hydronic valves, control wire, etc). Include HVAC Emergency stop at entrance to the building with cover and Boiler Emergency Stop at entrance to mechanical room. Existing conduit may be reused as required to route new control wire. A new Tridum based N4 JACE has been installed and shall be incorporated.

1.4.2.3. Demolish all existing control system materials, (except N4 JACE) in order to install new control system per Government-accepted shop drawings. This shall include all existing controllers, actuators, room temperature controllers, hydronic control valves, sensors, and control wires on all equipment. Existing conduit may be reused as required to route new control wire. Access to occupied spaces shall be coordinated with occupant and DPW QA.

1.4.2.4. Install DDC per Government-accepted shop drawings. Install new LON rated communication wire. Plenum rated wire is acceptable above ceiling tile outside mechanical rooms without conduit. Use conduit inside mechanical rooms. Access to occupied spaces shall be coordinated with occupant and DPW QA.

1.4.2.5. Generate new graphics per specification 23 09 23, “DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING SYSTEMS.

1.4.2.6. Archive JACE to Tridium Work Bench Software in BLDG 2012 to include alarms and history, navigation to supervisor, and pdf copies of shop drawings.

1.4.2.7. Coordinate and provide Performance Verification Testing (PVT) with DPW EMCS Administrator. Generate a list of any non-functioning mechanical equipment and provide to the Government.

1.4.2.8. Provide 7 day trend after PVT and coordinate Trend Meeting with Government DPW EMCS Administrators. After review meeting, make adjustments to programing as required by DDC System Managers.

1.4.2.9. Install laminated 11x17 control shop drawings and O&Ms in mechanical rooms.

1.4.3. CLIN 0003 – Remove Underground Storage Tanks – 12731, 12734, 12737 and 12741. DEJ176617J, Repair

1.4.3.1. Remove four (4) 2000 gallon Underground Storage Tank (UST) and all associated components in accordance with the UST closure and replacement requirements of Washington State Department of Ecology regulation See Attachment #5 Fuel Tank As Built. Pierce County Health Department regulations, OSHA standards, and JBLM standards. Removal includes but not limited to the concrete top deck, manhole covers and frame, riser, fill ports, tank, and leak detection components. Concrete base and wire anchors may be abandoned in place. All decommissioning activities shall be witnessed by a Washington Department of Ecology Certified Site Assessor in accordance with API Recommended Practice 1604 – Closure of Underground Petroleum Storage Tanks. Soil samples shall be collected by a Washington State certified Site Assessor. All clean‐up levels will comply with MTCA Method A under WAC 173‐340‐900. See building’s mechanical as-built for UST location of tank and equipment. Submit all certifications to the Government for acceptance prior to starting any on site construction.

1.4.3.2. The contractor shall:

a. Notify DPW Environmental, Doug Skitch 966-1779, prior to excavation.

b. Obtain a Pierce County Health Permit per FL Reg 200-1 Environmental Protection and Enhancement Appendix O Underground and Aboveground Storage Tank paragraph 2e for tanks above 1100 gallons. Submit permit as submittal to the Government before construction.

c. Pump out and recycle fuel oil prior to removing tank. Provide the Government with receipt in submittal format. Contractor to assume tank is full.

d. Excavate tank and remove accessible piping from the tank to the building. Place all excavated material on 6 mil plastic.

e. Flush, rise, and cap all piping to be abandoned from the mechanical room to the tank. All waste water shall be collected on site, removed and properly disposed of with receipts.

f. Use the triple rise method for tank cleaning and accomplished prior to transport. All waste water shall be collected on site, removed and properly disposed of with receipts.

g. Before any soil is backfilled, perform and obtain soil samples in accordance with the Minimum Soil Sampling Requirements for Site Check and Site Assessments section found in the Department of Ecology’s Guidance for Site Checks and Site Assessments for Underground Storage Tanks and per the Site Assessor requirements, see Tables 1 and 2 below. Excavated and pit soils samples shall be tested for Diesel (NWTPH-Dx) and Benzene, Toluene, Ethylbenzene, Xylene (BTEX) by EPA 8260. Submit all test results to the Government in submittal format. Submit test results to Pierce County Health Department to close the permit.

Table 1 -Number of Samples for Excavated Soil

Cubic Yards of Soil
Minimum Number of Samples
0‐100
3
101‐500
5
501‐1000
7
1001‐2000
10
>2000
10+1for each additional 500 cubic yards

Table 2 -Number of Samples for Excavation Pit

Tank Size, Piping, Pipe Island
Minimum Number of Samples
<20,000
3, one at each end and at the middle
>20,000
5, one at each side wall and one in the middle
Per 50 feet of piping
1
At base of island
1

h. If all excavated soils and pit samples with product contamination levels below 2,000ppm for NWTPH‐Dx and below 0.03mg/kg of BTEX from all sample locations the pit shall be backfilled with the excavated soil. Backfill excavation with compacting in 12” lifts. Add additional acceptable backfill material as required to fill excavation.

i. If any of the excavated soils or pit samples have a product contamination level above 2,000ppm for NWTPH‐Dx and above 0.03mg/kg of BTEX it will be considered an unforeseen site condition and the Contracting Officer shall be notified.

j. Install 4” of topsoil on top of compacted base material, add fescue grass seed and ½” of peat moss top coat.

k. Remove all additional fuel oil related materials from the mechanical room (piping, filters, supports, etc).

l. Remove all leak detection equipment, panels, alarms, and all electrical (conduit, wire, and breakers) associated with the system.

m. Submit Site Assessors Report of all removed tanks to the Government as a submittal.

1.4.4. CLIN 0004 – Replace DHWH in Building 11671, 11672, 11674, DEJ185848J Repair Note: Replacement of the DHWH may be sequenced with coordination with DPW.

1.4.4.1. Install a temporary domestic hot water heater (DHW) system with a minimum of 1000 MBH capacity and 500 gallon storage tank. Contractor may sequence the replacement system at each building. Connection points to the existing piping to be determined by the contractor. All hoses shall be new and designed for DHW. Contractor to decide best heating method. Connection to the building’s natural gas and electrical is acceptable. Coordinate with DPW on the cut over times. Cut over times should not exceed 4 hours and scheduled after 0900. The temporary DHW heater shall be inspected by DPW personnel and shall be operational before demolition begins.

1.4.4.2. Remove existing 1000 MBH DHW heater, AO Smith NG heater, piping, valves, fittings, flue, intake duct, pumps, and electrical as required to install two new DHW heater in accordance with Attachment #6 - DHW Piping Schematic and manufacturer’s installation requirements. The electrical (conduit, wire) shall be removed back to panel or nearest junction box. The contractor shall not abandon any piping or electrical. All recycled materials and waste shall be documented per the DPW CD Diversion and Disposal Reporting Instructions 032612. The TS EVAW in building 11674 shall be turnover to DPW and not demolished.

1.4.4.3. Demolish existing vinyl floor tile in mechanical rooms and remove adhesive using an adhesive solvent and remover to leave a bare concrete finish. Apply a concrete sealer following manufactures directions. Adhesive shall meet biobaseed content requirements per paragraph 13.4 and be on contractor’s Authorized User List, per paragraph 13.6. Floor shall be wet mopped cleaned following demolition and prior to final inspection.

1.4.4.4. Provide and install new 1000 MBH input /980 MBH output, 1188 gph recovery rate, condensing hot water heater with a 98% thermal efficiency and 97% combustion efficiency in buildings 11671, 11672 and 11674.

(1) Hot water specifications include (an example that meets these requirements is the Thermal Solutions AMPW1000):

(a) ASME 316L Stainless steel water tube heat exchanger

(b) Stainless steel mesh pre-mix burner

(c) Direct Spark Ignition and UV Scanner

(d) Full Modulation, 5:1 Turndown

(e) Heater Control with 4.3” Color Touch Screen.

(f) Manual Reset High Limit Temperature Control

(g) Water Flow Switch

(h) Manual Reset Probe Type Low Water Cutoff

(i) Manual Reset High & Low Gas Pressure Switches

(j) Supply & Return Temperature Sensors

(k) Flue Gas Temperature Sensor

(l) Condensate Trap

(m) Vent Outlet & Air Intake Connections

(n) 120/60/1 Electrical Power Strike

(o) <10 PPM NOx

(2) Install the following on site:

(a) ASME Safety Relief Valve

(b) Temperature Gauge

(c) Alarm and Silence Switch

(d) Condensate Neutralizer Kit

(e) Storage Tank Sensor

(f) LONworks Communication Card

1.4.4.5. Install all piping and components as depicted in Attachment #1-DHW Piping Schematic. Contractor to note the piping changes from original as-built configuration. Replace all failed piping, valves and components. Mineral build up on a joint or valve is considered failed and shall be replaced. Size to match the existing or per Attachment #6 Piping Schematic. Replace all Replace all failed temperature thermometers on DHW system in mechanical room. Size and type shall be like-in kind.

(1) .All DHW piping shall be full size Type L or match existing copper pipe conforming to ASTM B88 unless otherwise specified by manufacturer.

(2) Drains maybe Type L copper or schedule 40 PVC.

(3) Unions and piping fittings /components shall be brass or bronze with no lead, suitable for domestic water.

(4) Soldered joints shall be made with flux and are only acceptable for lines 2” diameter and smaller.

(5) Grooved or pressed connections are acceptable for greater than 2” diameter.

(6) All contractor installed piping shall be new, clean, and properly supported and secured.

(7) Isolation valves 3” and smaller shall be full port ball type with stainless steel trim. Use butterfly valves for greater than 3” diameter piping.

1.4.4.6. Heater pump shall be inline bronze/stainless steel flange type, UL approved, and sized for a 20°F temperature rise maintaining proper flow to heater. Heater control system shall control heater pump.

1.4.4.7. Install condensate trap assembly with factory neutralizer on flue and heater drain. Use Silicone tubing (an example is Silbrade tubing) shall be reinforced with braided mesh or schedule 40 PVC and piped to the floor drain to prevent collapsing or pinching.

1.4.4.8. Install full size schedule 40 black gas piping conforming to ASME A53/A53M to unit’s gas train inlet to include; low point drain, main gas and pilot light regulators, isolation ball valves and piping to atmosphere. Fittings shall conform to ASME B16. Label all NG piping with name and paint NG piping yellow.

1.4.4.9. Install a new AL 29-4C, UL listed stainless steel flue with built in mechanical locking band and gasket. Install condensate drain, chimney pass through, flashing, and supports.

1.4.4.10. Install new electrical (wire, conduit, disconnects and circuit breakers) meeting the requirements of the new heater and pump. Demolished wire and conduit shall be removed back to nearest junction box. Do not use screw set connectors on conduit.

1.4.4.11. Install new diaphragm expansion tank with new isolation valve, pressure gauge and bladder monitor. Size to match existing as-built. Tank shall be ASME certified, heavy duty butyl diaphragm, with a 125 psi working pressure.

1.4.4.12. Insulate all exposed (new and existing) piping with 1” mineral fiber insulation (ASTM C574) or 1.5” cellular glass (ASTM C552) with factory applied protective jacket. Corners shall have PVC jacket. For missing or failed insulation match existing thickness of remaining insulation. Seal the ends of pipe insulation with brush coat of waterproof vapor barrier coating. Insulation shall comply with applicable recycled content requirements per paragraph 13.6. Vapor barrier shall meet low emissions requirements at UFC 1-200-02. Include on contractor’s AUL.

1.4.4.13. Install name and directional labeling on each type of piping over insulation jacket according to the sequence of operation. Remove any failed or missing directional and pipe labels on the DHW system in the mechanical room. Color of tape shall be yellow for DHW and green for DCW. Install new valve tags labelling “normally open” and “normally closed” according to the sequence of operation

1.4.4.14. Connect the DHW system to the building’s existing base wide Energy Management Control System (EMCS). Heater shall operate when either storage tank temperature falls below 140F.

(1) Set on-board heater controls to command heater pump operation on a call for heating.

(2) Monitoring points: status of pump, HW supply leaving heaters, HW temp supply, upper and lower storage tank temperature.

(3) Conduct a Performance Verification Test (PVT) on heater with DPW HVAC EMCS Manager.

1.4.4.15. Connect heater and existing boilers to one Emergency Stop at entrance to mechanical room. Button shall cut power and not through EMCS controls.

1.4.4.16. Install durable identification tags for DHW Heater System matching EMCS graphics.

1.4.4.17. Install a laminated warranty tag; stating contractor’s name, contract number, Government point of contact with phone number, date of install, and warranty dates. Attach with zip tie on equipment in noticeable location and completed before Government final inspection.

1.4.4.18. Install an O&M manual metal holder or plastic tote on or near heater, properly labeled “DHW Heater O&M”. Place all Government approved Operation & Maintenance in holder.

1.4.4.19. Clean mechanical room of all debris and wet mop floor before final Government inspection.

1.4.4.20. Perform heater start up and tuning by manufacturer’s representative with DPW present for safety checks in accordance with the manufacturer documentation.

1.4.4.21. The heater shall be inspected and tested by a Washington State Boiler Inspector with Washington State boiler inspection certificate.

1.4.5. CLIN 0005 – Repair Domestic Hot Water Heater Piping – BLDG 12360, Repair work (“K”) DEJ176397J

1.4.5.1. Background: Two 2000 MBH DHWH were installed in 2018 with two 750 gallon storage tanks. Each heater is piped to its respective storage tank with a common pipe between them. During startup, it was discovered the heaters could not be configured in Primary / Secondary configuration feeding both tanks due to the location of the temperature sensors. The common pipe was closed and each heater heats its own respective tank. After two years of monitoring the heater’s cycle run times it was discovered they are excessive and could possibly shorten the life of the heater. It appears the actual usage is not matching the calculated usage for the barracks.

1.4.5.2. Contractor shall modify piping and control system to allow one heater to heat both tanks. The supply and return piping shall be balanced from the heaters to the tanks to each tank is equally supplied with hot water to the design temperature of 140°F. Heaters will change as Primary heater by EMCS control system according to a schedule. The hot water supply piping to the building shall also be repaired to balance piping to pull equally from both tanks.

2. PERFORMANCE AND SCHEDULING

2.1. Performance Period Requirements

2.1.1. The Contractor is required to commence work under this Contract within ten (10) calendar days after the date of issuance of the Notice to Proceed (NTP) for the Base Item(s), prosecute the work diligently, and complete all work on all Base Item(s) no later than 360 calendar days after the date of issuance of the Notice to Proceed for the Base Item(s). The time stated for completion includes final cleanup of the premises and submission of all required close-out documentation.

2.2. Construction Phasing Requirements

2.2.1. Reserved.

3. SUBMITTALS

3.1. Project Submittal Requirements All submittals shall be submitted electronically (emailed) to the Government Project Manager (PM) in Adobe Acrobat .pdf format. A ENG Form 4025 shall accompany each submittal. These forms will be furnished to the Contractor by the PM. The submittal file name shall be in the format “Contract # – submittal #, submittal name” for example; “0020-001 RTU”. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Drawings if required by the SOW shall be in ACAD format and a second electronic copy in PDF format.

3.1.1. Pre-Construction Submittals:

(1) Quality Control Plan

(2) Accident Prevention Plan

(3) Site Specific Environmental Protection Plan

(4) Construction Schedule

(5) Training and Completion Letters (AT/FP, OPSEC, iWATCH, E-Verify)

3.1.2. Construction Submittals:

(1) Manufacturer’s equipment specification sheets. All applicable items such as model numbers, sizes, and accessories shall be indicated using arrows or highlight.

(2) Applicable materials meeting specifications of SOW.

3.1.3. Closeout Submittals:

(1) Operation and Maintenance (O&M) manual to include:

(a) Contractor’s Warranty Letter

(b) Equipment operations and maintenance manual

(c) Startup and test reports

(d) Checklists

(2) One printed Operation and Maintenance (O&M) manual in 3-ring binder The Contractor shall provide a letter of non-retention for all contract documents, plans, drawings, and specifications after the destruction of all copies that are not required by the contractor to meet legal requirements.

4. DRAWINGS , SPECIFICATIONS & CODES:

4.1. Drawings

4.1.1. The drawings outlined below are attached. - See Attachments.

Drawing Number
Sheet Number
Title
Rev Number
Date

4.1.2. Dimensions and utility locations are approximate and must be verified in the field.

4.2. Specifications

4.2.1. none

4.3. Codes

4.3.1. The Contractor shall comply with all pertinent local, State, and Federal building life/health/safety codes as listed.

a. Applicable Unified Facilities Criteria (UFC)

b. UFC 1-200-01: General Building Requirements http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01

c. UFC 1-200-02: High Performance and Sustainable Building Requirements https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02

d. ASA IE&E SDD policy https://www.wbdg.org/FFC/ARMYCOE/POLICY/Army_SDD_Policy_Update_2017.pdf

e. UFC 1-201-01 Non-Permanent DOD Facilities in Support of Military Operations

f. EM 385-1-1 (http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx)

g. National Electrical Code, NFPA 70

h. National Plumbing Code

i. National Fire Protection Association (NFPA) Codes

j. Telecommunication Industry Association/Electrical Industry Association Wiring Standards (Building Telecommunication Wiring Standards)

k. Army Installation Information Infrastructure Architecture Policy (I3A)

l. JBLM Design Standard specifications (http://www.lewis-mcchord.army.mil/designstandards/)

m. JBLM 420-1 (2017); https://intra.lewis-mcchord.army.mil/dhr/forms/hfl/PubsSite/index.htm

n. JBLM Master Plan, which includes Architectural Appearance Standards

o. PWE-707, Standard Operating Procedure for Construction and Demolition (C&D) Waste Planning and Reporting (Available through Government Project Manager)

p. National Pollutant Discharge Elimination System (NPDES) small Municipal Separate Storm Sewer Systems (MS4) Permit No. WAS-026638. Use guidance documents found at https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater

5. SAFETY:

5.1. USACE Safety and Health Requirements Manual (EM 385-1-1), available online at https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf shall be considered to be a part of this contract and will be enforced as such. The Contractor shall prepare an accident prevention plan in accordance with the most current version of EM 385-1-1.

6. CONTRACTOR QUALITY CONTROL (CQC) DAILY REPORTS:

Maintain current daily records providing factual evidence that required quality control activities and/or tests have been performed. Contractor shall use the Government-provided daily inspection form. Daily inspection forms shall start at first day of on-site construction and continue until the final inspection date. Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; equipment on site, and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Furnish the electronic copy of the report to the Government daily within 24 hours after the date covered by the report. Reports need to be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the Contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC Manager or Site Superintendent.

7. CONTRACTOR PERSONNEL AND SUB-CONTRACTOR QUALIFICATIONS

7.1. The Government will not exercise any supervision or control over contractor or subcontractor employees performing work under this contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the Government for all contractor employees.

7.2. The Contractor shall take appropriate personnel action, as required, in the event any employee becomes involved with civilian or local authorities because of misconduct. The Contractor’s employees are subject to the same general rules of conduct while on the Government installation that apply to Government civilian employees.

7.3. The Government reserves the right to refuse access to Government installation grounds to any contractor employee if the KO determines it to be in the best interest of the Government.

7.4. The Contractor shall not allow any employee to perform work under the contract while under the influence of alcohol, drugs, or any other incapacitating agent.

7.5. The Contractor shall provide a Site Superintendent at the work site during any construction and shall be the main point of contact for the Government QA. The Site Superintendent shall not be delegated to a subcontractor.

7.6. The Contractor shall provide a Site Safety and Health Officer (SSHO) as required in the EM385-1-1. The Contractor SSHO may be assigned other duties in addition to the duties required as SSHO. The SSHO may not be delegated to subcontractor.

7.7. The Contractor shall provide a Construction Quality Control (CQC) System Manager. The CQC System Manager may be assigned other duties in addition to the duties required as CQC System Manager. CQC System Manager may be the Superintendent, Project Manager or Lead Trades person. The CQC may not be delegated to subcontractor.

7.8. The Site Superintendent, Safety and Health Officer, and Construction Quality Control may be the same person but not delegated to subcontractor.

8. CONTRACTOR INSPECTIONS

8.1.1. Near the completion of all work or stated elsewhere in the specifications, the QC Manager shall conduct an internal inspection of all the work performed to ensure it meets all the requirements of the contract. Once this is accomplished, contractor shall notify the Government that the facility is ready for the Government pre-final inspection. The contractor shall give 5 working day notice to the Government Quality Assurance Representative when requesting a pre-final inspection.

8.1.2. Pre-Final Inspection and Punch List Items. Upon request for a pre-final inspection, the Government will schedule a pre-final inspection to verify that the facility is complete and ready to be occupied. For this inspection to commence a representative from contractor, Directorate of Public Works (DPW), and Contracting shall be present. A Government pre-final punch list may be developed as a result of this inspection which shall detail the items needing correction. The contractor’s QC Manager shall ensure that all any items noted on the pre-final inspection have been corrected within 7 calendar days. Once these items have been addressed, contractor shall notify the Government to request a final inspection, giving 5 working day notice.

8.1.3. Final Inspection and Acceptance. Upon request for a final inspection, the Government will schedule a final inspection to verify that the facility is complete and ready to be occupied. For this inspection to commence a representative from contractor, DPW, and Contracting shall be present. If all items listed in the pre-final punch list have been corrected, and all work meets the requirements of the Base Contract and TO SOW, Specifications, and Drawings, (if included) the Government shall accept the work and take ownership of the site. If during the pre-final inspection it is discovered that there are no discrepancies, the pre-final inspection may turn into a final inspection.

9. PAYMENT INVOICE: Requests for payment shall be submitted in accordance with Federal Acquisition Regulations (FAR) Subpart 32.9, entitled "PROMPT PAYMENT", and Paragraphs 52.232-5 and 52.232-27, entitled "Payments Under Fixed-Price Construction Contracts", and "Prompt Payment for Construction Contracts", respectively, as well as DFARS Clause 252.232-7003, entitled “ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS”. Requests for payments to be made by DFAS will be submitted via WIDE AREA WORK FLOW (WAWF). Requests for payments to be made by paying offices other than DFAS shall be submitted in the number of copies and to the designated billing office as indicated in the Contract. WIDE AREA WORK FLOW: See DFARS Clause 252.232-7003 .The payment requests shall be emailed to the DPW Procurement Technicians. The e-mail shall include a copy of the invoice, the release of claims and the invoice checklist. The email subject line name shall include contract number and Invoice number. Upon approval from DPW, the Contractor is then required to use Wide Area Work Flow (WAWF) to electronically submit invoice payment requests. The contractor is also required to submit the Release of Claims in WAWF for final invoice payment requests. For approved invoice checklists, input the invoice information into WAWF and send a WAWF generated e-mail to the Procurement Technician and Inspector. For disapproved invoice checklists, make the necessary corrections and submit a new invoice and invoice checklist.

10. ELECTRONIC FILE FORMATS: The Contractor shall establish and maintain the capability to open, create, and send all documents, including contract submittals in Microsoft Office (EXCEL, WORD, PROJECT, etc.), Adobe Acrobat (.pdf), and other similar formats.

11. ELECTRONIC MAIL (E-MAIL) ADDRESS: The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. The Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for quotes, and other correspondence. The Contracting Officer may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple e-mail addresses will not be allowed. It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.

12. ENVIRONMENTAL AND CULTURAL RESOURCES

12.1. Asbestos Containing Material

12.1.1. Existing suspect materials involved with all disturbance work are assumed to be Asbestos-Containing Material (ACM). It is the contractor’s responsibility to either test for, or to assume the suspect material is ACM, and that it is abated /encapsulated in accordance with AHERA, Federal, and local regulations. No Asbestos Hazard Emergency Response Act (AHERA) inspection is required when the suspect materials are assumed to be ACM. The Government reserves the right to accept assumptions of ACM-positive, or to require such AHERA surveys to be performed.

12.1.2. Available AHERA survey data will be included with each Contract. The Contractor shall determine the adequacy of the existing survey documentation and include additional AHERA inspections in the proposal if necessary.

12.1.3. When performed, inspections shall be accomplished in accordance with the Asbestos Hazard Emergency Response Act (AHERA), Federal and local regulations. A Certified AHERA Asbestos Building Inspector shall perform all inspections. The inspection documentation shall comply with AHERA, Federal and local regulations and shall include assessment of each Asbestos-Containing Material (ACM), its location, quantity, type, friability and percentage of asbestos.

12.1.4. If the tested material is positive for asbestos, or assumed to be ACM and must be disturbed during project execution, contractor shall have a certified Asbestos Contractor perform all asbestos disturbance work necessary to complete the project in accordance with 29 CFR 1926.1101, WAC 296-62-077, 296-65, and PSCAA Regulation 3.4. A certified abatement plan and all other applicable requirements of ‘UFGS 02 82 00 Asbestos Remediation’ are also required to be submitted and accepted before work is started. If this effort is believed to constitute differing site condition(s), then submit an RFI identifying the situation.

12.2. Lead-Containing Paint

12.2.1. Existing suspect painted surface materials involved in disturbance work will be considered to contain detectable lead paint. It is the contractor’s responsibility to either test for, or to assume the suspect material is either Lead Based Paint (LBP) or Lead Containing Paint (LCP), and that it is abated/encapsulated in accordance with OSHA, HUD, Federal and local regulations. The Government reserves the right to accept assumptions of LCP/LBP-positive, or to require such LCP/LBP surveys to be performed.

12.2.2. Available lead paint survey will be included with each Contract. The Contractor shall determine the adequacy of the existing survey documentation and include additional lead paint inspections in the proposal if necessary.

12.2.3. When performed, testing shall be accomplished in accordance with OSHA and/or HUD guidelines. A Certified Lead Paint Inspector shall perform lead paint inspections. The inspection documentation shall comply with Federal and local regulations and shall include identification of all lead paint, its location, quantity, percentage by weight, and TCLP characteristics IAW ASTM E1908-16, “Standard Guide for Sample Selection of Debris Waste from a Building Renovation or Lead Abatement Project for Toxicity Characteristic Leaching Procedure (TCLP) Testing for Leachable Lead (Pb)”

12.2.4. If the suspect lead containing material is tested and proves positive for lead, or when assumed to be a lead containing painted surface, any disturbance work concerning the painted surfaces shall be in accordance with:

a. Federal level: 29 CFR 1926.62: https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=10641

b. Washington WISHA-DOSH: WAC 296-62-07521 http://app.leg.wa.gov/WAC/default.aspx?cite=296-62-07521

c. A contractor work plan is required to be submitted and accepted before work is started, in accordance with applicable sections of ‘UFGS 02 83 00 Lead Remediation.

d. If this effort is believed to constitute differing site condition(s), then submit and RFI identifying the situation.

12.3. Environmental Coordination

12.3.1. The Contractor shall comply with all Joint Base Lewis-McChord (JBLM) environmental requirements, including the most current installation regulation 200-1 (Environmental Protection and Enhancement) and Design Standards specification section 01 57 19 (Temporary Environmental Controls). This includes the submission of an Environmental Protection Plan prior to commencement, as detailed in section 01 57 19. The JBLM Environmental Division will review the Plan and provide any necessary corrections or additions to the Contracting Officer or the Contracting Offer Representative (COR). Regulation 200-1 and specification section 01 57 19 are available at the JBLM Design Standards website (https://www.lewis-mcchord.army.mil/designstandards/index1.htm).

12.3.2. In accordance with JBLM Reg. 200-3, no construction process water or wastewater shall be discharged to the ground or stormwater conveyance system. Construction discharge must meet requirements of the NPDES Construction General Permit (CGP) for Discharges from Construction Activities and guidance documents under the MS4 Permit. In accordance with JBLM Reg. 200-2, any wastewater generated must be collected, processed, characterized, and disposed of into the JBLM sanitary sewer system or other authorized disposal method. Prior to disposal, waste water characterization must at a minimum include pH, Oil and Grease, BOD, and TSS analysis by a NELAC accredited laboratory. Additional analyses may be required if non-conventional wastes or hazardous materials are potential contaminants. Results shall be submitted for review and approval by Public Works. On site characterization by JBLM Pretreatment staff may waive analytical requirements at the discretion of the Pretreatment program manager. JBLM sanitary sewer discharge requires a Sanitary Sewer Discharge Permit issued by DPW Waste Water Treatment Plant. The Environmental Protection Plan for the project must identify any potential wastewater generation and the process of proper disposal. Contact Stormwater office to coordinate with any stormwater related topics at: as usarmy.jblm.id-readiness.list.dpw-stormwater1@mail.mil

12.4. Sustainable Acquisition

12.4.1. In order to comply with federally mandated sustainable acquisition requirements and Department of Defense (DOD) and Department of the Army (DA) Green Procurement Program (GPP) policies, Joint Base Lewis-McChord (JBLM) requires the purchase, supply, and use of environmentally preferable products and services. Program elements include: recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, and environmentally preferable products. For a listing of designated items, associated requirements and managing program websites, see https://sftool.gov/greenprocurement.

12.4.2. Additionally, the JBLM Guide to Sustainable Acquisition for Construction is available in the “Reference Manuals” section of the JBLM Design Standards webpage (http://www.lewis-mcchord.army.mil/designstandards/index1.htm).

12.4.3. The Contractor shall comply with all applicable Federal, DOD, Army, and JBLM sustainable acquisition laws and policies. If compliant products are unavailable or determined to be impracticable based on cost or performance, the Contractor shall contact the Contracting Officer or the COR for further guidance and exception requirements. Claims of exception must meet applicable legal criteria and be justified in writing through the submission of a completed HJB Form 225 (Sustainable Acquisition Exception). The form is available at usarmy.jblm.id-readiness.list.dpw-green-procurement1@mail.mil Additional information is available from the JBLM Sustainable Acquisition Program at (253) 966-6466 or usarmy.jblm.id-readiness.list.dpw-green-procurement@mail.mil

12.5. Environmental Management System

12.5.1. Environmental Management System (EMS). The JBLM EMS conforms to the criteria defined in the international standard, ISO 14001:2004 Environmental management systems – Requirements with guidance for use.

12.5.2. In accordance with EMS procedures, the Contractor shall be familiar with the JBLM environmental policy and shall ensure that this information is considered and incorporated into this project.