The document is a Statement of Work (SOW) issued by the State of Ohio Adjutant General's Department located in Columbus, Ohio, dated April 10, 2020. The SOW solicits a contractor to replace a failed split unit at the DSCC Building 6 located at 3990 E. Broad St. in Columbus, Ohio. The specific unit to be replaced is a split unit with Model J05ZRC00P4BZZ10005C and Serial Number N1M0486752. Site visits for potential bidders are available on April 3, 2025, and can be arranged by contacting Mr. Thom Thorpe between 7:00 a.m. and 3:00 p.m., Monday through Friday.
The invoicing instructions specify that all invoices must be submitted on company letterhead, including vendor details, invoice number, and itemized description of services or goods delivered, with pricing excluding tax (as the State of Ohio is tax exempt). Invoices can be submitted via email to ng.oh.oharng.mbx.invoices-dimr@mail.mil or by U.S. Mail to the Adjutant General's Department State Finance at 2825 West Dublin Granville Road, Columbus, Ohio 43235. The contractor will be responsible for cleaning the work site daily, removing all materials and debris upon project completion, and restoring the property to safe, normal operating conditions to the Project Officer's satisfaction.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| COMPLIANCE VERIFICATION DOCUMENTATION.pdf | ||
| Environmental_Procedures.pdf_safe (1).pdf | ||
| How to submit a quote.pdf | ||
| Instructions to Bidders.pdf | ||
| Bidder Certification.pdf | ||
| INSTRUCTIONS ON HOW TO REGISTER AS A PAYEE .pdf | ||
| Request for Quotes.docx | DOCX document | |
| Standard Terms and Conditions Ohio.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF OHIO
Adjutant General’s Department
2825 West Dublin Granville Road Columbus, Ohio 43235
April 10, 2020
STATEMENT OF WORK
SW I
SW II
SCOPE
Furnish all labor and materials to perform work in strict accordance with specifications for the project to replace failed split unit at , DSCC Bld 6 (CSMS) 3990 E. Broad St. Columbus, OH 43218.
SITE OF WORK
Work will take place at DSCC building 6 3990 E Broad St, Columbus, Ohio 43218.
SW III WORK TO BE ACCOMPLISHED
1. Contractor shall provide all labor, materials and equipment and perform the
SW IV SITE VISITATION
SW V PERFORMANCE
1. Submittal of a Bid by a Contractor shall be accepted as prime facie evidence that the has examined the Specifications and the Job Site, and has satisfied himself as to the nature and location of the work and all matters which can in any way affect the work or cost thereof, under the contract. Any failure of the Contractor to acquaint himself with following:
Replace split unit Model J05ZRC00P4BZZ10005C SN: N1M0486752
Site visits may be arranged by contacting Mr. Thom Thorpe, Monday through Friday between 7:00 a.m. and 3:00 p.m. by phone at 624-496-1577 or by e-mail at thom.l.thorpe.nfg@army.mil Site visits are available on April 3 2025.
thom.thorpe Cross-Out all available information, including physical survey of the proposed work, will not relive him from successfully performing all work to be done for a complete and acceptable job.
2. The above brief outline of principle features of work in no way limits the responsibility of the Contractor to perform all work and furnish all labor and materials, required by the Specifications referred herein. Any omission from the Specification, or misdescriptions thereof, shall not relieve the Contractor from performing all work required, and furnishing the materials required to completely fulfill the intent of the Contract
3. The Contractor shall confine operations at the site of areas permitted by the Project Officer. He shall not unreasonably encumber the site with materials or equipment and shall assume full responsibility for the protection and safekeeping of products that interfere with the operation of the facility and, if necessary, obtain and pay for additional storage areas.
4. At the completion of each working day, the Contractor shall clean and clear away any excess supplies and debris from the site.
5. Upon completion and before the final acceptance of the work, the Contractor is responsible for the removal of all material rubbish. All property shall be restored to safe, normal operating conditions. The area shall be in a neat, clean, presentable condition satisfactory to the Project Officer.
SW VI INVOICING
1. All invoices should be submitted on vendors company letterhead or standard invoice document to include vendors name, address, remit to address if different from main office, invoice date, invoice number, itemized description of goods delivered or services performed to include pricing less any tax ( The State of Ohio is tax exempt).
2. All invoices should be submitted using one of the methods listed below.
Preferred method:
Email invoices to:
ng.oh.oharng.mbx.invoices-dimr@mail.mil
Alternate method:
U.S. Mail
Adjutant General’s Department State Finance
2825 West Dublin Granville Road Columbus Ohio 43235
END OF SECTION