This statement of work outlines requirements for the purchase and installation of an ion chromatography system for Naval Shipbuilding and Repair Facility Portsmouth in Building 59. The deliverables include a Dionex Ion Chromatography System 6000 comprising a pumping system, detector, autosampler, eluent generator, computer system, mass spectrometer, auxiliary pump, and nitrogen generator. The contractor must be a US citizen with proof of citizenship and the appropriate security clearance to access the facility. Installation is estimated at 40 hours and will be coordinated through the government representative, Tom Oates. The total estimated cost is $232,172.81.

View the file

Other files for this federal contract opportunity

Other files attached to ICS6000 SYSTEM, newest first.
File Type Posted
31418700 THRU 8746 - CDRL MANUALS.pdf PDF
23Q2001 ICS6000 SYSTEM.pdf PDF
Salient Characteristics.pdf PDF
31418700 THRU 8746 - CDRL WARRANTY.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PSNS&IMF 4200/43 (2-16) Page 1 of 3

STATEMENT OF WORK–SERVICE CONTRACT WORKSHEET PSNS&IMFINST 4200.14

CHECK ALL THAT APPLY:

HIGH RISK (Justify in No. 12 below)

SUBSAFE Fly By Wire DSS SOC

WORK IS WITHIN: ENGINEERING SPACE PROPULSION PLANT SYSTEM

(Review NAVSEAINST 9210.4B for applicability)

JML No.: 31418700 THRU 8747

NAVCOMPT 2276 No.: (Request for Contractual Procurement (RCP) required for services over $2,500 or services with terms and conditions.)

Ship/Activity: Code 134.

Title: Purchase and Installation of Ion Chromatograph/MS System

Place of Performance: Bldg. 59

Period of Performance: Year-round

Estimated Cost: ~$232,172.81(check final quote)

Source of Estimate: Vendor quote

REFERENCES: NA

1. BACKGROUND: Purchase and Installation of Ion Chromatograph/MS

System

Describe current (baseline) condition: NA (new equipment that has not been purchased or received yet)

2. SCOPE: Purchase and installation of Dionex Ion Chromatography

System 6000 (NEW).

3. DELIVERABLE ITEMS: Delivery and installation by a manufacturer representative of the Thermo Fisher Dionex Ion Chromatography System

6000 that includes a pumping system, DC detector, autosampler, eluent generator, computer system, ISQ™ EC Single Quadrupole Mass

Spectrometer, AXP-MS auxiliary pump, and nitrogen generator.

PSNS&IMF 4200/43 (2-16) Page 2 of 3

4. CONTRACTOR FURNISHED MATERIAL: See JML(s) and vendor-provided quote for an estimated list of materials, part numbers, quantities, and prices.

5. GOVERNMENT-FURNISHED PROPERTY:

5.1 Original acquisition value of material:

5.2 Location of GFP:

5.3 Manufacturer, model number, and type. Include serial number(s):

5.4 Government provided or contractor pickup:

6. QUALITY ASSURANCE REQUIREMENTS:

PSNS & IMF –or- Contractor is responsible for quality assurance.

The installed equipment must be new and in good working order.

7. SECURITY REQUIREMENTS: Contractor personnel must be a US citizen, with proof of citizenship document, and will require access to PSNS&IMF controlled industrial area (White or Green security badge). Originator determines if a Department Of Defense Contract Security Classification

Specification (DD254) is required.

8. TRAVEL REQUIREMENTS: PSNS&IMF, Bldg 59, 1400 Farragut Ave, Bremerton, WA 98314

Is carrier onboard delivery (COD) required? (i.e., when the contractor is transported to a vessel underway.) No

9. GOVERNMENT REPRESENTATIVE: Tom Oates, 1400 Farragut Ave, Bremerton, WA 98314; 360-476-3406; Fax: 360-476-5587;

thomas.c.oates2.civ@mail.mil.

10. OTHER CONSIDERATIONS:

10.1 Estimated Work Hours: 40 hours

PSNS&IMF 4200/43 (2-16) Page 3 of 3

10.2 All technical clarifications will be coordinated through the

Government representative.

10.3 Environmental and safety concerns: Contractor personnel is limited to Bldg 59, laboratory.

10.4 Laydown and utilities requirements: NA

12. JUSTIFICATION FOR HIGH-RISK FLAG: e.g., SUBSAFE, Steam Plant, complex or first time work, work with significant milestone impact.

Date:

Code 413 Statement of Work review

Date:

Cognizant technical code review

Date: _____

Cognizant APS/PLM or WIM Review

Notes:

1. Code 413 reviews SOW for contractual adequacy.

2. Cognizant technical code reviews SOW for technical adequacy.

3. Cognizant APS/PLM or WIM reviews SOW to ensure project requirements are adequately described.