This is a Request for Quotation (RFQ) issued by the Department of the Army's Tobyhanna Army Depot for the removal and replacement of an existing NORTEC GSTC-300NDV gas-fired humidifier in room 1A-278. The contractor must install a new like-in-kind humidifier with a capacity of 300 lb/hr, make all necessary electrical and control connections, and ensure proper integration with the existing Modular Air Handling Unit (MAHU01).
The RFQ was issued on December 6, 2024, with responses due by December 16, 2024, at 12:00 PM. This is an unrestricted solicitation under NAICS code 333415 with a size standard of 1,250 employees. The scope includes providing all labor, materials, equipment, and supervision for the installation, including factory-authorized startup and commissioning. The contractor must maintain compliance with various environmental and safety requirements, submit required documentation including equipment submittals and shop drawings within 10 days of award, and provide startup and commissioning reports within 30 days of installation completion. Payment will be processed through Wide Area Workflow (WAWF) with HQ0303 as the pay office.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Nortec-1.pdf | ||
| Nortec-2.pdf | ||
| Nortec-3.pdf | ||
| Nortec-9.pdf | ||
| Nortec-5.pdf | ||
| Nortec-4.pdf | ||
| Nortec-8.pdf | ||
| Nortec-10.pdf | ||
| 1A-4-292.pdf | ||
| 1A-4-297.pdf | ||
| Nortec-6.pdf | ||
| Nortec-7.pdf | ||
| 1A-5-416.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W51AA125Q0012 06-Dec-2024
b. TELEPHONE NUMBER
570-615-7056
8. OFFER DUE DATE/LOCAL TIME
12:00 PM 16 Dec 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W51AA19. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
ROBYN L LAYTON
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W25G1V43170071
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ACC-APG TOBYHANNA DIVISION (W51AA1)
11 HAP ARNOLD BLVD
TOBYHANNA PA 18466
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W25G1V 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
SEE BELOW FOR SEPARATE SHIPPING INSTRUCT
XXX
XXX PA 00000
TEL: FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
1,250
NAICS:
333415
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF86
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 30 - BLOCK 14 CONTINUATION PAGE
ADDENDUM
ADDENDUM TO INSTRUCTIONS TO OFFERORS
SEE 52.212-2 FOR BASIS OF AWARD
PLEASE SUBMIT BIDS TO: robyn.l.layton.civ@army.mil
THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY COSTS INCURRED FOR THE CONTRACTORS’
TIME OR MATERIALS EXPENDED IN PREPARING AN OFFER FOR THIS SOLICITATION.
TO RECEIVE AN AWARD, THE CONTRACTOR MUST HAVE AN ACTIVE REGISTRATION IN THE
SYSTEM FOR AWARD MANAGEMENT (SAM), HTTPS://WWW.SAM.GOV . PROSPECTIVE OFFERORS
MUST BE FOUND TO BE RESPONSIBLE IN ACCORDANCE WITH (IAW) FAR 9.1 AND HAVE NO
DELINQUENT FEDERAL DEBT.
OFFERS / QUOTATIONS OFFERS SHALL BE SUBMITTED ELECTRONICALLY VIA EMAIL TO THE
PURCHASING AGENT, ROBYN.L.LAYTON.CIV@ARMY.MIL BY THE CLOSING DATE AND TIME
SPECIFIED IN BLOCK 8 OF THIS SF1449.
SUBMITTALS WILL INCLUDE :
SIGNED SF1449 WITH QUOTE
SPECIFICATIONS FOR TECHNICAL APPROVAL
QUALITY CONTROL PLAN (REFERENCED IN 1.5.1 OF SOW)
EMAIL TRANSMISSIONS – IF THE CONTRACTOR DOES NOT RECEIVE WRITTEN CONFIRMATION OF
RECEIPT FROM THE PURCHASING AGENT, (VIA “READ RECEIPT” OR MANUAL REPLY TO
ACKNOWLEDGE RECEIPT), BEFORE THE ESTABLISHED DEADLINE, IT IS THE RESPONSIBILITY OF
THE CONTRACTOR TO CONTACT THE PURCHASING AGENT WITHIN 2 BUSINESS DAYS OF INITIAL
TRANSMISSION TO CONFIRM THAT THEIR SUBMISSION WAS RECEIVED.
THE GOVERNMENT WILL NOT CONSIDER SUBMISSIONS THAT WERE DELAYED, OR OTHERWISE
NOT TIMELY DELIVERED TO THE PURCHASING AGENT’S EMAIL INBOX, DUE TO COMPLICATIONS
WITH THE CONTRACTOR’S OR THE GOVERNMENT’S SERVICE PROVIDERS, TO INCLUDE EMAIL
MAINTENANCE, FIREWALL, DELIVERY TO ANY OTHER EMAIL INBOX, (I.E. JUNK FOLDER, SPAM
FOLDER, ETC.). CONTRACTORS SHOULD ANTICIPATE DELAYS IN TRANSMISSION AND ARE
ADVISED TO PLAN AHEAD AND BEGIN TRANSMITTING THEIR SUBMISSION IN ENOUGH TIME TO
ENSURE SUCCESSFUL DELIVERY PRIOR TO THE SUBMISSION DEADLINE
OFFERORS NEED NOT COMPLETE AND SUBMIT WITH THEIR OFFER, ANY PROVISIONS OR
CLAUSES THAT ARE ALREADY ANSWERED WITHIN THEIR CURRENTLY ACTIVE SAM PROFILE.
(END OF ADDENDUM)
STATEMENT OF WORK
STATEMENT OF WORK (SOW)
BUILDING 1A HUMIDIFIER REPLACEMENT
09.10.2024
Par t 1 General Informatio n
1. General: This is a non-personnel services contract for the purposes of removing and replacing, with new, an existing humidifier located in room 1A-278 of building 1A to achieve as-designed operating conditions.
1.1 Description of Replacement/Introduction: To complete this contract, contractor shall provide and replace existing humidifier according to all specifications. Contractor shall provide labor, materials, equipment, management and supervision to complete the project in accordance with all existing contract documents, Tobyhanna Army Depot (TYAD) Master specifications and Industrial Design Guide (IDG). All and any exceptions shall be submitted in writing. The objective of the effort is to replace a non-functional humidifier located in building 1A. Project specific requirements are provided herein.
1.2 Background:
a. The existing humidifier with equipment identification (ID) Tag number 1A-278- GHUM01 is obsolete and no longer functional. Humidifier serves 1A-278-MAHU01 (Indoor Modular Air Handling Unit). See schedule and plan on provided As-Built drawings 1A-4-296 and 1A-4-292 respectively for more information.
b. Existing humidifier is a self-contained gas fired indoor humidifier unit. See schedule on provided As-Built drawing 1A-4-297 for additional humidifier information.
Manufacturer:
NORTEC Model:
GSTC-300NDV
Distributor Model: SAM-e Type B, 304 SS
c. Existing humidifier is fed from Power Panel 1A-278-PP052, Circuit numbers 1 and 3 and as shown on provided As-Built drawings 1A-5-416. Electrical connection consists of a 208/1 Phase connection with 20A breaker.
1.3 Scope: Contractor shall be responsible for removing the existing NORTEC humidifier within room 1A-278 in its entirety and install a like-in-kind humidifier with a basis of design as listed below.
a. Basis Of Design Manufacturer: Any Capacity: 300 lb./hr.
b. Contractor shall be responsible for making all necessary electrical connections according to manufacturer specifications.
c. Contractor shall be responsible for relabeling panel insert as well as providing a new label on front of unit showing what panel and what circuits unit is fed from.
d. Contractor shall be responsible for reestablishing controls connections and communications such that existing sequences of operation and functionality are retained between new humidifier and MAHU01 (Modular Air Handling Unit 01).
NOTE: In the event that something is not working correctly, the contractor must be capable of making corrections and have knowledge of modifying code in Distech, if necessary.
1.4 Objectives: The objective of this contract is to replace a non-functional humidifier in building 1A. Work include all mechanical, electrical, controls programming and final commissioning. If not performed personnel will be subject to uncomfortable environmental conditions
1.5 General Information:
1.5.1 Quality Control Plan (QCP): The contractor shall develop and maintain an effective Quality Control Program (QCP) to ensure services are performed in accordance with this S O W . The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s Quality Control Program is the means by which he assures himself that his work complies with the requirement of the contract. The Contractor shall provide their QCP along with their bid submission to the Contract Specialist for review. If the Government requires changes to the QCP, the Contractor must provide a revision within five (5) business days.
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The Contractor IS NOT required to work on the following recognized holidays:
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th
Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.4 Operating Hours: The contractor is responsible for conducting business, between the hours of 07:00 through 16:30 Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons.
At all times, the Contractor shall maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.5.5 Training Holidays: RESERVED
1.5.6 Place of Performance: The work to be performed under this contract will be at Tobyhanna Army Depot, 11 Hap Arnold Boulevard, Tobyhanna, PA 18466.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.1 Security Program: Contractor personnel performing work under this contract must have a completed background check prior to start of any work to be performed and must maintain the level of security required for the life of the contract. The Contractor or Subcontractor must maintain unescorted access to the Installation. The security requirements are IAW with the DoD Contract Security Classification Specification (DD Form 254), which is currently accessible at the following link: http://www.dtic.mil/whs/directives/forms/eforms/dd0254.pdf
1.6.2 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.
1.7 Key Control: RESERVED
1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include
Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter.
Meetings may start or end outside of regular duty hours.
1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this SOW for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.10 Key Personnel: The following personnel are considered key personnel by the Government: Project Manager, Quality Control Manager. The Contractor shall provide a Project Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Project Manager, who shall act for the Contractor when the Project Manager is absent. The Project Manager and Alternate Project Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract
1.11 Identification of Contractor Employees: RESERVED
1.12.2 Contractor Identification Badges: Contractor personnel shall be easily identifiable through the display of badges.
1.13 Contractor Travel: RESERVED
1.14 Other Direct Costs (ODCs): RESERVED
1.15 Data Rights: RESERVED
1.16 Non-Disclosure Requirements: RESERVED
1.17 Protection of Government and Contract Information: RESERVED
1.18 Non-Disclosure Statements: RESERVED
1.19 Organizational Conflict of Interest (OCI): RESERVED
1.20 Phase In /Phase Out Period: RESERVED
1.21 Safety: The following provides information pertaining to Safety and Accident Prevention:
The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)), The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:
(a) Before initiation of work at the job site, an Accident Prevention Plan, written by the
Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1; will be reviewed for acceptance by designated Government personnel. Specific requirements for development of the Accident Prevention Plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1-1 is available online at www.usace.army.mil.
(b) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of EM 385-1-1).
(c) The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.
(d) The Contractor shall discuss the plans in conferences convened by the Contracting
Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within fifteen
(15) calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than fifteen (15) calendar days prior to initiation of work on each major phase; and
(e) In all areas where construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:
(i) Short sleeve shirt.
(ii) Long trousers.
(iii) Steel-toed safety boots; and
(iv) Hard hat.
1.22 Environmental Compliance: RESERVED
1.23 Required Training: The following provides information on training requirements.
1.23.1 Anti-Terrorism (AT) Level I Training: All Contractor employees, including subcontractor employees, who are employed under the contract, shall complete AT Level I Training within 30 days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR within 7 days after completion of this training by all employees and subcontractor personnel.
AT Level I awareness training is available at https://jkodirect.jten.mil.
If training cannot be conducted on the website, the Contractor shall coordinate with the COR who will contact the local AT Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the AT Officer. Verification of the training shall be provided to the COR within 7 days after completion of the training.
1.23.2 OPSEC Training: All Contractor employees, including subcontractors, shall complete Level I OPSEC training within 30 days of employment under this contract. Verification of the training shall be provided to the COR within 7 days after completion of the training. OPSEC Level I training is available at http://www.cdse.edu/catalog/elearning/GS130.html.
If training cannot be conducted on the website, the Contractor shall coordinate with the COR, who will contact the local OPSEC Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the OPSEC Officer. Verification of the training shall be provided to the COR within 7days after completion of the training.
1.23.3 iWATCH Training: The Contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 days after the contract is awarded. Verification of the training shall be provided to the COR within7 days after completion of the training. Training slides can be found on the Army OneSource we site:
http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx
1.25 Notice to Proceed: The notice to proceed will be provided as indicated below.
☐The effective date of contract will constitute the date of notice to proceed ☐A notice to proceed letter will be issued
☐The date of the letter transmitting the contract will constitute the date of the notice to proceed
1.26 Electromagnetic Compatibility Directive: RESERVED
1.27 Government Property and Services: RESERVED
1.28 Conventional Forces Europe (CFE) Treaty Verification Inspection: RESERVED
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this SOW, the following provides a list of definitions used throughout this SOW and commonly used in the acquisition field.
Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line-item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract
Government Property - means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however, they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Workday - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this SOW, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.
ACOR Alternate Contracting Officer's Representative AE Army in Europe AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis AOR Area of Responsibility AR Army Regulation AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCE Contracting Center of Excellence CFE Conventional Forces Europe CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense FAR Federal Acquisition Regulation FRG Federal Republic of Germany GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification
IGCE Independent Government Cost Estimate IT Information Technology JTR Joint Travel Regulation JPAS Joint Personnel Adjudication System KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison USAREUR United States Army Europe UOM Unit of Measure
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Services: RESERVED
3.2 Facilities: The Government will access to facilities as needed to complete the requirements of the contract.
3.3 Utilities: The Government will provide water and electricity. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the necessary amount to accomplish the task being performed.
The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.
3.4 Equipment: RESERVED
3.5 Special Tooling and Test Equipment: RESERVED
3.6 Materials: RESERVED
3.7 Training: The Government will provide the following training: AT Level 1 Awareness, OPSEC, iWATCH if necessary.
3.8 Common Access Cards (CAC): RESERVED
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract that are not listed under Section 3 of this SOW.
4.2 Secret Facility Clearance: RESERVED
4.3 Materials: The Contractor shall provide all materials necessary to meet the requirements under this Statement of Work.
4.4 Vehicles and Equipment: The Contractor shall provide all necessary and equipment to perform the work described in this SOW. All Contractor provided vehicles and equipment shall have the company name prominently displayed on both sides of the vehicle or equipment and present a neat, professional appearance. Contractor's vehicles and equipment used in the performance of this contract shall meet all local and Host Nation traffic, safety, and environmental requirements. Vehicles and equipment found to be unsafe shall be removed from the installation and replaced. The Contractor shall not use any Government-owned tools, materials, or parts to maintain Contractor vehicles and equipment without prior written approval of the Contracting Officer.
4.5 Background Checks: The Contractor shall provide Background Checks in accordance with this SOW and as determined by the Government.
PART 5
SPECIFIC TASKS
5.1 Basic Services: Contractor shall be responsible for removing the existing NORTEC humidifier within room 1A-278 in its entirety and install a like-in-kind humidifier with a basis of design as listed below.
a. Basis Of Design Manufacturer: Any Capacity: 300 lb./hr.
b. Contractor shall be responsible for making all necessary electrical connections according to manufacturer specifications.
c. Contractor shall be responsible for relabeling panel insert as well as providing a new label on front of unit showing what panel and what circuits unit is fed from.
d. Contractor shall be responsible for reestablishing controls connections and communications such that existing sequences of operation and functionality are retained between new humidifier and MAHU01 (Modular Air Handling Unit 01).
NOTE: In the event that something is not working correctly, the contractor must have knowledge of modifying code in Distech, if necessary.
1) SEQUENCE: Humidification Control (For 1A-278-MAHU01, 1A-278-MAHU02, 1A- RFFRAHU13 only):
New humidifier shall have a packaged automatic control system furnished by the humidifier manufacturer. Provide control signal and enable/disable signal to humidifier controller. When this loop is enabled the humidifier capacity shall be modulated to maintain a return air relative humidity (RA-RH) at 50% setpoint (RA-RH-SP, Adj.)
sensed by duct mounted humidity sensor per AHU. Discharge air humidity setpoint shall be reset by controlling humidity sensor between zero and 60% RH (adj). The humidifier capacity shall be modulated in sequence with the cooling-and-dehumidification control valve as shown to avoid simultaneous dehumidification and humidification. When the supply air duct humidity (SA-RH) rises above 80% relative humidity, the humidifier capacity shall begin to modulate towards closed and shall continue to gradually move towards closed until the supply air duct humidity reaches 90% relative humidity, at which point the humidifier shall be fully de-energized. When this loop is disabled, the humidifier shall be de-energized.
(a) Enable/Disable: Enable humidification loop control in heating mode when the outside air temperature is below 55-degree F during occupied or unoccupied mode. Disable humidification loop control in cooling mode when the outside air temperature is 60-degree F or greater and/or the chillers are energized and/or supply fan is OFF.
Humidity Control: When the dew point as sensed by an unoccupied dew point sensor rises above 62.5 degree F or when a room temperature sensor senses 83 degree F or higher, the AHU shall be energized; when in the unoccupied cycle, the outdoor damper shall remain closed, the cooling coil valve shall be modulated to reduce the space to
57.5 degree F dew point and 78 degree-F space temperature. AHU shall be deenergized and indexed to Unoccupied Cycle, when the set points indicated above are satisfied. Provide minimum of two dew point sensors per each air handling unit.
e. Contractor shall be responsible for reconnecting and/or supplying all necessary connections such as, but not limited to, drains, vents, gas piping, steam outlets, water lines, etc.
f. Contractor shall replace and/or install all necessary accessories such as, but not limited to, tube and header insulation, distributor, manifold stand kit, mounting frame, steam line inlet adapter kit, etc.
g. Contractor shall be responsible for the commissioning of the humidifier to ensure proper start-up and functionality. Commissioning shall be by factory trained technician only.
Commissioning shall include, but not be limited to:
1. Verification of proper unit operation.
2. Verification of communication and interoperability with air handler served by the new humidifier.
3. Verification of sequence of operation for the overall humidifier/AHU system.
5.3 Service Contract Reporting - RESERVED
PART 6
APPLICABLE PUBLICATIONS
6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this SOW and are listed below.
6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)
6.1.2 Department of Defense Security Agreement (DD Form 441)
6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)
6.1.4 Installation Access Control (AE Reg 190-16)
6.1.5 The Army Physical Security Program (AR 190-13)
6.1.6 Contractor Identification (AE Reg 27-715)
6.1.7 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)
6.1.8 Information Assurance Workforce Improvement Program (DoD 8570-M)
6.1.9 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)
6.1.10 Information Assurance (AR 25-2)
6.1.11 Electromagnetic Compatibility Directive (2004/108/EC)
6.1.12 Policies and Procedures for Property Accountability (AR 735-5)
PART 7
ATTACHMENT AND TECHNICAL EXHIBIT LISTING
7. Attachment and Technical Exhibit List
7.1 Technical Exhibit A – Performance Requirements Summary
7.2 Technical Exhibit B – Deliverables Schedule
TECHNICAL EXHIBIT A
Performance Requirements Summary (PRS)
PERFORMANCE
OBJECTIVE
STANDARD PERFORMANCE
THRESHOLD
ACCEPTABLE
QUALITY
LEVELS (AQLs)
METHOD OF
SURVEILLANCE
PRS#1 – SOW
The Contractor shall remove the existing NORTEC humidifier within room 1A-278 in its entirety.
Per Section 5.1 – Existing self-contained gas fired indoor humidifier unit.
Manufacturer:
NORTEC
Model: GSTC-300NDV shall be disassembled and remove from humidifier location along with humidifier stand.
Zero deviation from the standard.
Inspection will be performed at the end of humidifier removal.
PRS#2 - SOW
The contractor shall replace existing humidifier with like-in-kind humidifier
Per Section 5.1a – New self-contained gas fired indoor humidifier unit shall be installed on the base platform provided by contractor.
Manufacturer: Any Capacity: 300 lb./hr.
Zero deviation from the standard.
Inspection will be performed at the end of humidifier installation.
PRS#3 - SOW
The contractor shall reconnect all necessary connections such as, but not limited to, electrical wires, controls, drains, vents, gas piping, steam outlets, water lines, etc.
Per Section 5.1b,c,d,e,f.- New humidifier shall be connected to: a) existing steam distribution system
b) electrical wires
c) gas line
d) water supply
e) controls
f) drain
g) Provide pipe insulation as necessary
Zero deviation from the standard.
Inspection will be performed at the end accessories connection process.
PRS#4 - SOW
The contractor shall perform Humidifier
Per Section 5g – Contractor shall perform commissioning of the humidifier to
Zero deviation from the standard.
100% Inspection will be performed at the end of the start up and commissioning.
ensure proper start-up and functionality.
Commissioning shall be by factory trained technician only.
Commissioning shall include, but not be limited to:
1. Verification of proper unit operation.
2. Verification of communication and interoperability with air handler served by the new humidifier.
3. Verification of sequence of operation for the overall humidifier/AHU system commissioning process
W51AA125Q0012
TECHNICAL EXHIBIT B
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To
The contractor shall provide:
Equipment submittals and Shop drawings Start-up report Commissioning report
Once within 10 days after contract award and no later than 30 days prior to any work begin.
One each to the Contracting Officer
Electronic delivery via email using PDF file
Email to:
COR
The contractor shall provide:
Start up report and Commissioning report
Once within 30 days after installation completed
One each to the Contracting Officer
Electronic delivery via email using PDF file
Email to:
COR
CLAUSES INCORPORATED BY FULL TEXT
252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION (JAN 2023)
(a) Definitions. As used in this clause-
Automatic identification device means a device, such as a reader or interrogator, used to retrieve data encoded on machine-readable media.
Concatenated unique item identifier means--
(1) For items that are serialized within the enterprise identifier, the linking together of the unique identifier data elements in order of the issuing agency code, enterprise identifier, and unique serial number within the enterprise identifier; or
(2) For items that are serialized within the original part, lot, or batch number, the linking together of the unique identifier data elements in order of the issuing agency code; enterprise identifier; original part, lot, or batch number;
and serial number within the original part, lot, or batch number.
Data Matrix means a two-dimensional matrix symbology, which is made up of square or, in some cases, round modules arranged within a perimeter finder pattern and uses the Error Checking and Correction 200 (ECC200) specification found within International Standards Organization (ISO)/International Electrotechnical Commission
(IEC) 16022.
Data qualifier means a specified character (or string of characters) that immediately precedes a data field that defines the general category or intended use of the data that follows.
DoD recognized unique identification equivalent means a unique identification method that is in commercial use and has been recognized by DoD. All DoD recognized unique identification equivalents are listed at https://www.acq.osd.mil/asda/dpc/ce/ds/unique-id.html.
DoD item unique identification means a system of marking items delivered to DoD with unique item identifiers that have machine-readable data elements to distinguish an item from all other like and unlike items. For items that are serialized within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier and a unique serial number. For items that are serialized within the part, lot, or batch number within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier; the original part, lot, or batch number; and the serial number.
Enterprise means the entity (e.g., a manufacturer or vendor) responsible for assigning unique item identifiers to items.
Enterprise identifier means a code that is uniquely assigned to an enterprise by an issuing agency.
Government's unit acquisition cost means--
(1) For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;
(2) For cost-type or undefinitized line, subline, or exhibit line items, the Contractor's estimated fully burdened unit cost to the Government at the time of delivery; and
(3) For items produced under a time-and-materials contract, the Contractor's estimated fully burdened unit cost to the Government at the time of delivery.
Issuing agency means an organization responsible for assigning a globally unique identifier to an enterprise, as indicated in the Register of Issuing Agency Codes for ISO/IEC 15459, located at http://www.aimglobal.org/?Reg_Authority15459.
Issuing agency code means a code that designates the registration (or controlling) authority for the enterprise identifier.
Item means a single hardware article or a single unit formed by a grouping of subassemblies, components, or constituent parts.
Lot or batch number means an identifying number assigned by the enterprise to a designated group of items, usually referred to as either a lot or a batch, all of which were manufactured under identical conditions.
Machine-readable means an automatic identification technology media, such as bar codes, contact memory buttons, radio frequency identification, or optical memory cards.
Original part number means a combination of numbers or letters assigned by the enterprise at item creation to a class of items with the same form, fit, function, and interface.
Parent item means the item assembly, intermediate component, or subassembly that has an embedded item with a unique item identifier or DoD recognized unique identification equivalent.
Serial number within the enterprise identifier means a combination of numbers, letters, or symbols assigned by the enterprise to an item that provides for the differentiation of that item from any other like and unlike item and is never used again within the enterprise.
Serial number within the part, lot, or batch number means a combination of numbers or letters assigned by the enterprise to an item that provides for the differentiation of that item from any other like item within a part, lot, or batch number assignment.
Serialization within the enterprise identifier means each item produced is assigned a serial number that is unique among all the tangible items produced by the enterprise and is never used again. The enterprise is responsible for ensuring unique serialization within the enterprise identifier.
Serialization within the part, lot, or batch number means each item of a particular part, lot, or batch number is assigned a unique serial number within that part, lot, or batch number assignment. The enterprise is responsible for ensuring unique serialization within the part, lot, or batch number within the enterprise identifier.
Type designation means a combination of letters and numerals assigned by the Government to a major end item, assembly or subassembly, as appropriate, to provide a convenient means of differentiating between items having the same basic name and to indicate modifications and changes thereto.
Unique item identifier means a set of data elements marked on items that is globally unique and unambiguous. The term includes a concatenated unique item identifier or a DoD recognized unique identification equivalent.
Unique item identifier type means a designator to indicate which method of uniquely identifying a part has been used. The current list of accepted unique item identifier types is maintained at https://www.acq.osd.mil/asda/dpc/ce/ds/unique-id.html.
(b) The Contractor shall deliver all items under a contract line, subline, or exhibit line item.
(c) Unique item identifier. (1) The Contractor shall provide a unique item identifier for the following:
(i) Delivered items for which the Government's unit acquisition cost is $5,000 or more, except for the following line items:
Contract line, subline, or exhibit line item No. Item description
..CLIN 0001
(ii) Items for which the Government's unit acquisition cost is less than $5,000 that are identified in the Schedule or the following table:
Contract line, subline, or exhibit line item No. Item description N/A
(If items are identified in the Schedule, insert “See Schedule” in this table.)
(iii) Subassemblies, components, and parts embedded within delivered items, items with warranty requirements, DoD serially managed reparables and DoD serially managed nonreparables as specified in Attachment Number ----.
(iv) Any item of special tooling or special test equipment as defined in FAR 2.101 that have been designated for preservation and storage for a Major Defense Acquisition Program as specified in Attachment Number ----.
(v) Any item not included in paragraphs (c)(1)(i), (ii), (iii), or
(iv) of this clause for which the contractor creates and marks a unique item identifier for traceability.
(2) The unique item identifier assignment and its component data element combination shall not be duplicated on any other item marked or registered in the DoD Item Unique Identification Registry by the contractor.
(3) The unique item identifier component data elements shall be marked on an item using two dimensional data matrix symbology that complies with ISO/IEC International Standard 16022, Information technology--International symbology specification--Data matrix; ECC200 data matrix specification.
(4) Data syntax and semantics of unique item identifiers. The Contractor shall ensure that--
(i) The data elements (except issuing agency code) of the unique item identifier are encoded within the data matrix symbol that is marked on the item using one of the following three types of data qualifiers, as determined by the Contractor:
(A) Application Identifiers (AIs) (Format Indicator 05 of ISO/IEC International Standard 15434), in accordance with ISO/IEC International Standard 15418, Information Technology--EAN/UCC Application Identifiers and Fact Data Identifiers and Maintenance and ANSI MH 10.8.2 Data Identifier and Application Identifier Standard.
(B) Data Identifiers (DIs) (Format Indicator 06 of ISO/IEC International Standard 15434), in accordance with ISO/IEC International Standard 15418, Information Technology--EAN/UCC Application Identifiers and Fact Data Identifiers and Maintenance and ANSI MH 10.8.2 Data Identifier and Application Identifier Standard.
(C) Text Element Identifiers (TEIs) (Format Indicator 12 of ISO/IEC International Standard 15434), in accordance with the Air Transport Association Common Support Data Dictionary; and
(ii) The encoded data elements of the unique item identifier conform to the transfer structure, syntax, and coding of messages and data formats specified for Format Indicators 05, 06, and 12 in ISO/IEC International Standard 15434, Information Technology-Transfer Syntax for High Capacity Automatic Data Capture Media.
(5) Unique item identifier.
(i) The Contractor shall--
(A) Determine whether to--
(1) Serialize within the enterprise identifier;
(2) Serialize within the part, lot, or batch number; or
(3) Use a DoD recognized unique identification equivalent (e.g. Vehicle Identification Number); and
(B) Place the data elements of the unique item identifier (enterprise identifier; serial number; DoD recognized unique identification equivalent; and for serialization within the part, lot, or batch number only: Original part, lot, or batch number) on items requiring marking by paragraph (c)(1) of this clause, based on the criteria provided in MIL- STD-130,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .