Solicitation_140P5423R0020_Attach_0002-SOW.pdf
PDF 3 MB Posted
- Attached to
- PAINT PARK STRUCTURES Federal contract opportunity
- Solicitation number
- 140P5423R0020
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_140P5423R0020_Attach_0004-Q_and_A_0001.pdf | ||
| Sol_140P5423R0020_Amd_0001.pdf | ||
| Sol_140P5423R008_Attachment_0003-_WD.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| Sol_140P5423R0020.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAN JUAN NATIONAL HISTORIC SITE
OLD SAN JUAN, PUERTO RICO
Repaint Santa Elena Guardhouse, Castillo San Felipe del Morro Level 5 and la Puerta de San Juan
PMIS 319161
STATEMENT OF WORK
JUNE 2023
NATIONAL PARK SERVICE
SOUTHEAST REGION
SOUTH MAJOR ACQUISITION BUYING OFFICE
SAJU 319161 PAGE 2 OF 8
TABLE OF CONTENTS
TABLE OF CONTENTS 2
1 BACKGROUND 3
2 OBJECTIVES 3
3 PLACE OF PERFORMANCE 3
4 PERIOD OF PERFORMANCE 3
5 SCOPE AND GENERAL REQUIREMENTS 4
6 DELIVERABLES: 5
7 SAFETY: 5
8 SECURITY CONSIDERATIONS: 6
9 OTHER UNIQUE REQUIREMENTS & CONSIDERATIONS: 6
10 QUALITY ASSURANCE REQUIREMENT 7
11 TECHNICAL REQUIREMENTS 8
12 ATTACHMENTS 8
SAJU 319161 PAGE 3 OF 8
1 BACKGROUND
This contract is to perform exterior paint work at Santa Elena Guardhouse, Castillo San Felipe del Morro Level 5 Main Plaza including Sally Port (Fee Collection Entrance) and la Puerta de
San Juan. The buildings are located on the grounds of the San Juan National Historic Site on
Paseo Del Valle, main road in Old San Juan for both pedestrians and vehicles. The park will contract the painting of the buildings using historically accurate colors. Work includes prep work such as scaffolding, man lifts, removing loose paint, low pressure washing, patching as needed, and repainting.
2 OBJECTIVES
This contract is to paint the exterior of Santa Elena Guardhouse, Castillo San Felipe del Morro
Level 5 Main Plaza including Sally Port (Fee Collection Entrance) and la Puerta de San Juan.
Painting is needed to maintain proper appearance and to prevent building masonry deterioration.
Buildings require painting every 3 years due to the carbon monoxide emanating from passing vehicles, deterioration caused by the wind and human action, and the effects of the high humidity and the salt air since the building is adjacent to the coast. If the building is not painted the park will not be able to prevent deterioration of the building. Also, the visual impact to the area will be immense since the Santa Elena Guard House building is in one of the entrances to the park.
The buildings and structure would look neglected, and this will probably incite acts of vandalism like graffiti.
3 PLACE OF PERFORMANCE
Street Address: San Juan National Historic Site, NPS
511 Calle Norzagaray, San Juan, Puerto Rico, 00901
a. Santa Elena Guardhouse (18.46820°N, 66.12369°W)
b. Castillo San Felipe del Morro Level 5
i. Main Plaza (18.47096°N, 66.12404°W)
ii. Sally Port (Fee Collection Entrance) (18.47073°N, 66.12390°W)
c. Puerta de San Juan (18.46515°N, 66.11944°W)
• The El Morro road’s entrance is down the road from Castillo El Morro and is within San
Juan National Historic Site. There are no parking facilities at El Morro, but the contractor may park in front of Castillo El Morro only before 9:30am. After 9:30am, all contractor vehicles must be moved. The Contractor may park two (2) vehicles at the Polvorin.
Additional vehicles must be parked off site. A non-NPS affiliated commercial parking garage is located at Ballajá Parking Garage about 0.4 miles away.
4 PERIOD OF PERFORMANCE
Workdays and hours: 6:30am to 3:00 pm Monday through Friday, excluding federal holidays.
Access to jobsite and electrical panels will be gained through the Contracting Officer
Representative (COR) and/or park maintenance staff.
Construction:
http://maps.google.com/?q=18.46820779826704,-66.12369013239805 http://maps.google.com/?q=18.47096750964627,-66.12404651375789 http://maps.google.com/?q=18.4707345234808,-66.12390396964918 http://maps.google.com/?q=18.465156286871597,-66.11944492766864
SAJU 319161 PAGE 4 OF 8
Construction shall not begin until the Contracting Officer has issued the Notice to Proceed.
Construction shall be completed no later than 120 calendar days after Notice to Proceed.
As-Constructed Drawings:
As-Constructed Drawings completed no later than 30 calendar days after Substantial
Completion.
All Shop Drawings and As-Constructed Drawings shall be submitted to the COR.
5 SCOPE AND GENERAL REQUIREMENTS
All work must be done in accordance with SECTION 090190 - HISTORIC MAINTENANCE
REPAINTING. Remove hardware, lighting fixtures, and similar items that are not to be painted.
Mask items that cannot be removed. Drop cloths shall be used. Reinstall items in each area after painting is complete. Clean and prepare surfaces in an area before beginning painting in that area. Schedule painting so cleaning operations will not damage newly painted surfaces.
Contractor shall establish barriers around the areas of Electric Personnel Scissor Lift, scaffolding, and painted areas to prevent visitors from damaging recently painted areas. Scaffold will be permitted with the exemption of Castillo San Felipe del Morro. Electric Personnel Scissor
Lift will be used for painting areas of Castillo San Felipe del Morro. Contractor staff must have a current certification for Electric Personnel Scissor Lift and Scaffolding.
The contractor should plan on extensive preparatory work prior to painting and avoid to the maximum extent practicable overlapping with potential rain events listed in local weather applications. Do not apply exterior paint in rain, fog or mist; or when the relatively humidity exceeds 85 percent; or to damp or wet surfaces.
Should unexpected rain occur, the contractor is required to halt work, demobilize, and only resume when surfaces are dry. Resumption of work, which includes re-mobilization, should only occur once the surfaces have thoroughly dried, no sooner than 24 hours following the rain event.
Cleaning of painting equipment on park property is strictly forbidden.
Cost proposal shall be based on field measurements taken from offeror, measurements in this statement of work are estimates only.
BASE BID – REPAINT PARK STRUCTURES
CONTRACT LINE-ITEM NO. 1 – SANTA ELENA GUARDHOUSE: This item consists of removing loose flaking paint, low pressure power wash, patching substrates, repainting surfaces for approximately 6,384 square feet, and providing product datasheets for all products used. This item also includes mobilization, costs of preparatory work and operations, including but not limited to, those necessary for the movement of personnel, equipment, supplies, materials and incidentals to the project site, site facilities necessary for the work on the project, traffic control, project closeout, punch lists, final cleanup, demobilization from the project site upon completion of work, and all other work necessary for the completion of the project.
SAJU 319161 PAGE 5 OF 8
CONTRACT LINE-ITEM NO. 2 – CASTILLO SAN FELIPE DEL MORRO LEVEL 5: This item consists of removing loose flaking paint, low pressure power wash, patching substrates, repainting surfaces for approximately 55,640 square feet, and providing product datasheets for all products used. This item also includes mobilization, costs of preparatory work and operations, including but not limited to, those necessary for the movement of personnel, equipment, supplies, materials and incidentals to the project site, site facilities necessary for the work on the project, traffic control, project closeout, punch lists, final cleanup, demobilization from the project site upon completion of work, and all other work necessary for the completion of the project.
CONTRACT LINE-ITEM NO. 3 – PUERTA DE SAN JUAN: This item consists of removing loose flaking paint, low pressure power wash, patching substrates, repainting surfaces for approximately 17,202 square feet, and providing product datasheets for all products used. This item also includes mobilization, costs of preparatory work and operations, including but not limited to, those necessary for the movement of personnel, equipment, supplies, materials and incidentals to the project site, site facilities necessary for the work on the project, traffic control, project closeout, punch lists, final cleanup, demobilization from the project site upon completion of work, and all other work necessary for the completion of the project.
6 DELIVERABLES:
A. Product Submittals (with product literature such as data, cut sheets, and information)
An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting
Officer before the first progress payment is processed.
7 SAFETY:
Accident Prevention Program: Prior to the Preconstruction Meeting submit a tailored accident prevention plan. The plan must be accepted by the NPS before any on site work can begin. The plan shall comply with OSHA and project requirements. Please include the name of responsible supervisor to carry out the plan; monthly safety meetings; first aid procedures; outline of each phase of work, hazards associated with each phase and methods proposed to ensure property protection, and safety of the public, National Park Service staff and Contractor employees;
training; planning for possible emergency situations; housekeeping and fire protection.
Accident Reporting: Reportable accidents, defined as death, occupational disease, traumatic injury to contractor’s personnel, NPS employees or the public, property damage of any accident more than $100 and fires, must be reported immediately to the Contracting Officer and park’s
COR.
Ensure that all employees are physically qualified to perform their assigned duties in a safe manner. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment.
Ensure to comply with:
A. First aid facilities.
B. Personnel protective equipment: Meet requirements of NIOSH and MSHA.
SAJU 319161 PAGE 6 OF 8
C. Emergency instructions, including telephone numbers and reporting instruction for ambulance, physician, hospital, fire department and park police. Place in conspicuous locations at the worksite
D. Adequate egress always in accordance with the Standard for Safeguarding
Construction, Alteration, and Demolition Operations (NFPA 241).
E. Fall protection plan
F. Hard hats for all employees.
G. Designate and post signs in all hardhat areas.
Cultural Resources - An archeological monitor may be present at the work site. If archeological resources are damaged at the project site while the archeological monitor is present or absent, all work directly affecting the discovery must stop immediately, and the damage must be reported to the COR. Contractor shall move on to work on other portions of the scope that do not directly affect the archaeological discovery with the approval of the COR.
8 SECURITY CONSIDERATIONS:
Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.
Staging is limited in or near the construction area. Construction equipment and material storage shall be in previously disturbed areas near the construction site. All staging areas shall be returned to pre-construction conditions once construction is complete.
Site Access - Contractor properly identified employees will be the only ones allowed on site and shall comply with Federal Code of conduct during work hours.
Construction zones shall be fenced with approved construction barrier fencing, plastic or portable fencing, before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. Workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.
9 OTHER UNIQUE REQUIREMENTS & CONSIDERATIONS:
Disruptions of services shall be kept to a minimum. All disruptions shall be arranged at least 48 hours in advance with National Park Service and must be approved by Contracting Officer.
Construction procedures will prevent accidental disruptions to facilities outside the project limits by investigation of existing utilities and protection during construction: accidental disruptions shall be remedied at no cost to National Park Service.
Hauling Restrictions - Comply with all legal load restrictions in the hauling of materials.
Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent.
Cleaning - Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.
SAJU 319161 PAGE 7 OF 8
Thoroughly clean building interiors. Pick up and remove all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
Substantial Completion and Final Inspection - Submit written certification to the CO and COR that the project, or designated portion of project, is substantially complete, and request a final inspection. Upon receipt of written request that project is substantially complete, the Contracting
Officer will proceed with inspection within 10 days of receipt of request or will advise the
Contractor of items that prevent the project from being designated as substantially complete.
When work is determined to be substantially complete, a list of deficiencies ("Punch List") to be corrected before final acceptance might be prepared. The Contracting Officer will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the
Contracting Officer will notify the contractor in writing. After completing work, the contractor shall resubmit certification and request a new final inspection.
Acceptance of the work - After all deficiencies have been corrected, the Contracting Officer will issue a Letter of Final Acceptance.
10 QUALITY ASSURANCE REQUIREMENT
While performing work, the contractor shall comply with the latest applicable versions of the following:
• Federal, State and Local Codes, Standards and Policies for Environmental Protection
Authority requirements.
• Occupational Safety and Health Administration (OSHA) requirements.
• Shall meet Secretary of Interior Standards for Historic Preservation and follow Section
106 National Historic Preservation Act (NHPA)
• NPS Reference Manual 10A and 10B
The quality of all work shall be the responsibility of the Contractor. Testing, if required, shall be the responsibility of an independent testing laboratory. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is following applicable specifications and drawings. All affected areas must be restored to their original condition from before the work began. Any damages will be fixed and repaired at no cost to the government. Any damage to floor, or walls will be the contractor’s responsibility to repair to match existing materials.
PERSONNEL
Contracting Officer: TBD
Contracting Officer Representative (COR): TBD
Park Facility Manager: TBD https://www.nps.gov/dscw/upload/ReferenceManual10A_April2001_110817_AF.pdf https://www.nps.gov/orgs/1804/upload/ReferenceManual10B_Nov2009_V508.pdf
SAJU 319161 PAGE 8 OF 8
11 TECHNICAL REQUIREMENTS
Division 9 – Finishes
A. SECTION 090190 - HISTORIC MAINTENANCE REPAINTING
12 ATTACHMENTS
Attachment A – Pictures
SAJU 319161 090190 - 1
HISTORIC MAINTENANCE REPAINTING
SECTION 090190 - HISTORIC MAINTENANCE REPAINTING
PART 1 - GENERAL
1.01 Section Includes
A. Removing loose flaking paint B. Low pressure power wash C. Remove fungus D. Patching substrates E. Repainting surfaces
1.02 References
A. ASTM C 136-96a – Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates;
1996.
B. EN459/BS459 – European Norm and British Standards for Specifications for Building Limes;
1995.
C. ASTM C 144-97 – Standard Specification for Aggregate for Masonry Mortar; 1997.
D. ASTM C207 - ASTM C207: Standard Specification for Hydrated Lime for Masonry Purposes E. ASTM C5 – Quicklime for Structural Purposes F. ASTM C5-79 - Standard Test Methods for Compressive Strength of Chemical-Resistant
Mortars, Grouts, Monolithic Surfacing’s, and Polymer Concretes G. ASTM C1489 – Lime Putty for Structural Purposes H. ASTM C1713 – Mortars for the Repair of Historic Masonry
1.03 Submittals
A. Product Data:
1. Submit for each type of binder: Product data sheets.
2. Storage and shipping requirements information.
3. Manufacturer’s climate requirements for installation and curing.
B. Aggregate (sand):
1. Sieve analysis.
2. Aggregate void ratio.
3. Source location description.
C. Lime Paint:
1. Paint colors and manufacturer.
2. Samples for verification with texture to simulate actual conditions.
D. Lime Based Patching Material:
1. Material manufacturer and product
2. Samples for verification of compatibility to historic walls material.
1.04 Quality Assurance
A. Contractor Qualifications: Utilize personnel experienced in masonry restoration to perform the work of this Section. Individuals shall have successful experience in comparable masonry restoration Projects similar in material, design and extent to that indicated for this Project.
B. Field Inspection: Patching material shall be inspected prior to applying by the COR or NPS mason determined by the COR.
C. The quality of the patch repairs needs to be examined and approved before painting by the COR or NPS mason determined by the COR, patching deficiencies will be difficult to locate once paint is applied.
PART 2 - PRODUCTS
2.01 Mortar Materials
SAJU 319161 090190 - 2
A. Restaura Natural Hydraulic Lime: CALIX NHL 3.5 white or approved equal.
B. Sand: Must originate from a fresh water river sand. Ocean sand will not be accepted.
C. Water: Clean, clear, potable water.
D. Pigments: Not required and not permitted unless mortar analysis reveals the presence of pigments in the historic mortars.
2.02 Paint
A. Restaura Lime Paint or approved equal.
B. Fabricated for the restauration or preservation of historic structures.
2.03 Mold Remover
A. D/2 Biological Solution or approved equal.
PART 3 - EXECUTION
3.01 Removing Loose Flaking Paint
A. Remove only loose flaking paint in necessary areas.
B. Using a cautionary approach, the contractor shall only lightly scrape off any loose flaking paint with a tool similar to a soft bristle brush.
C. Scraping shall be done in a manner that protects and preserves the historic wall.
3.02 Low pressure power wash
A. Maximum 1000 psi
3.03 Remove Fungus
A. After power wash, remove all remining surface fungus using D/2 Biological Solution or approved equal.
3.04 Patching substrates
A. Binder: (Natural Hydraulic Lime & Water) shall be mixed as per manufacturers recommendations.
B. Aggregate: (River Sand).
C. Binder / Aggregate = 1 part / 3 parts (in volume).
D. Do not proceed with patching until the COR or NPS mason determined by the COR examines and approves mortar patching material mix.
E. Patch only necessary areas (gouges and/or holes).
F. Surfaces to be patched must be clean, dry, and in sound condition.
G. Patching shall create a smooth finish between the repair and the surrounding surface.
H. Protect all adjacent surfaces and areas from patching operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection.
I. Patching defects shall be corrected at no extra cost.
3.05 Repainting surfaces
A. Prior to commencement of work of this section, thoroughly examine all conditions and surfaces scheduled to be painted and report to the Contractor any conditions or surfaces that will adversely affect work of this section.
B. Patched surfaces must have previous curing time of 24-hours prior to painting unless approved by the COR.
C. No painting work shall commence until all such adverse conditions and defects have been corrected and surfaces and conditions are acceptable to the COR.
D. Remove and securely store all miscellaneous hardware and surface fittings prior to painting.
Carefully clean and replace all such items upon completion of painting work in each area.
SAJU 319161 090190 - 3
E. Paint entire walls with 2 coats minimum, patched areas must be completely dry before painting.
F. Protect all adjacent interior surfaces and areas from painting operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection.
G. Substrate painting defects shall be corrected by the painter at no extra cost.
END OF SECTION 090190
Attachment A – Pictures
Santa Elena Guardhouse (18.46820°N, 66.12369°W) http://maps.google.com/?q=18.46820779826704,-66.12369013239805
Castillo San Felipe del Morro Level 5 Main Plaza (18.47096°N, 66.12404°W) http://maps.google.com/?q=18.47096750964627,-66.12404651375789
Castillo San Felipe del Morro Level 5 Sally Port (18.47073°N, 66.12390°W) http://maps.google.com/?q=18.4707345234808,-66.12390396964918
Puerta de San Juan (18.46515°N, 66.11944°W) http://maps.google.com/?q=18.465156286871597,-66.11944492766864
| SOW Attachments.pdf |
| 090190 HISTORIC MAINTENANCE REPAINTING - Hydraulic Lime |
| SECTION 090190 - HISTORIC MAINTENANCE REPAINTING |
| PART 1 - GENERAL |
| 1.01 Section Includes |
| A. Removing loose flaking paint |
| B. Low pressure power wash |
| C. Patching substrates |
| D. Repainting surfaces |
| 1.02 References |
| A. ASTM C 136-96a – Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates; 1996. |
| B. EN459/BS459 – European Norm and British Standards for Specifications for Building Limes; 1995. |
| C. ASTM C 144-97 – Standard Specification for Aggregate for Masonry Mortar; 1997. |
| D. ASTM C207 - ASTM C207: Standard Specification for Hydrated Lime for Masonry Purposes |
| E. ASTM C5 – Quicklime for Structural Purposes |
| F. ASTM C5-79 - Standard Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacing’s, and Polymer Concretes |
| G. ASTM C1489 – Lime Putty for Structural Purposes |
| H. ASTM C1713 – Mortars for the Repair of Historic Masonry |
| 1.03 Submittals |
| A. Product Data: |
| 1. Submit for each type of binder: Product data sheets. |
| 2. Storage and shipping requirements information. |
| 3. Manufacturer’s climate requirements for installation and curing. |
| B. Aggregate (sand): |
| 1. Sieve analysis. |
| 2. Aggregate void ratio. |
| 3. Source location description. |
| C. Lime Paint: |
| 1. Paint colors and manufacturer. |
| 2. Samples for verification with texture to simulate actual conditions. |
| D. Lime Based Patching Material: |
| 1.04 Quality Assurance |
| A. Contractor Qualifications: Utilize personnel experienced in masonry restoration to perform the work of this Section. Individuals shall have successful experience in comparable masonry restoration Projects similar in material, design and extent to t... |
| B. Field Inspection: Patching material shall be inspected prior to applying by the COR or NPS mason determined by the COR. |
| C. The quality of the patch repairs needs to be examined and approved before painting by the COR or NPS mason determined by the COR, patching deficiencies will be difficult to locate once paint is applied. |
| PART 2 - PRODUCTS |
| 2.01 Mortar Materials |
| A. Restaura Natural Hydraulic Lime: CALIX NHL 3.5 white or approved equal. |
| B. Sand: Must originate from a fresh water river sand. Ocean sand will not be accepted. |
| C. Water: Clean, clear, potable water. |
| D. Pigments: Not required and not permitted unless mortar analysis reveals the presence of pigments in the historic mortars. |
| 2.02 Paint |
| A. Restaura Lime Paint or approved equal. |
| B. Fabricated for the restauration or preservation of historic structures. |
| PART 3 - EXECUTION |
| 3.01 Removing Loose Flaking Paint |
| A. Remove only loose flaking paint in necessary areas. |
| B. Using a cautionary approach, the contractor shall only lightly scrape off any loose flaking paint with a tool similar to a soft bristle brush. |
| C. Scraping shall be done in a manner that protects and preserves the historic wall. |
| 3.02 Low pressure power wash |
| A. Maximum 1000 psi |
| 3.03 Patching substrates |
| A. Binder: (Natural Hydraulic Lime & Water) shall be mixed as per manufacturers recommendations. |
| B. Aggregate: (River Sand). |
| C. Binder / Aggregate = 1 part / 3 parts (in volume). |
| D. Do not proceed with patching until the COR or NPS mason determined by the COR examines and approves mortar patching material mix. |
| E. Patch only necessary areas (gouges and/or holes). |
| F. Surfaces to be patched must be clean, dry, and in sound condition. |
| G. Patching shall create a smooth finish between the repair and the surrounding surface. |
| H. Protect all adjacent surfaces and areas from patching operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection. |
| I. Patching defects shall be corrected at no extra cost. |
| 3.04 Repainting surfaces |
| A. Prior to commencement of work of this section, thoroughly examine all conditions and surfaces scheduled to be painted and report to the Contractor any conditions or surfaces that will adversely affect work of this section. |
| B. Patched surfaces must have previous curing time of 24-hours prior to painting unless approved by the COR. |
| C. No painting work shall commence until all such adverse conditions and defects have been corrected and surfaces and conditions are acceptable to the COR. |
| D. Remove and securely store all miscellaneous hardware and surface fittings prior to painting. Carefully clean and replace all such items upon completion of painting work in each area. |
| E. Paint entire walls, patched areas must be completely dry before painting. |
| F. Protect all adjacent interior surfaces and areas from painting operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection. |
| G. Substrate painting defects shall be corrected by the painter at no extra cost. |
| Attachment A – Pictures |
| 090190 HISTORIC MAINTENANCE REPAINTING - Hydraulic Lime.pdf |
| SECTION 090190 - HISTORIC MAINTENANCE REPAINTING |
| PART 1 - GENERAL |
| 1.01 Section Includes |
| A. Removing loose flaking paint |
| B. Low pressure power wash |
| C. Remove fungus |
| D. Patching substrates |
| E. Repainting surfaces |
| 1.02 References |
| A. ASTM C 136-96a – Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates; 1996. |
| B. EN459/BS459 – European Norm and British Standards for Specifications for Building Limes; 1995. |
| C. ASTM C 144-97 – Standard Specification for Aggregate for Masonry Mortar; 1997. |
| D. ASTM C207 - ASTM C207: Standard Specification for Hydrated Lime for Masonry Purposes |
| E. ASTM C5 – Quicklime for Structural Purposes |
| F. ASTM C5-79 - Standard Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacing’s, and Polymer Concretes |
| G. ASTM C1489 – Lime Putty for Structural Purposes |
| H. ASTM C1713 – Mortars for the Repair of Historic Masonry |
| 1.03 Submittals |
| A. Product Data: |
| 1. Submit for each type of binder: Product data sheets. |
| 2. Storage and shipping requirements information. |
| 3. Manufacturer’s climate requirements for installation and curing. |
| B. Aggregate (sand): |
| 1. Sieve analysis. |
| 2. Aggregate void ratio. |
| 3. Source location description. |
| C. Lime Paint: |
| 1. Paint colors and manufacturer. |
| 2. Samples for verification with texture to simulate actual conditions. |
| D. Lime Based Patching Material: |
| 1.04 Quality Assurance |
| A. Contractor Qualifications: Utilize personnel experienced in masonry restoration to perform the work of this Section. Individuals shall have successful experience in comparable masonry restoration Projects similar in material, design and extent to t... |
| B. Field Inspection: Patching material shall be inspected prior to applying by the COR or NPS mason determined by the COR. |
| C. The quality of the patch repairs needs to be examined and approved before painting by the COR or NPS mason determined by the COR, patching deficiencies will be difficult to locate once paint is applied. |
| PART 2 - PRODUCTS |
| 2.01 Mortar Materials |
| A. Restaura Natural Hydraulic Lime: CALIX NHL 3.5 white or approved equal. |
| B. Sand: Must originate from a fresh water river sand. Ocean sand will not be accepted. |
| C. Water: Clean, clear, potable water. |
| D. Pigments: Not required and not permitted unless mortar analysis reveals the presence of pigments in the historic mortars. |
| 2.02 Paint |
| A. Restaura Lime Paint or approved equal. |
| B. Fabricated for the restauration or preservation of historic structures. |
| 2.03 Mold Remover |
| A. D/2 Biological Solution or approved equal. |
| PART 3 - EXECUTION |
| 3.01 Removing Loose Flaking Paint |
| A. Remove only loose flaking paint in necessary areas. |
| B. Using a cautionary approach, the contractor shall only lightly scrape off any loose flaking paint with a tool similar to a soft bristle brush. |
| C. Scraping shall be done in a manner that protects and preserves the historic wall. |
| 3.02 Low pressure power wash |
| A. Maximum 1000 psi |
| 3.03 Remove Fungus |
| A. After power wash, remove all remining surface fungus using D/2 Biological Solution or approved equal. |
| 3.04 Patching substrates |
| A. Binder: (Natural Hydraulic Lime & Water) shall be mixed as per manufacturers recommendations. |
| B. Aggregate: (River Sand). |
| C. Binder / Aggregate = 1 part / 3 parts (in volume). |
| D. Do not proceed with patching until the COR or NPS mason determined by the COR examines and approves mortar patching material mix. |
| E. Patch only necessary areas (gouges and/or holes). |
| F. Surfaces to be patched must be clean, dry, and in sound condition. |
| G. Patching shall create a smooth finish between the repair and the surrounding surface. |
| H. Protect all adjacent surfaces and areas from patching operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection. |
| I. Patching defects shall be corrected at no extra cost. |
| 3.05 Repainting surfaces |
| A. Prior to commencement of work of this section, thoroughly examine all conditions and surfaces scheduled to be painted and report to the Contractor any conditions or surfaces that will adversely affect work of this section. |
| B. Patched surfaces must have previous curing time of 24-hours prior to painting unless approved by the COR. |
| C. No painting work shall commence until all such adverse conditions and defects have been corrected and surfaces and conditions are acceptable to the COR. |
| D. Remove and securely store all miscellaneous hardware and surface fittings prior to painting. Carefully clean and replace all such items upon completion of painting work in each area. |
| E. Paint entire walls with 2 coats minimum, patched areas must be completely dry before painting. |
| F. Protect all adjacent interior surfaces and areas from painting operations and damage with drop cloths, shields, masking, templates, or other suitable protective means and correct any damage caused by failure to provide such protection. |
| G. Substrate painting defects shall be corrected by the painter at no extra cost. |