Sol_140P5323R0014.pdf

PDF 1003 KB Posted

Attached to
MACA-RESURFACE MAPLE SPRINGS & CG RD. Federal contract opportunity
Solicitation number
140P5323R0014
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This federal solicitation seeks proposals for resurfacing roads at Mammoth Cave National Park. Key details include:

  • The National Park Service is soliciting proposals to resurface Maple Springs Road and Campground Road at Mammoth Cave National Park in Kentucky.

  • Proposals are due by April 21, 2023. The period of performance is from May 1, 2023 to September 30, 2023.

  • The total estimated value of the contract is between $100,000 and $250,000.

  • The solicitation is set aside for small businesses. The NAICS code is 237310 for highway, street, and bridge construction.

  • A site visit will be held on April 12, 2023, and attendance is highly recommended.

  • Questions are due by April 14, 2023, and answers will be posted as an amendment by April 17, 2023.

  • Proposals must include technical, price, and past performance sections addressing the criteria in the solicitation. Price will be evaluated for reasonableness based on adequate cost breakdown and comparison to independent estimates.

View the file

Other files for this federal contract opportunity

Other files attached to MACA-RESURFACE MAPLE SPRINGS & CG RD., newest first.
File Type Posted
Questions_and_Answers_0002.pdf PDF
Sol_140P5323R0014_Amd_0002.pdf PDF
Sol_140P5323R0014_Amd_0001.pdf PDF
WAGE_RATE_DETERMINATION.pdf PDF
(SOW)_Maple_Springs_Loop___Campground_Rd.pdf PDF
Construction_Contract_Administration.docx DOCX document
Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040608321

NPS, SER - North MABO

107 Park Headquarters Road

Gatlinburg TN 37738

PSN

marilia_mateo@nps.gov

PROPOSALS TO BE SUBMITTED BY EMAIL ONLY

Marilia Mateo 3052427742

1x 03/09/2023

140P5323R0014

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

SOW, WAGE RATE, PAST PERFORMANCE QUESTIONAIRRE

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

5 120 calendar days and complete it within ________________ ________________ calendar days after receiving

04/21/2023

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

DOI, NPS, SER - North MABO 107 Park Headquarters Road

Gatlinburg TN 37738

PSN

Ashley Warcewicz

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 27

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140P5323R0014

THERE WILL BE A SIGHT VISIT SCHEDULED ON APRIL

12TH, 2023 AT 09:00 AM CENTRAL TIME.

Please refer to the solicitation/contract form for more information.

All questions regarding this solicitation must be submitted in writing to the Contracting Officer or Contract Specialist. Questions must be submitted by APRIL 14TH, 023 BY 5:00 PM EASTERN

TIME.

Questions submitted after this time may NOT be considered. Answers to the questions submitted in writing will be posted to the solicitation as an amendment on or around April 17th, 2023. Email shall contain subject: QUESTIONS 140P533R0014.

PROPOSALS ARE DUE ON APRIL 21ST, 2023 AT 3:00PM

EASTERN TIME. Email should contain subject line:

PROPOSAL 140P5323R0014.

Delivery: 09/30/2023

Delivery Location Code: 0009060308

NPS, Mammoth Cave NP

P O Box 7

NPS Warehouse, 61 Maintenance Rd

Mammoth Cave KY 42259 US

Period of Performance: 05/01/2023 to 09/30/2023

00010 Resurface Maple Springs & Campground Rd.

Product/Service Code: Z2LB

Product/Service Description: REPAIR OR ALTERATION

OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

TABLE OF CONTENTS

PART I – THE SCHEDULE

SECTION A - SF 1442 (Solicitation/Contract Form) ………………………………………………………………………………………… 5 SECTION B - Supplies or Services and Price Cost (See SF 1442 (block 17) for offer) ………………………………………. 6 Price Schedule …………………………………………………………………………………………………………………………… 6 SECTION C - Specifications ……………………………………………………………………………………………………………………………. 6 SECTION D – Packaging and Marking ……………………………………………………………………………………………………………. 7 SECTION E – Inspection and Acceptance ………………………………………………………………………………………………………. 7 Inspection of Construction ……………………………………………………………………………………………………….. 7 SECTION F – Deliveries or Performance ………………………………………………………………………………………………………… 7 Commencement, Prosecution, and Completion of Work ………………………………………………………….. 7 Suspension of Work ………………………………………………………………………………………………………………….. 7 SECTION G – Contract Administration Data ………………………………………………………………………………………………….. 7 Contract Administration Contacts ……………………………………………………………………………………………. 7 Technical Direction ………………………………………………………………………………………………………………….. 7 Correspondence, Contract Payments, and Job Site Administration ………………………………………….. 8 Payroll Records, Subconracting ………………………………………………………………………………………………… 8 SECTION H – Special Contract Requirements ………………………………………………………………………………………………… 8 Executive Order – Prohibition of Text Messaging while Driving ……………………………………………….. 9 Safety, Progress Meetings, Payrolls ………………………………………………………………………………………….. 9 Operation of Facility during Construction, Work Hours, Use of Premises …………………………………. 9 Disposal, Contractor Employees, Permits …………………………………………………………………………………. 10 Quality of Work, Completion of Work, Material Approval Submittals ………………………………………. 10 DOI Electronic Invoicing and Payment Requirements (IPP) ………………………………………………………. 11

PART II – CONTRACT CLAUSES

SECTION I – Contract Clauses ………………………………………………………………………………………………………………………. 12 Incorporation by Reference of Representations and Certifications …………………………………………… 13 Warranty of Construction …………………………………………………………………………………………………………. 14 Clauses Incorporated by Reference ……………………………………………………………………………………………. 14 Performance of Work by the Contractor ……………………………………………………………………………………. 15 Release of Claims – Department of Interior ……………………………………………………………………………….. 15 Liability Insurance - Department of Interior ………………………………………………………………………………. 15 Buy American Construction Materials ………………………………………………………………………………………… 15

PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J – List of Attachments …………………………………………………………………………………………………………………… 19

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K – Representations, Certifications, and Other Statements of Offerors …………………………………………. 19 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment ……………………………………………………………………………………………………………… 19 Preparations or Proposals ………………………………………………………………………………………………………… 21 SECTION L – Instructions, Conditions and Notices to Bidders ……………………………………………………………………….. 22 Solicitation Provision Incorporated by Reference ……………………………………………………………………… 22 Service of Protest – DOI ……………………………………………………………………………………………………………. 22 Site Visit (Construction) ……………………………………………………………………………………………………………. 23 Inquiries, Delivery of Offers ……………………………………………………………………………………………………… 23 Proposal File Format ………………………………………………………………………………………………………………… 23 SECTION M - Evaluation Factors for Award …………………………………………………………………………………………………. 23 Evaluation Factors for Award …………………………………………………………………………………………………… 24 Relative Weight of Evaluation Criteria ……………………………………………………………………………………… 26 Additional Information …………………………………………………………………………………………………………….. 27

SECTION A: SOLICITATION/CONTRACT FORM

PROJECT TITLE: RESURFACE OF CAMPGROUND – MAMMOTH CAVE NATIONAL PARK

SOLICITATION: 140P5323R0014

SITE LOCATION: Mammoth Cave National Park (MACA) 61 Maintenance Road Mammoth Cave, KY 42259

SET – ASIDE: Total Small Business NAICS: 237310 – Highway, Street, and Bridge Construction

SIZE STANDARD: $39.5 MIL

NOTICE TO PROSPECTIVE OFFERORS

SUBMISSION OF DOCUMENTS: Your offer must include the following Sections and Forms:

1. SF-1442

2. SOLICITATION

3. OFFER

PLEASE NOTE: The SF-1442 must be signed, and dated, and blocks 14 through 20c must be completed.

SF-1442, ITEM 17, Offeror is cautioned to review acceptance time stated in 13d prior to completing this item. Proposals offering less than specified time will cause proposal to be rejected.

THE MAGNITUDE OF THIS PROJECT IS BETWEEN $100,000 AND $250,000

THERE WILL BE A SITE VISIT SCHEDULED ON APRIL 12, 2023 AT 9:00 A.M. CENTRAL TIME. PLEASE

REFER TO PAGE 23 OF THE DOCUMENT FOR ADDITIONAL INFORMATION.

QUESTIONS MUST BE SUBMITTED TO EMAIL ADDRESS: marilia_mateo@nps.gov no later than APRIL 14, 2023 at 5:00 P.M. EASTERN TIME, with subject line: “Questions SOL 140P5323R0014”. Offerors must submit all questions regarding this solicitation in writing to the Contracting Officer. Answers to questions, information or changes provided during the site visit are not considered valid until they have been provided in writing by the Contracting Officer as part of the amendment. Questions submitted after this time may NOT be considered. Answers to questions submitted in writing will be posted to the solicitation as an amendment on or around APRIL 17TH, 2023.

OFFERS MUST BE SUBMITTED TO EMAIL ADDRESS: marilia_mateo@nps.gov no later than 03:00 P.M.

(EST) on Friday, April 21, 2023, with subject line – “Offer Sol 140P5323R0014”.

PERFORMANCE/PAYMENT BONDS – Successful offeror will be required to furnish Performance and Payment bonds on Standard Forms 25 and 25A based on total contract amounts within the following ranges: 100 percent performance bond, 100 percent payment bond. Offerors are now advised that the Government will inspect, accept, and take possession of completed work and release the bonding upon completion/acceptance of the work in accordance with FAR 28.203-5.

THE SITE SUPERINTENDENT FOR THE PROJECT MUST BE AN EMPLOYEE OF THE PRIME CONTRACTOR.NO

EXCEPTIONS WILL BE MADE.

PROPOSALS / OFFERS ARE DUE ON FRIDAY, APRIL 21, 2023 AT 3:00 P.M. EASTERN TIME.

SECTION B – SUPPLIES OR SERVICES AND PRICES – PRICE SCHEDULE

The contractor should provide all labor, parts, tools, equipment, supervision, and all incidentals as necessary to remove existing furnishings and proceed to renovate and remodel the HQ breakroom with new furnishings in accordance with attached specifications and drawings.

PRICE SCHEDULE

SOLICITATION NUMBER: 140P5323R0014

PROJECT TITLE: Resurface of Campground – Mammoth Cave National Park Contract Line-Item Number

Contract Line Item

Quantity

Unit of Measure

Unit Price

Total Price

Resurface of Campground in accordance with the SOW and Site Plan

Lump Sum

Please Provide a Price Breakdown in your proposal

TOTAL COMBINED PROPOSED PRICE:

COMPLETION TIME:

NOTE: Please provide a detailed cost breakout of your lump sum bid to include all costs associated with your proposal. Also, please fill out the following information for your entity:

Price Schedule Completed By:

Position:

Company Name:

Company Address:

SAM.gov Unique Entity ID (UEI):

Signature:

SECTION C – SPECIFICATIONS/DRAWINGS

Statement of Work Attachment 001

Site Plan Attachment 002

Wage Determination Attachment 003

Past Performance Questionnaire Attachment 004

SECTION D – PACKAGING AND MARKING

D.1 PAYMENT OF POSTAGE AND FEES

All postage and fees related to submitting information forms, reports, etc., to the Contracting Officer (CO), Contract Specialist (CS), or the Contracting Officer’s Representative (COR) shall be paid by the contractor.

D.2 MARKING

All information submitted to the Contracting Officer, Contract Specialist, or the Contracting Officer’s Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.

SECTION E – INSPECTION AND ACCEPTANCE

CLAUSES INCORPORATED BY REFERENCE:

Clause Title Date

52.246-2 INSPECTION OF SUPPLIES – FIXED-PRICE AUG 1996

52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

SECTION F – DELIVERIES OR PERFORMANCE

Clause Title Date

52.242-14 SUSPENSION OF WORK APR 1984

CLAUSES INCORPORATED BY FULL TEXT:

F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK APR 1984

The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than One Hundred and Twenty (120) calendar days after receiving the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 Contracting Officer’s Representative(s) for this contract will be determined and their contact information will be provided at time of award.

G.2 Contract Officer for administering this contract:

Marilia Mateo, Contracting Officer DOI – National Park Service – Interior Region 2 PH: 305-242-7742 EM: marilia_mateo@nps.gov

G.3 TECHNICAL DIRECTION

The performance of the work required herein shall be subject to the technical direction and surveillance of the COR or his designee. As used herein, “technical direction” is direction to the Contractor which requires pursuit of certain lines of inquiry, filing in details or otherwise serving to accomplish the contract specifications. The technical direction, to be valid:

(a) Must be issued in writing consistent with the general scope of the work set forth in the contract;

b) May not constitute a new assignment of work changes to the expressed terms, conditions, or specifications incorporated into this contract;

(c) Shall not constitute a basis for extension of the contract delivery schedule.

Nothing contained in this part authorizes the Contractor to incur costs in excess of the contract price or other limitation of funds set forth in the contract due to extra work performed in response to informal directions, suggestions, or instructions (oral or written) given by representatives of the CO, unless prior to commencing such work, the Contractor: 1) directly notifies the CO; 2) requests a formal contract modification; and 3) receives written authorization to proceed from the CO.

G.4 CORRESPONDENCE

Any correspondence initiated by the Contractor shall include the Contract Number and shall be addressed to the CO or CS (original and one copy) at the address provided in the clause entitled “Contractor Administration”.

G.5 CONTRACT PAYMENTS

The Contractor shall submit invoices to the Contracting Officer for the percentage of work completed. Contractor and COR at the site must agree on the percentage of work completed.

G.6 JOB SITE ADMINISTRATION

The COR will be available at the site to inspect the work as it progresses. The COR is not authorized to make technical decisions or give technical directions; the Contractor or the Contractor’s Superintendent must contact the COR regarding such decisions and directions.

The Contractor shall have a competent superintendent (hereinafter referred to as the “Contractor’s Superintendent”) who is (i) deemed acceptable to the Government; (ii) authorized to act on the Contractor’s behalf; and (iii) to be always present on the job site when contract work is being performed.

G.7 PAYROLL RECORDS

The Prime Contractor is responsible for furnishing the Contracting Officer with one (copy of the Weekly Payroll Form WH-347 or equivalent) to include payroll records for his/her subcontractor’s. Payroll records shall be submitted within seven (7) days after the close of the payroll period and numbered in consecutive order. The Prime Contractor shall review all subcontractors’ payroll and ensure that all employees are paid in accordance with the Wage Determination, which is a part of this contract.

The Prime Contractor shall ensure that compliance is met. The Contractor is subject to the Wage and Hour Dept., U.S. Department of Labor.

G.8 SUBCONTRACTING

The Prime Contractor shall complete a Standard Form (SF1413) for each subcontractor and submit the form to the Contracting Officer or Specialist. No subcontractor shall be allowed on the site without an executed SF 1413. The Prime shall be held responsible for ensuring that his/her subcontractor’s DO NOT subcontract any portion of this work. The Prime Contractor is responsible to ensure that all subcontractors carry sufficient insurance in accordance with this contract.

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 Executive Order 13513 Prohibition on Text Messaging and Using Electronic Equipment Supplied by the Government While Driving as prescribed in Federal Leadership on Reducing Text Messaging While Driving.

PROHIBITION ON TEXT MESSAGING AND USING ELECTRONIC EQUIPMENT SUPPLIED BY THE GOVERNMENT

WHILE DRIVING (OCT 2009)

This Executive Order introduces a Federal Government-wide Prohibition on the use of text messaging while driving on official business or while using Government –supplied equipment. Additional guidance enforcing the ban will be issued at a later date. In the meantime, please adopt and enforce policies that immediately ban text messaging while driving company-owned or –rented vehicles, government-owned or leased vehicles, or while driving privately owned vehicles when on official government business or when performing any work for or on the behalf of the government.

(End of Order)

H.2 GENERIC GENDER TERMINOLOGY

Except where stipulated by the Federal Acquisition Regulations, the use of terms such as he, she, his, and her are not to be interpreted as implying other than neutral gender terms such as “it” or “their”.

H.3 SAFETY

The Contractor is responsible for establishing and maintaining compliance with all applicable laws, regulations, rules, and standards, including without limitation, those regulations, rules, and standards, promulgated for the administration and enforcement of the following laws: the Occupational Safety and Health Act (OSHA) or Federally approved State equivalent(s) thereof; the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) as amended by Superfund Amendments and Reauthorization Act (SARA); Emergency Planning and Community Right-to-Know Act (EPCRA); Clean Air Act (CAA); Clean Water Act (CWA) and Toxic Substances Control Act (TSCA); and Solid Waste Disposal Act (SWDA), as amended by Resource Conservation and Recovery Act (RCRA).

H.4 PROGRESS MEETINGS

(a) The Contractor shall be available to meet with the CO or his/her representative at the job site during construction to discuss work progress.

(b) Meetings will be scheduled by the CO with timely notification to the Contractor.

(c) At the progress meetings, the Contractor shall give oral reports of the progress on the project to the CO. If the work is behind schedule, the Contractor shall be prepared to:

(i) discuss the work and any causes of work delay(s);

(ii) present a plan to bring the work back into conformance with the schedule; or, if necessary

(iii) to propose a revised work schedule.

H.5 PAYROLLS

The Contractor must furnish copies of his weekly payrolls to the CO. Payroll submission is required weekly, seven

(7) days after close of payroll period.

H.6 OPERATION OF FACILITY DURING CONSTRUCTION

Construction activities must not interrupt the function and day-to-day operations of the facility during construction. The contractor must coordinate with the COR for any temporary measures. All temporary measures employed shall be at the Contractor’s expense and shall be removed upon completion of the contract.

H.7 WORK HOURS

Normal work hours are from 7:00 a.m. through 5:00 p.m., Monday through Friday. Contractor will not be permitted to work at the job site on Saturday, Sunday or legal holidays unless otherwise authorized by the CO and approved by the park 48 hours prior.

H.8 USE OF PREMISES

(a) Before any location, other than shown in the photos or during the site visit, is accessed, written permission shall be obtained through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor.

(b) Unless provided otherwise, the Contractor shall provide and maintain a sanitary working environment for the workforce at the site. Solid waste shall be disposed of in accordance with applicable Federal, State, and local regulations.

H.9 MAXIMUM WORK WEEK

The maximum workweek that will be approved is 40 hours. The Contractor’s proposed hours of work are to include daily starting and stopping times.

H.10 EXCAVATION AND UTILITY CLEARANCES

The Chief of Maintenance, for each park, shall ensure that the Contractor is provided with necessary excavation and utility clearances. The Contractor shall request such clearances and staking in writing to the Contracting Officer no less than ten (10) calendar days prior to the date which he/she anticipates commencement of work. The Contractor will not proceed with excavation of any kind until such clearances have been issued. Clearances will be valid from the date of issue or completion of, or otherwise directed by the issuing authority.

H.11 DISPOSAL

Debris, rubbish, and non-usable material resulting from under this contract shall be disposed in a manner that meets federal, state and local laws.

H.12 CONTRACTOR EMPLOYEES

(a) The Contractor shall provide the Contracting Officer with the name of the responsible supervisor authorized to act for the Contractor.

(b) The Contractor shall furnish sufficient personnel to perform, supervise and manage all work.

(c) Contractor employees shall conduct themselves in a proper, efficient, courteous and business-like manner.

(d) The Contractor shall remove from the site any individual whose continued employment is deemed by the contracting officer to be contrary to public interest or inconsistent with the National Park Service.

H.13 PERMITS

The contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required to perform work under this contract. The Contractor shall comply with federal, state and local laws.

Evidence of such permits and licenses shall be provided to the Contracting Officer before work commences, or as requested.

H.14 QUALITY OF WORK

Workmanship shall be of the highest quality and best practices of the trade. Contractor shall conform to all requirements of the state and county code, ANSI A 10.6 and applicable codes of the National Fires Protection Association. All replacement materials shall conform to the manufacturer specifications and standards. Substitute items shall be equal to or better that the original material and must be approved by the Government.

H.15 COMPLETION OF WORK

The time stated for completion of the project includes all materiel procurement, payroll records, corrections of all discrepancies (Punch List Items), and final clean up on premises as stated in the clause “Commencement, Prosecution and Completion of Work”, FAR 52.211-10 (APR 1984) Section F.

H.16 MATERIAL APPROVAL SUBMITTALS

The submittals contemplated by the clause herein entitles “Materials and Workmanship”, FAR 52.236-5 (APR 1984), Section I, shall be submitted to the Contracting Officer through the COR in five (5) copies. The Denver Service Center Form (DSC-1) entitled “Transmittal USDI, National Park Service”, shall be used. Contractor shall re-submit any disapproved submittals within seven (7) calendar days of disapproval.

H.17 ARCHEOLOGICAL FINDINGS

Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed and only by the Government. Should Contractor’s operations uncover, or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operation in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for the contractor, he will be compensated by an equitable adjustment under the General Provision of the Contract.

H.18 DOI ELECTRONIC INVOICING ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET

PAYMENT PLATFORM (IPP) APRIL 2013

Payment requests must be submitted electronically through the U. S. Department of the Treasury’s Invoice Processing Platform System (IPP).

“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

The contractor must submit to the CO and the COR the payroll for the general contractor and any applicable sub contractors and an updated schedule.

The contractor must us the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instruction via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment the Contractor must submit a waiver request in writing to the Contracting Office with its proposal or quotation.

(End of Local Clause)

H.19 DOI AAAP-0050 V2 NOTICE TO CONTRACTORS

CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DECEMBER 2015)

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of Notice)

SECTION I – CONTRACT CLAUSES

1452.203-70 Restriction on Endorsements JUL 1996

1452.215-70 Examination of Records by the Department of the Interior APR 1984 1452.224-01 Privacy Act Notification (July 1996) Deviation JUL 1996 1452.236-70 Prohibition Against Use of Lead-based Paint JUL 1996 52.202-01 Definitions JUN 2020

52.203-03 Gratuities APR 1984 52.203-05 Covenant Against Contingent Fees MAY 2014 52.203-06 Restrictions on Subcontractor Sales to the Government JUN 2020 52.203-07 Anti-Kickback Procedures MAY 2014 52.203-08 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity MAY 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions OCT 2010 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights

APR 2014

52.204-01 Approval of Contract JUN 2020 52.204-04 Printed or Copied Double-Sided on Recycled Paper MAY 2011 52.204-19 Incorporation by Reference of Representations and Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab and other Covered Entities

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.209-06 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment

NOV 2021

20.209-09 Updates on Publicly Available Information Regarding Responsibility Matters OCT 2018 52.215-02 Audit and Records–Negotiation JUN 2020 52.215-08 Order of Precedence–Uniform Contract Format OCT 1997 52.215-10 Price Reduction for Defective Cost or Pricing Data AUG 2011 52.215-12 Subcontractor Certified Cost or Pricing Data AUG 2020 52.219-08 Utilization of Small Business Concerns OCT 2022 52.219-14 Limitations on Subcontracting OCT 2022 52.222-01 Notice to the Government of Labor Disputes FEB 1997 52.222-03 Convict Labor JUN 2003 52.222-04 Contract Work Hours and Safety Standards – Overtime Compensation MAY 2018 52.222-06 Construction Wage Rate Requirements AUG 2018 52.222-07 Withholding of Funds MAY 2014 52.222-08 Payrolls and Basic Records JUL 2021 52.222-09 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations MAY 2014 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition of Segregated Facilities APR 2015 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment

Opportunity for Construction

FEB 1999

52.222-26 Equal Opportunity SEPT 2016 52.222-27 Affirmative Action Compliance Requirements for Construction APR 2015 52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Affirmative Action for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor Relations Act DEC 2010 52.222-50 Combat Trafficking in Persons NOV 2021 52.222-54 Employment Eligibility Verification MAY 2022 52.222-55 Minimum Wages Under Executive Order 13658 JAN 2022 52.223-03 Hazardous Material Identification and Material Safety Data FEB 2021 52.223-05 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-06 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving JUN 2020 52.225-09 Buy American – Construction Materials MAY 2014 52.225-10 Notice of Buy American Act Requirement – Construction Materials MAY 2014 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-04 Patent Indemnity-Construction Contracts DEC 2007 52.228-02 Additional Bond Security OCT 1997 52.228-05 Insurance – Work on a Government Installation JAN 1997 52.228-11 Pledges of Assets FEB 2021 52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022 52.228-15 Performance and Payment Bonds – Construction JUN 2020 52.229-03 Federal, State, and Local Taxes FEB 2013 52.232-05 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments NOV 2021 52.232-17 Interest MAY 2014 52.232-23 Assignment of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer – System for Award Management OCT 2018 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors NOV 2021 52.233-01 Disputes MAY 2014 52.233-03 Protest after Award AUG 1996 52.233-04 Applicable Law for Breach of Contract Claim OCT 2004 52.236-02 Differing Site Conditions APR 1984 52.236-03 Site Investigation and Conditions Affecting the Work APR 1984 52.236-04 Physical Data APR 1984 52.236-05 Material and Workmanship APR 1984 52.236-06 Superintendence by the Contractor APR 1984 52.236-07 Permits and Responsibilities NOV 1991 52.236-08 Other Contracts APR 1984 52.236-09 Protection of Existing Vegetation, Structures, Equipment, Utilities and

Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JULY 1995 52.243-04 Changes JUN 2007 52.248-03 Value Engineering-Construction OCT 2020 52.249-02 Termination for Convenience of the Government (Fixed-Price) APR 2012 52.249-10 Default (Fixed-Price Construction) APR 1984 52.252-04 Alterations in Contract APR 1984 52.252-06 Authorized Deviations in Clauses NOV 2020 52.253-01 Computer Generated Forms JAN 1991

CLAUSES INCORPORATED BY FULL TEXT:

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/

I.2 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR APR 1984

The Contractor shall perform on the site, and with its own organization, work equivalent to at least fifteen percent (15%) of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction, and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of Clause)

I.3 1452.204-70 RELEASE OF CLAIMS – DEPARTMENT OF THE INTERIOR JUL 1996

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of Clause)

I.4 1452.228-70 LIABILITY INSURANCE JUL 1996

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

1. Worker’s compensation and employer’s liability: $1,000,000

2. General Liability: $500,000 each person and $1,000,000 each occurrence

3. Property Damage: $2,000,000

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

(c) The contractor shall name the United States, National Park Service, as the insured party(ties) on the liability insurance policy.

(End of Clause)

I.5 52.225-9 BUY AMERICAN – CONSTRUCTION MATERIALS OCT 2022

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.

supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)).

The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components. (1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .