Section 02827 Albert Creek Fence Project Fence Removal Final.docx
DOCX document 22 KB Posted
- Attached to
- ALBERT CREEK FENCE Federal contract opportunity
- Solicitation number
- 140L6220Q0106
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 01009 General Albert Creek Fence Project Final.docx | DOCX document | |
| Albert Creek Fence Project BLM Standard Panels and Gates Drawings.docx | DOCX document | |
| Albert Creek Fence Project Work Data Sheet Final.docx | DOCX document | |
| Albert Creek Fence bid schedule.xlsx | XLSX spreadsheet | |
| Section 02826 Albert Creek Fence Project Drainage Crossings Final.doc | DOC document | |
| Albert Creek Fence SOW Final.docx | DOCX document | |
| Albert Creek Fence Project Material Specifications Final.doc | DOC document | |
| Section 01505 Albert Creek Fence Project Mobilization and Demobilization Final.doc | DOC document | |
| Sol_140L6220Q0106.pdf | ||
| Section 02824 Albert Creek Fence Project Wire Fence and Gates Final.docx | DOCX document | |
| Albert Creek Fence Drawings 2020 Contract.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02827
FENCE REMOVAL
PART 1: GENERAL
1.1 SUMMARY
A. Section Includes: Removing existing three barbed wire fence, including all wood, Tee posts, stress and end panels and drainage crossings.
B. Requirements: Access roads shall not be constructed along fence lines or to the jobsite unless written approval is granted by the Contracting Officers Representative. Cross-country travel with wheeled or tracked vehicles shall be only to and along fence lines.
C. Do not damage adjoining pasture fences. Leave any posts shared by adjoining fences.
PART 2: PRODUCTS
2.1 Not Applicable
PART 3: EXECUTION
3.1 REMOVAL
A. Removal of Existing Fence: Furnish all labor and equipment necessary to completely remove all fencing where the new fence will be constructed.
B. Disposal of debris shall be according to Section 01009 – General Information and Requirements.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: Fence removal will be measured and paid for by the linear foot removed as measured along the ground surface next to the fence prior to removal, including distance across gate openings, end, stress, and corner panels and drainage crossings.
4.2 BASIS OF PAYMENT
A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
| Pay Item | Pay Unit | |
| Fence Removal and Disposal | Linear Foot |
END OF SECTION 02827
Albert Creek Fence FENCE REMOVAL
02827 - 3