RFQ_ATTACHMENT_3_-_LINE_ITEM_SCHEDULE.pdf

PDF 23 KB Posted

Attached to
Automated Microbial Culture, Sample Preparation, and Analysis System Federal contract opportunity
Solicitation number
SB134117RQ0418
Issued by
Department of Commerce National Institute of Standards and Technology

About this file

RFQ ATTACHMENT 3 - LINE ITEM SCHEDULE

View the file

Other files for this federal contract opportunity

Other files attached to Automated Microbial Culture, Sample Preparation, and Analysis System, newest first.
File Type Posted
RFQ_Amendment_1_-_Q&A.pdf PDF
RFQ_ATTACHMENT_2_-_APPLICABLE_PROVISIONS_&_CLAUSES.docx DOCX document
RFQ_ATTACHMENT_4_-_DRAFT_RFQ_WITH_AMENDMENTS_1-3_&_Q&A.pdf PDF
RFQ_ATTACHMENT_1_-_SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ ATTACHMENT 3 – LINE ITEM SCHEDULE

The Contractor shall provide all deliverables in accordance with the Line Item Schedule below. The overall period of performance of this purchase order shall not exceed one (1) year after receipt of this purchase order (ARO).

Line Item Schedule Line

Item # Description Base or Option

Qty Due Date

0001 Automated Microbial Culture, Sample Preparation, and Analysis System

Base 1 210 Days ARO

0002 Enclosure Base 1 210 Days ARO 0003 System Design Base 1 30 Days ARO

(Payment 1 – 40%) 0004 Positive-Pressure Solid Phase Extraction Option 1 *See Note 1 Below 0005 Active SBS Plate Position Option 1 *See Note 1 Below 0006 Automated Bacterial Colony Picking Option 1 *See Note 1 Below 0007 Thermocycler Option 1 *See Note 1 Below 0008 Liquid Waste Collection System Option 1 *See Note 1 Below 0009 Additional Absorbance Plate Readers Option 2 *See Note 1 Below 0010 Additional Plate Sealer Option 1 *See Note 1 Below 0011 Software for Control of Automated System and

Scheduling of Automated Processes Base 1 210 Days ARO

0012 Method Programming Option 1 *See Note 1 Below 0013 Factory Acceptance Testing (FAT) Base 1 120 days after NIST

Acceptance of System Design (NTE 2 days in duration) (Payment 2 - 30%)

0014 Installation Base 1 224 Days ARO 0014 Site Acceptance Testing (SAT) 1 231 Days ARO (NTE 2 days in duration) 0015 Training Base 1 235 Days (Payment 3 –

30%)

*Note 1: If NIST chooses to exercise an option line item, depending on the date of exercise, the Contractor shall deliver option item deliverables by the later of 210 ARO or 90 days from the date of option exercise.