VTL-QAs.docx
DOCX document 17 KB Posted
- Attached to
- NIST Vertical Turning Lathe Federal contract opportunity
- Solicitation number
- SB1341-15-RQ-0573
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| syn_sol.docx | DOCX document | |
| SOW-VTL.doc | DOC document | |
| syn_sol.docx | DOCX document | |
| SOW-VTL.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SB1341-15-RQ-0573, Amendment 1
Question #1:
4.1 Machine Size
Is the machine height a facilities height limit?
Answer: Yes.
#2: If yes can the machine be in a pit?
Answer: No, NIST cannot recess the VTL into a pit.
#3: 4.7 Turret Will other tool holding systems be considered if they meet the other requirements in this section?
Answer: No. The proposed VTL must conform to static and live tool requirements.
#4: 4.9 Associated tooling Included Calls for two hydraulic chucks. Is one chuck that covers the full range acceptable?
Answer: No, NIST requires two chucks as a smaller chuck will be used the majority of the time.
#5 The Scope states “Contractor shall manufacture, Deliver, Install and Demonstrate the operation of VTL.” We do not Manufacture…Do I need to take exception to this since we do not manufacture this machine?
Answer: The word manufacture has been changed to provide in the Statement of Work.
#7: Is this machine going into the same building that the Large Boring Mill is going into?
Answer: This machine will be located in the same building as the Boring Mill, but in a separate wing with separate access.
#8: Will there be a site visit scheduled?
Answer: No site visit will be scheduled. The Access point is a 10ft high by 12ft wide door.
#9: Is this machine planned to be installed before or after the Boring Mill? This could impact the rigging costs.
Answer: NIST expects the VTL to be installed before the HBM. Again, the VTL will be located in a different wing of the building.
#10: In the SOW Section 4.5, acceptable controllers are listed at "Fanuc, Mazcontrol, or Heidenhain". I believe that should read Mazatrol since there are multiple machines in the shop that have this control. Our official name for the current controls are "Mazatrol Matrix Nexus 2; or Mazatrol Smart". Can you clarify that these would be acceptable controls.
Answer: Mazatrol is correct. The SOW has been revised accordingly.
#11: In the Synopsis, under "Required Submissions" Section 3 list two statements regarding acceptance and exceptions to the terms and conditions. Is there a place where I can get a copy of the complete terms and conditions that will be included in the award document?
Answer: All terms and conditions are contained in the Solicitation document. The revised Solicitation document includes a Payment Schedule, which was omitted from the original posting. The provisions will be removed from the resultant Purchase Order prior to award.
File details come from the government source that posted it. Updated .