About this file

Solicitation for Murcilago CR Barracks Remodeling

View the file

Other files for this federal contract opportunity

Other files attached to Murcilago CR Barracks Remodeling, newest first.
File Type Posted
Solictation_Questions.xlsx XLSX spreadsheet
J.2_Attachments.zip ZIP file
J.3_Attachments.zip ZIP file
J.1_Adminstrative_Documents.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

SAQMMA17R0011 SEALED BID (IFB)

X NEGOTIATED (RFP)

2. TYPE OF SOLICITATION 3. DATE ISSUED

10/31/2016

RATING

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

CODE LMAQM

OFFICE OF ACQUISITION MANAGEMENT (A/LM/AQM)

PO BOX 9115, ROSSLYN STATION

US DEPARTMENT OF STATE

ARLINGTON, VA 22219

7. ISSUED BY 8. ADDRESS OFFER TO

9. FOR INFORMATION EMAIL: a. NAME

Billy Morris

b. TELEPHONE NO. (Include area code)(NO COLLECT CALLS)

703-875-5811

c. EMAIL morrisb@state.gov

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Funds for this project are not currently available but will be at the time of award.

11. The Contractor shall begin performance within ___10___ calendar days and complete it within ___240___ calendar days after receiving award, X notice to proceed. This performance period is X mandatory negotiable. ( (See __.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and ____ copies to perform the work required are due at the place specified in item 8 by __10:00:00__ (hour) local time __11/29/2016 __ (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

a.

b. An offer guarantee is, X is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

d. Offers providing less than ____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA - FAR (48 CFR) 53.236-1(e)

SAQMMA17R0011

am

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CONTACT: DUNS:

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No futher contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) Larry A. Pruitt

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 4-85) BACK

Table of Contents

Section Description Page Number

B Supplies or Services and Prices/Costs

001 Remodeling Murcilago CR Barracks in accordance with the Statement of Work and Designs

1.00 LT

Doc Ref No:

Delivery Date FOB:

SAQMMA17R0011

Line Item Summary

Solicitation Number:

SAQMMA17R0011

Contract Number: Title: Murcilago CR Barracks Remodeling

Date of Solicitation:

10/31/2016

Line Item No. Description Quantity Unit Unit Price Total Cost

Table of Content

SAQMMA-17-R-0011 Page 5 of 121

PART I - THE SCHEDULE

SECTION A – FORM

SECTION B – PRICING

B.1 PRICING

B.2 CONTRACT PRICE - CONTRACT LINE ITEM NUMBERS (CLIN)

B.3 TYPE OF CONTRACT

B.4 COST OF MATERIALS/EQUIPMENT

B.5 GOVERNMENT FURNISHED PROPERTY/EQUIPMENT

B.6 RFP QUESTIONS AND RESPONSES

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

GENERAL DESCRIPTION

C.1 Specific Task C.1.1 Preliminary work

C.1.2 Construction of new walls

C.1.3 Bathrooms Extension

C.1.4 Laundry Renovation

C.1.5 Floors Renovation

C.1.6 Paint and Coating for Walls and Countertops

C.1.7 Ceilings

C.1.8 Hydraulic and Sanitary Systems

C.1.9 Construction of the Electric System

C.1.10 Construction of Special Systems

C.1.11 Install Doors and Windows

C.2 General Specifications

C.2.1 QUANTITIES

C.2.2 TRIALS AND TESTS

C.2.3 WORK EXECUTION

C.2.4 COST OF THE PROJECT

C.3 Task Specifications

C.3.1 PRELIMINARY WORK

C.3.2 EARTHWORK, EXCAVATION AND BACKFILLING

C.3.3 CONCRETE STRUCTURES

C.3.4 STEEL REINFORCEMENT AND METALLIC STRUCTURES

C.3.5 MASONRY

C.3.6 METALLIC ROOFS & CEILING

C.3.7 COATINGS FOR WALLS AND FLOORS

C.3.8 EXTERIOR WORKS

SAQMMA-17-R-0011 Page 6 of 121

C.3.9 DOORS AND WINDOWS

C.3.10 SANITARY DEVICES & COUNTERTOPS

C.3.11 POTABLE WATER SYSTEM

C.3.12 SEWER AND STORM SYSTEMS

C.3.13 ELECTRIC SYSTEM

C.3.14 MISCELLANEOUS

SECTION D – PACKAGING AND MARKING

D.1 RESERVED

D.2 DEPARTMENT OF STATE MAIL AND COURIER ADDRESS

D.3 PACKAGING REQUIREMENTS FOR MAIL AND COURIER SHIPMENT OF DOCUMENTS AND

DRAWINGS

D.4 DOCUMENTATION OF SHIPMENTS

D.5 DESPATCH AGENTS

SECTION E – INSPECTION AND ACCEPTANCE

E.1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996) (Reference 46.312)

E.2 SUBSTANTIAL COMPLETION

E.3 USE OF EQUIPMENT BY THE GOVERNMENT

E.4 FINAL COMPLETION AND ACCEPTANCE

E.5 QUALITY ASSURANCE AND QUALITY CONTROL

E.6 PROJECT COMMUNICATIONS

SECTION F – DELIVERIES OR PERFORMANCECLAUSES INCORPORATED BY

REFERENCE

F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

Alternate I (APR 1984) (Reference 11.404) F.2 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION (SEPT 2000) (Reference 11.503) F.3 52.211-13 TIME EXTENSIONS (SEPT 2000) (Reference 11.503) F.4 52.242-14 SUSPENSION OF WORK (APR 1984) (Reference 42.1305)

F.5 SCHEDULES

F.6 WORK HOURS

F.7 EXCUSABLE DELAYS

F.8 DELIVERABLES/SUBMITTALS

F.9 RESERVED

F.10 PROJECT EXECUTION SCHEDULE

F.11 DOCUMENTATION OF REQUESTS FOR EXTENSION

F.12 SUSPENSION OF WORK- NONCOMPLIANCE WITH CONTRACT REQUIREMENTS

F.13 NOTICES TO PROCEED

F.14 RESERVED

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 DOSAR 652.232-70 PAYMENT SCHEDULE AND INVOICE SUBMISSION (FIXED-PRICE) (AUG

1999) (Reference 632.908(a))

G.2 DOSAR 652.242-70 CONTRACTING OFFICER’S REPRESENTATIVE (COR) (AUG 1999)

(Reference DOSAR 642.272(a))

G.3 COST LOAD SCHEDULE FOR PROGRESS PAYMENTS

G.4 MONTHLY PROGRESS PAYMENT REQUESTS (Application for Payment)

G.5 CERTIFICATION OF PAYMENT TO SUBCONTRACTORS

G.6 AUTHORITY OF CONTRACTING OFFICER

G.7 PAYMENT

G.8 INVOICING

G.9 CONTRACT PROGRESS PAYMENT

G.10 RESERVED

SAQMMA-17-R-0011 Page 7 of 121

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 AUTHORIZED INSURANCE CARRIERS FOR DBA INSURANCE

H.2 RESERVED

H.3 INSURANCE

H.4 BOND REQUIREMENTS

H.5 SAFEGUARDING OF INFORMATION

H.6 PUBLIC RELEASE OF INFORMATION

H.7 DOCUMENTS - OWNERSHIP AND USE

H.8 REQUIREMENT FOR SHOP DRAWINGS

H.9 GOVERNING LAW

H.10 LAWS AND REGULATIONS

H.11 LANGUAGE PROFICIENCY

H.12 WAR RISKS

H.13 ASSIGNMENT

H.14 REVIEW OF DOCUMENTS AND LOCAL CONDITIONS

H.15 INDEMNIFICATION AGAINST CLAIMS AND ENCUMBRANCES

H.16 OTHER SERVICES NOT TO RELIEVE CONTRACTOR

H.17 ERRONEOUS REPRESENTATIONS

H.18 AUTHORIZED REPRESENTATIVE OF THE CONTRACTING OFFICER

H.19 Reserved

H.20 REFERENCED STANDARDS

H.21 NOTIFICATION OF DIFFERING SITE CONDITIONS

H.22 EQUITABLE ADJUSTMENTS

H.23 PRESERVATION OF REFERENCE POINTS AND BENCHMARKS

H.24 CERTIFICATION OF BOUNDARY MARKERS

H.25 ORGANIZATION OF DRAWINGS AND SPECIFICATIONS

H.26 RESPONSIBILITY OF CONTRACTOR

H.27 ORGANIZATION AND DIRECTION OF THE WORK

H.28 CONSTRUCTION OPERATIONS

H.29 SUBCONTRACTORS AND SUPPLIERS

H.30 TEMPORARY FACILITIES AND SERVICES

H.31 DEFENSE BASE ACT INSURANCE

H.32 CONTRACTOR PERSONNEL

H.33 Reserved

H.34 WATCHMEN

H.35 MATERIALS AND EQUIPMENT

H.36 IMPORTED MATERIALS, EQUIPMENT, AND PERSONNEL

H.37 HAZARDOUS MATERIAL IDENTIFICATION

H.38 SPECIAL WARRANTIES

H.39 DEFINITIONS

H.40 INFORMATION CONCERNING THE HOST COUNTRY

H.41 CONFERENCES

H.42 CHANGE ORDER PROCESSING

H.43 ENGLISH LANGUAGE DOCUMENTATION REQUIREMENT

H.44 TRAFFICKING PERSONS COMPLIANCE PLAN CERTIFICATION

H.45 LABOR RELATIONS & ACTIONS

PART II - CONTRACT CLAUSES

SECTION I – CONTRACT CLAUSES

I.1 DEFINITIONS

I.2 THE CONTRACT

I.3 STANDARDS OF CONDUCT

I.4 FINANCIAL RECORDS AND ACCOUNTING

I.5 MISCELLANEOUS

I.6 MODIFICATIONS AND PROPOSAL SUBMISSION

I.7 BONDS AND INSURANCE

I.8 TIME

SAQMMA-17-R-0011 Page 8 of 121

I.9 GOVERNMENT’S RESPONSIBILITIES

I.10 CONTRACTOR’S RESPONSIBILITIES

I.11 PRELIMINARY MATTERS

I.12 PROTECTION OF PERSONS AND PROPERTY

I.13 SUBCONTRACTORS AND SUPPLIERS

I.14 CONSTRUCTION PERSONNEL

I.15 MATERIALS AND EQUIPMENT

I.16 CHANGES AND EQUITABLE ADJUSTMENTS

I.17 PAYMENTS AND COMPLETION

I.18 CLAIMS, DISPUTES AND PROTESTS

I.19 SUSPENSION AND TERMINATION

I.20 ADMINISTRATION

SECTION J – LIST OF ATTACHMENTS

J.1 ADMINISTRATIVE DOCUMENTS

J.2 Drawings J.3 AutoCAD Drawing

PART IV -- REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS

OF OFFERORS

K.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) (Reference 4.1202) K.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) (Reference 9.104-7(b))

K.3 52.230-1 COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION (OCT 2015)

(Reference 30.201-3) K.4 52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997) (Reference 36.520) .. 103 K.5 DOSAR 652.225-70 ARAB LEAGUE BOYCOTT OF ISRAEL (AUG 1999) (Reference DOSAR 625.7002(a))

K.6 DOSAR 652.228-70 DEFENSE BASE ACT – COVERED CONTRACTOR EMPLOYEES (JUN 2006)

(Reference DOSAR 628.309-70(a))

K.7 RESERVED

K.8 52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN

ACTIVITIES OR TRANSACTIONS RELATING TO IRAN—REPRESENTATION AND CERTIFICATION

(OCT 2015) (Reference 25.1103(e)

K.9 52-222-56 CERTIFICATION REGARDING TRAFFICKING IN PERSONS COMPLIANCE PLAN

(MAR 2015)

K.10 652.209-79 REPRESENTATION BY CORPORATION REGARDING AN UNPAID DELINQUENT

TAX LIABILITY OR A FELONY CRIMINAL CONVICTION UNDER ANY FEDERAL LAW (DEVIATION

PIB 2014-21) (SEPTEMBER 2014)

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

L.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) (Reference 52.107(a))

L.2 52.204-6 DATA UNIVERSAL NUMBERING SYSTEM (DUNS) NUMBER (JUL 2013)

(Reference 4.607(b)) L.3 DOSAR 652.206-70 ADVOCATE FOR COMPETITION/OMBUDSMAN (FEB 2015) (Reference

DOSAR 606.570)

L.4 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)

(Reference 14.201-6) L.5 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991) (Reference 14.201-6) L.6 52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004) (Reference 15.209) 108

L.7 52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)--

ALTERNATE I (OCT 1997) (Reference 15.209)

SAQMMA-17-R-0011 Page 9 of 121

L.8 52.232-14 NOTICE OF AVAILABILITY OF PROGRESS PAYMENTS EXCLUSIVELY FOR SMALL

BUSINESS CONCERNS (APR 1984) (Reference 32.502-3) 52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER (JUL 2013) (Reference 32.1110(g))

L.9 MAGNITUDE OF CONSTRUCTION PROJECT

L.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)--ALTERNATE I (FEB 1995) (Reference 36.523) 108

L.11 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) (Reference 11.204(a))

L.12 52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM

DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION

INFORMATION SYSTEM (ASSIST) (APR 2014) (Reference 11.204(b)) L.13 52.216-1 TYPE OF CONTRACT (APR 1984) (Reference 16.105)

L.14 DEFENSE BASE ACT INSURANCE

L.15 52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984) (Reference 32.502-3(a)) L.16 52.233-2 SERVICE OF PROTEST (SEPT 2006) (Reference 33.106)

L.17 PROPOSAL PREPARATION INSTRUCTIONS

SECTION M – EVALUATION FACTORS FOR AWARD

M.1 RESERVED

M.2 EVALUATION OF OFFERS

M.3 EVALUATION OF PRICE

M.4 BASIS OF AWARD

M.5 JOINT VENTURE/SIGNED STATEMENT OF JV INTENT AND DESCRIPTION OF PARTNERSHIP

M.6 AWARD WITHOUT DISCUSSIONS

Part I - The Schedule

SECTION B

PRICING

SAQMMA-17-R-0011 Page 10 of 121

SECTION B – PRICING

Note:

Clauses numbered 52.XXX… Are Federal Acquisition Regulation Clauses Clauses numbered DOSAR 652.XXX… Are Department of State Acquisition Regulation Clauses

B.1 PRICING

B.1.1 As a firm-fixed price contract, the Contract Price includes all labor, materials, equipment and services necessary to accomplish the construction required by the Contract. Documents including applicable customs duties, transportation to the site, storage, premiums for insurance and bonds required by the Solicitation Documents and/or the Contract Documents, permits, license and inspection fees, taxes, and all other items called for by the contract or otherwise necessary for performance of the contract. The Contract Price may be adjusted only by a written Contract modification signed by the Contracting Officer.

B.1.2 The contractor shall complete all work, including furnishing all labor, material, equipment and services as called for and required by the terms and conditions of this contract document and all attachments hereto.

The maximum time allowable for performance has been identified in Section/Paragraph F.1, clause 52.211- 10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (Reference FAR 11.404(b)). The price is firm fixed-price and shall include all labor, materials, equipment, services, overhead and cost for insurance required by Section/Paragraph I.7 52.228-3, Workers’ Compensation Insurance (Defense Base Act) (for DBA Insurance also see Sections/Paragraphs H.1 and I.16 and I.7 52.228-4, Workers’ Compensation and War-Hazard Insurance Overseas (APR 1984)

B.1.3 All other taxes should be included in the firm fixed price and not separately reimbursable. (See Section

B.1.1)

B.2 CONTRACT PRICE - CONTRACT LINE ITEM NUMBERS (CLIN)

CLN Description Unit Price Unit of Issue

QTY Total

0001 Remodeling Murcilago CR Barracks in accordance with the Statement of Work and Designs

LT 1

TOTAL

B.3 TYPE OF CONTRACT

This contract is Firm Fixed-Price payable entirely in the currency indicated on the SF1442. No additional sums will be payable because of any escalation in the cost of materials, equipment, and services or labor, or because of the contractor’s failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract. Nor will the contract price be adjusted because of fluctuations in currency exchange rates. Changes in the contract price or time to complete will be made only due to changes made by the Government in the work to be performed, or by delays caused by the Government.

B.4 COST OF MATERIALS/EQUIPMENT

The cost of any materials or equipment required in conjunction with the services rendered herein shall be included in the proposed firm fixed-price.

B.5 GOVERNMENT FURNISHED PROPERTY/EQUIPMENT

52.245-2 Government Property Installation Operation Services

SAQMMA-17-R-0011 Page 11 of 121

The US Government will not furnish equipment and materials to be incorporation into the work by the contractor.

B.6 RFP QUESTIONS AND RESPONSES

Request for Proposal questions are submitted by email by the contractor(s) and responded to by the Government by posting on FBO.gov. Q&A does not change the RFP. The Q&A is intended to clarify requirements and to reflect the parties understanding of the specific RFP performance requirements at time of award. The initial RFP as amended shall form the contract between the contracting parties. Q&A will be reviewed and utilized during the course of contract execution, performance to ensure the descriptive and instructive clarifications provided and used to assure understanding of the performance requirements and relied on during the RFP, and proposal development phase are implemented.

SAQMMA-17-R-0011 Page 12 of 121

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

REMODELING OF BARRACKS FOR THE

POLICE ACADEMY AT MURCIELAGO

COSTA RICA

GENERAL DESCRIPTION

The Embassy of the United States of America, through the International Narcotics and Law Enforcement (INL) Affairs Office, and in cooperation with the Costa Rican Police Academy, is heading an infrastructure improvement project of the Police Academy training site at Murcielago. The goal of the project is to improve the barracks facilities used by the students during their assigned periods of training.

The overall intent of the contractual effort for this project is to remodel the existing building according to the architectural design that has been performed by the INL technical advisor. The existing building is located at the Murcielago Police Academy training site, in the vicinity of Cuajiniquil de La Cruz, Guanacaste, Costa Rica, (approximately 168 miles from San Jose.)

The project shall be conducted in accordance with the plans and specifications detailed in this document. The Contractor shall perform the following work:

C.1 Specific Task

C.1.1 Preliminary work

Preliminary work includes the construction of temporary facilities according to the specifications detailed in Section 3.1.

Also preliminary work includes the demolition of the existing walls, windows and doors that are no longer needed in order to accomplish with the new architectural distribution.

The preliminary work shall also include a technical revision of the designs and the technical advice in order to nationalize the designs and accomplish with all the local requirements that the host country demands for construction approvals. Therefore the contractor shall provide all the qualified technical staff that will be responsible of all the designs, and will develop all the drawings according the local regulations based on the designs, drawings and specifications stated in this document.

C.1.2 Construction of new walls

The contractor shall build the walls according to the architectural drawings and these specifications, nevertheless the contractor shall guarantee the stability of the walls, therefore the contractor shall include any type of reinforcement that he considers and that is not included in these specifications and drawings.

The walls shall be finished with plaster (stucco) according to the materials specifications, this type of finish will also be applied to the existing exterior and interior block walls in the areas that are visible and in the area of the improvement that are detailed in drawings.

C.1.3 Bathrooms Extension

The contractor shall design and build the appropriate structure for the extension of the barracks’ bathrooms

(102) in order to accomplish with the new architectural design. The design shall be based on concrete (for foundations and columns) and a metallic structure (for the roof) covered with a thermal and acoustic roof. The floor shall be built with reinforced concrete (minimum thickness 10cm) and covered with ceramic tiles according to the specifications.

In order to develop the bathrooms for men (area 102), the contractor shall demolish the floor of the existing bathrooms and shall build a new concrete floor according to the new architectural distribution including the extension. The new floor shall be constructed according to detail #1 specified at drawing AD-07.

SAQMMA-17-R-0011 Page 13 of 121

C.1.4 Laundry Renovation

At the back of the existing building are located two rudimentary laundries, these laundries shall be reconstructed according to the new architectural design. This renovation includes the design and build of the appropriate structure for the laundries (101) in order to accomplish with the new design. The design shall be based on concrete (for foundations and columns) and a metallic structure (for the roof) covered with a thermal and acoustic roof. The floor shall be built with reinforced concrete (minimum thickness 10cm) and covered with ceramic tiles according to the specifications. Also the new floor shall be constructed according to detail #1 specified at drawing AD-07.

C.1.5 Floors Renovation

Also a renovation of floors with an epoxy treatment shall be performed for the laundries (101), the interior hall

(302) and the armory (201). For this area the contractor shall first repair all the cracks and holes detected in the existing concrete floor, then shall clean the area and build a colored epoxy layer according to the specifications (See Chapter 7). Also it is needed to clarify that the floor for the laundries (101) shall be concrete according to C.1.4.

All the bathrooms (102, 301), the barracks (100), the auditorium (103), and the instructors’ dormitories (300) shall be covered with new ceramic floor tiles ( Ceramic tiles or Porcelanato / see material specifications) according to the specifications, except for the showers areas that will be covered with an antiskid ceramic tile.

The floors finishing is detailed at drawing AD-07.

Between the finished floors and the interior walls mop boards of timber or vinyl shall be provided and installed by the Contractor (see finishing schedule at drawing AD-06), except for those areas that are covered with ceramic tiles.

C.1.6 Paint and Coating for Walls and Countertops

New ceramic wall tiles shall be provided and installed by the Contractor in all the bathrooms (102, 301) and the laundries (101) according to drawings AD-02, AD-03, AD-04 and AD-06.

The new ceramic wall tile shall be according to the respective specification.

All the walls of the project shall be painted with acrylic paint according to the spec except for those that are covered with ceramic tiles. The paint shall include the existing walls at the interior and exterior areas of the building.

Also the existing metallic structure of the building shall be painted with enamel in order to provide an appropriate maintenance of the facilities. The contractor shall cover with two layers of enamel.

Regarding the countertops for the barrack’s bathrooms (102), and for the medic center (202) the contractor shall build it with granite. Granite Countertop shall be according to the respective specification. The Contractor shall guarantee the stability of the Countertop that will support the washbasins.

C.1.7 Ceilings

Ceiling type “gypsum” of 9 mm in thickness with metallic support shall be installed for all the bathrooms (102, 301). For this purpose contractor shall follow the respective ceiling specification.

C.1.8 Hydraulic and Sanitary Systems

Construction of a potable water system:

Following the specifications stated in the project and drawings W-01, and W-02, the contractor shall provide, place, connect, fix and test all the pipes, accessories and special items, as well as the required valves, which together will serve to conduct potable water. The potable water comes from two sources, the first one from the existing water supply that is located in front of the existing building, which shall provide the water to the

SAQMMA-17-R-0011 Page 14 of 121 different sanitary devices of the bathrooms. The second water supply comes from a main line at rear of the building; this source shall provide water to the laundries. The Contractor shall include all the accessories needed to connect the building to the existing water system and according to drawing W-01.

The system shall follow the local regulations and the regulations of the American Water Works Association (AWWA), and the National Standard Plumbing Code (NSPC).

Maintenance and Construction of the Sewer System:

The Contractor shall provide, place, connect and satisfactorily test the pipes, revision points, and other devices of the entire sewer systems for the barracks’ bathrooms (102) and for the sink located at the medic center (202) according to drawings SW-01 and SW-02. Requirements include a connection to an existing sewage system located besides the building to provide appropriate drainage of wastewater from the bathrooms and the construction of inspection wells constructed with reinforced concrete. Regarding the sewage system of the bathrooms for instructors (301), the contractor shall clean all the existing pipes providing an appropriate maintenance.

Also the contractor shall repair the existing metallic gutters that collects the rainy water from the roof. The contractor can use the existing metallic gutter that does not have holes or that is not bent. Also all the joints between walls and roof shall be renovated in order to avoid leaks, this work shall be done using galvanized flashings and waterproof additives that guarantee the work.

C.1.9 Construction of the Electric System

The contractor shall design and build the electric system to meet the basic requirements identified in drawings EL-01, EL-02, and EL-03 and according to the Local Electric Code. This must be developed and certified by a professional (Electric Engineer).

The internal electric system of the building shall be totally reconstructed, therefor the contractor shall designed and built it according the basic requirements detailed in drawings EL-01, EL-02, and EL-03. Also the contractor shall design and build the electric connections (outlets, pipes and cables) for the air conditioning and ventilation systems. It is needed to clarify that the ventilation system and the air conditioning system shall be designed by the Contractor, for this design review section C.1.10.

The electric supply for the building shall be from the electric line that is located in front of the building. The final connection from the electric supply to the main electric boards shall be designed by the Contractor in order to have the electric service for the basic requirements.

This contract does not include the construction of the connection from the existing transformer to the main electric boards, the contractor can use the actual electric connection (transformer to the main electric boards) to provide the power, but it is needed to remark that If it the Contractor’s electric design requires an improvement of the actual connection, the contractor shall deliver all the drawings, specification and the economical proposal to the COR in order to process a modification. In this case INL will evaluate the request and will approve it through the CO.

C.1.10 Construction of Special Systems

C.1.10.1 Construction of the Fire Protection System:

The fire protection system includes a fire alarm system with smoke detectors, and Fire Host Cabinets that should be according to drawings EL-03, W01 and W-02.

The contractor shall design and build this system according to the mentioned drawings and shall include the equipment and pipes for the Fire Host Cabinets according to the specifications (Also review the water system).

C.1.10.2 Air Conditioning and Ventilation System:

The contractor shall design the air conditioning system considering the following requirements:

SAQMMA-17-R-0011 Page 15 of 121

All the areas of the building will have an air conditioning system that will provide a temperature of an average of approximately 20˚ C.

The design shall consider a multiple split systems.

Regarding the ventilation system, the contractor shall design an appropriate system in order to extract the odors from the toilets. The ducts shall conduct the odors to the exterior of the building through the ceiling with PVC pipes.

The air conditioning units, ventilation system and duct works will not be purchased or installed by contractor.

C.1.11 Install Doors and Windows

The contractor shall provide and install the doors and windows according to the architectural drawing AD-05 and the respective specifications detailed in this document. A summary of doors and windows are detailed in drawing AD-06, in this drawing the designs are for a reference, if the Contractor has to provide other type of model it can be done by a simple COR authorization, but the materials and the main concept shall remain the same as it is established in the specifications. Before the Contractor manufactures these items, the Contractor will provide samples for the COR approval.

C.2 General Specifications

All work shall be carried out in strict compliance with all contract clauses and these technical specifications. In the event that the Contractor discovers discrepancies contained in the various design/technical documents, Contractor must immediately notify the Contracting Officer Representative (COR) before taking any other action.

C.2.1 QUANTITIES

This contract is based on a lump sum priced solicitation. Any quantities indicated in the specifications and drawings are for reference only and the Contractor is responsible for providing quantities needed to complete the work, without any price adjustment after award.

C.2.2 TRIALS AND TESTS

Materials, permanent equipment, its accessories and other elements destined to the work, shall be subject to trials and tests necessary to verify their compliance with specifications, properties and characteristics, in accordance with permitted requirements and tolerances, in line with the use for which they have been intended.

Materials, equipment, accessories or elements that have not been accepted by the COR, shall be withdrawn from the work site or replaced, at Contractor’s cost.

Laboratory tests can be carried out, according to the specific case, at the work site or in laboratories previously authorized by the COR. Materials that bear quality certificates issued by ISO or its equivalent, do not need to be routinely tested. Costs of laboratory trials and tests shall be for the account of Contractor. The COR shall be able to carry out special trials and tests at any time if it is needed to clarify the quality of any item.

C.2.3 WORK EXECUTION

The different items of the construction program shall be carried out in a gradual and progressive manner, without initiating work that could later be affected by other items that have not been concluded or that lack an adequate support or safety, taking care that work that has been finished is not affected by weather or other elements.

Contractor shall be responsible for maintaining quality of work by following proper operation procedures in construction.

Throughout the different stages of construction work, Contractor shall obtain approval from the COR, in order to continue with subsequent stages of construction. Before receiving approval to continue through various stages of work, samples of completed work shall be tested to verify the quality of the work.

SAQMMA-17-R-0011 Page 16 of 121

The Contractor shall provide a construction schedule in which all the works shall be detailed with the date of performance and delivery.

C.2.4 COST OF THE PROJECT

The Contractor should include all the costs of the materials, labor, transportation, and materials testing that will be needed to complete the project and comply with all the specifications stated in this document.

C.3 Task Specifications

C.3.1 PRELIMINARY WORK

C.3.1.1 LAYING OUT AND LEVELING

Prior to initiating construction, the Contractor and COR will define the outline of the components of the project in accordance with the project drawings and, if necessary, the construction levels to be achieved will be appointed.

Additionally, signals (B. M.) shall be placed on the main points to confirm location and levels of work. The signals shall be with paint at strategic points at the existing walls.

Before beginning the remodeling, the Contractor shall verify all data, as shown in the drawings, and correct them in case there are any divergences between the real dimensions of the building and the data of the drawings, in accordance with the COR.

The construction axes and levels shall be marked in the building in a safe manner. The marks should be the most precise, clear, safe and stable for the most important axes and elements.

To comply with these requirements, the Contractor shall provide an expert topographer, supported by precision equipment such as: total station, levels, measuring tape, etc. as required for the placement of milestones and layouts of the remodeling project.

C.3.1.2 WARNING SIGNALS:

The Contractor shall provide all the necessary signs and announcements to prevent accidents according to the safety plan, which shall have the approval of the COR. Signs shall be made of acrylic or galvanized sheets painted with a yellow background and with red or black letters.

C.3.1.3 TEMPORARY STRUCTURES: OFFICES, SANITARY FACILITIES & WAREHOUSES

Temporary structures will be implemented in the plot located in the rear of the building for the Contractor’s personnel, the COR, the Government Technical Advisor (GTA) as well as for the police students. It is the Contractor’s responsibility to implement offices, warehouses, provisional bathrooms and the guardhouses required for their own use. Also the contractor shall implement provisional bathrooms for the police in order to develop the enlargement of the existing bathrooms. For this reason the contractor shall provide the bathrooms for students that shall include 10 toilets, 10 washbasins and 10 showers. These bathrooms shall be used just for the students and shall not be used by the personnel of the Contractor. Structures must be safe and have appropriate sanitary and electrical facilities.

The Contractor will implement provisional offices, sanitary facilities for the personnel, and a guardhouse with a temporary connection to a potable water and sewage system prior to commencing construction. One sanitary facility shall be implemented for every 10 workers, and one for the technical staff, the COR and the GTA. The Contractor will provide a 9 square meters office for the exclusive use of the COR, the GTA or his authorized assistants. The Contractor will be responsible for cleaning and maintaining these structures.

The materials to be used for these provisional facilities can be of metal, concrete, or wood, as long as they are secure and provide a private area. The COR can demand changes or improvement of the provisional facilities at any time if he determines that the Contractor is not providing a clean area with sufficient privacy and safety.

SAQMMA-17-R-0011 Page 17 of 121

C.3.2 EARTHWORK, EXCAVATION AND BACKFILLING

The work described in this chapter includes excavation and backfilling, as well as carrying, piling up and removing excavation material necessary for the construction of the building, channels, piping, and all elements indicated in the project drawings.

C.3.2.1 LEVELING AND CLEARING OF LAND

This section refers to land modifications required for the execution of building construction in accordance with the project drawings.

To determine final levels, theodolites or precision instruments will be used. If there are considerable differences with the specifications in the drawings, the COR shall be notified and only through a report of mutual agreement will the new levels be determined.

The residual material must be removed and placed outside the construction site in places approved by the local authority.

C.3.2.2 SLOPE CONFIGURATION

Not applicable for this project.

C.3.2.3 EXCAVATION

Generally, excavation is understood as the removal of volumes of land or other materials for the purpose of forming spaces for construction, foundations, structures, buildings, roads, etc.

Excavation shall be done according to the heights, limits, elevations, gradients and sections set forth in the structural, architectural, and sanitary drawings, save for different or real conditions of the project.

During excavation, material satisfactory for backfilling shall be stockpiled in an orderly manner at a distance from banks of the trench equal to ½ the depth of the excavation, but in no instance closer than 60 cm. Excavated material not required or not satisfactory for backfill shall be removed from the site, without affecting the adjacent properties.

The material produced from excavation will be temporarily disposed of on the sides of excavations, so that it will not impede the execution of other work.

The final excavation to be performed in the places where specific concrete, exterior works are to be built shall be carried out as close to the pouring of concrete to avoid any alterations due to bad weather.

In no case shall excavation be performed to a depth so that the base soil is loosened or removed. If this happens, it will be considered as an “over excavation” that should be corrected by the contractor according to the project specifications.

If, in the Contractor’s or COR’s opinion, the bottom of the ditch is not strong or is unstable, over-excavation will be carried out until solid ground is reached, otherwise another solution shall be jointly agreed upon by the Contractor and the COR.

It is the Contractor’s duty to protect the stability of the adjacent properties while excavation is carried out. This should be done in such a way as to guarantee the stability of those buildings without causing any damage.

Excavation shall be protected against rain, landslides and other excavation. The Contractor shall protect the personnel executing the excavation in ditches and, if for safety reasons it is deemed necessary, the contractor shall provide timbering and shoring.

This shoring shall be reviewed and approved by the COR, and the Contractor will protect the shoring and will be removed after the excavation has been performed.

SAQMMA-17-R-0011 Page 18 of 121

The standards for the provisional shoring in excavations are the following:

When assemblages and props are used, these are placed at intervals no greater than 2.50 meters, measuring the timber lengthwise, and should penetrate the land enough to withstand the push of the walls in the excavation.

Metallic cribbing shall be used for excavations greater than 5.00 meters deep or when the lateral push on the excavation walls is great.

Whenever the conditions of the land demand so or when the structural drawings states, the excavation walls will be protected with stakes or projected concrete. This will be subsequently refilled according to the requirements established for the filling process.

For piping placement in excavation, the filling will be laid as a first step to cover a height of at least 20 centimeters above the highest part of piping and shall be compressed in accordance with the article of this section. Excavation will be done from the ditch in accordance with the gradient slope and required transversal lines for placement of piping as indicated on working drawings.

C.3.2.4 OVER EXCAVATION

The term over-excavation, for the purposes of the job to be carried out, is understood as excavation outside the lines and levels set forth in the drawings, the specifications and/or the COR’s instructions.

If over-excavation is done, removal should go up to the required level and filling with soil, granular material or concrete or any other material approved by the COR; compressing will be done with adequate water content, in layers that will not exceed a thickness of 15 cm, using an appropriate mechanical compressor. The compression process shall be done according to the regulations established by the standards of the American Association of State Highway and Transportation Officials (AASHTO T-130).The material to be used shall be granular selected material according AASHTO 145.

The Contractor agrees not to receive any additional payment for over-excavation that may result from the conditions of the land, the action of natural agents, operations that are executed to facilitate the construction, and mistakes made by the Contractor.

C.3.2.5 EXCAVATION IN CONGLOMERATE STRATUMS AND ROCK

The process of excavation when hard materials are found which cannot be loosened through ordinary methods is understood as conglomerate and rock excavation where the use of shovels, pickaxes, backhoes, or excavators is not sufficient and explosives, mechanical hammers, wedges, or sledge hammers or other similar are absolutely necessary.

If a rock is found in pieces, only fragments greater than 200 cubic decimeters will be considered a rock.

When removing rock or masonry fragments from a ditch is necessary, and if they form clusters that do not have to be totally extracted in order to erect structures, those pieces excavated within the presumed boundaries will be considered as rock, although their volume could be smaller than the one indicated in the above paragraph.

If the bottom of the trench (made to install pipes lines) is made up of conglomerate or rock, excavation will be carried out up to 0.15 m below the seat of the pipe and it will be filled later with sand and fine gravel.

When excavation is carried out on fixed rocks, the use of explosives will be allowed, provided that they do not alter the land adjacent to the excavation works and with a prior written authorization from the COR.

C.3.2.6 EXCAVATION WITH WATER PRESENCE

The excavation with presence of water may be caused by water coming from the underground, rainwater, floods, operation of the construction, sewage and others.

SAQMMA-17-R-0011 Page 19 of 121

Excavation cannot be executed in the presence of water, whatever its origin, and therefore due precautions and protections must be taken, as construction techniques advise in these cases. Excavating during the rainy season shall be prohibited.

When placing stone masonries, concrete structures, or any structure, the Contractor will insure that water is not present in excavations, and that it will remain so until mortar and concrete have set.

The presence of water makes work more difficult and the safety of the people and the projects themselves decreases. Therefore, the Contractor is required to take due precautions to eliminate water in excavation sites by using stake boards, cofferdams, pumping, drainage, curbs, etc.

Excavation is forbidden during the rainy season. None of the excavations should have water present before placing the pipes, and under no circumstance will they be placed under water. The trenches shall remain dry until the pipes have been totally coupled and the welded junctions are completely dry.

C.3.2.7 EXCAVATION FOR FOUNDATIONS

This section refers to the depth of the excavation needed for foundations that will be lower than that marked for cleaning and leveling, down to the depth established by the structural drawings or by recommendation of COR.

Excavation will be done in a fashion to satisfactorily build the structures. The excavation sides will be totally vertical and the bottom will be clean, free of waste, and correctly leveled.

In no case will machine excavation be performed to a depth so that the soil of the bottom is loosened or removed. The final material to be excavated must be removed by pickax and shovel to a depth of 50 centimeters, also known as “conforming the plinth or ditch bottom”.

If landslides or collapses due to the depth of excavations or inconsistency of soil happen, shoring shall be built to prevent further damages or accidents.

Ditches shall remain clean and no work will be executed in them if waste, loose dirt, water, etc. are found.

After casting the foundation and pouring the foundation, the gap caused by excavation shall be filled and compressed with the extracted soil until reaching the initial level. This work shall meet the specifications detailed for “compacted backfilling with natural soil”. Leftover material shall be removed or placed as filling if acceptable by COR.

The Contractor shall take all necessary precautions to prevent water from entering excavation sites awaiting concrete pours. However, if soil deterioration is caused by unforeseen circumstances, the Contractor will perform necessary studies and analyses of the soil to deepen excavation.

C.3.2.8 REMOVAL OF WASTE AND/OR EXCAVATED MATERIAL

Waste removal is defined as the method of transportation of the materials produced by excavation, which should have a specifically determined place for disposal approved by the local authority.

When there is an excess material, the Contractor shall remove it and place it outside the area of construction where such material will not obstruct watercourses or cause detriment to the neighboring areas.

Excess or waste material should not be located in properties adjacent to the construction site unless the Contractor receives written authorization from the owners of such properties.

The material produced by excavation that will not be used for the construction of the project shall be removed from the site using heavy mechanical equipment in good condition, without causing vehicle transit interruption or neighbors’ annoyance.

C.3.2. 9 BACKFILLING

Backfilling is defined at the sections indicated by the project, the existing gaps between structures and excavations, or between the structures and the natural soil in such a way that any point of the finished section will remain at a distance greater than 10 centimeters from the corresponding section of the project.

SAQMMA-17-R-0011 Page 20 of 121

The backfilling process will be carried out using earth, gravel, sand or rock with approval from the COR.

Prior to backfilling, the land shall be free of debris, trunks, branches, etc., and in general of all organic material and all the material that is not appropriate for backfilling. The COR will approve the material that will be used for backfilling in advance and the material will come from the excavation itself or other extraction sites.

The backfilling will be done according to the project specifications and according to the lines, levels and gradients described in the architectonic and structural drawings.

The Contractor is required to obtain, transport and maintain the necessary material for backfilling, either from the excavation site or from qualified quarries.

Special care will be given by not using the mechanical compactor in areas close to buildings or existing construction inside or outside of the property. If any damage occurs, this shall be repaired and costs assumed by the Contractor.

The refill and/or cover of any excavation that contains lines or pipes installations and other services will not proceed until they have been placed and tested as well as approved and accepted by the COR.

The backfilling for subflooring will be placed and mechanically compacted in beds of 0.20m thick according to the D698-64Tspecifications of the American Society for testing and Materials (ASTM).

Backfilling with gravel, sand or ground stone for formation of drains or filters shall be consistent with the grain grading specified in the working drawings; materials will be sieved and washed if required. For filter formation, the materials will be placed in such a way that the higher grade particles remain in contact with the structure and the ones with lesser diameters in contact with the natural terrain, unless otherwise indicated.

The backfilling of rock placement shall be made with fragments of healthy, dense, and exposure-resistant rocks, with angle formation satisfactory to COR. The minimal size of the stones shall be 20 centimeters, and the maximum determined by the project, always protecting the structure.

C.3.2.9.1 COMPACTED BACKFILLING WITH NATURAL SOIL

Compacted backfilling with natural soil is defined as placing horizontal layers of the existing soil, with a thickness of 20 cm, with the humidity that the material requires to get a mechanical compression to 95% minimum of the density of the Proctor Standard measure. Each layer shall be evenly compacted on the entire surface by pneumatic rammers or other construction equipment until obtaining the maximum compression possible with the use of these tools. The material to be used in this backfilling shall be free of organic residues and waste. Prior to backfilling, the land shall be free of debris. The COR will approve in advance the material that will be used in the backfilling process. The compression process shall be done according to the standards of the American Association of State Highway and Transportation Officials (AASHTO T-130).

If the approved material for this backfilling is not enough to reach the levels specified in the project design, the Contractor shall complete the volume needed, with granular material according to the specification for “Compacted backfilling with granular material.”

The Contractor shall carry out laboratory tests to guarantee the compliance with the aforementioned specifications and the cost of these tests will be assumed by the Contractor.

C.3.2.9.2 COMPACTED BACKFILLING WITH GRANULAR MATERIAL

Compacted backfilling with granular material is defined as placing horizontal layers of sub-base to a thickness of 20 cm. Each layer will be compacted evenly on its entire surface by pneumatic rammers or heavy construction equipment until obtaining the maximum compression possible with the use of these tools.

Compaction shall be carried out using sheepsfoot rollers, pneumatic-tried rollers,…