This solicitation is for a construction project to widen Circle Drive at Building 9 at the Veterans Affairs Medical Center in Lyons, New Jersey. The project involves widening the eastern side of West Circle Drive to provide 17 new parking spaces and sidewalk. Bids are due by June 15, 2021. The construction work must be completed within 120 calendar days of award. The awarded contractor will be responsible for all labor, materials, equipment, and other requirements to complete the project in accordance with the drawings and specifications. The Department of Veterans Affairs Veterans Health Administration is listed as the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24221B0029 0001.docx | DOCX document | |
| S02 - Final Plans.pdf | ||
| 36C24221B0029_2.docx | DOCX document | |
| P07 - Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract # 36C24220C0156
Project # 561A4-20-102
Date: March 5, 2021
Status: Final Bid Documents
Prepared For:
Lyons NJ VA Medical Center
151 Knollcroft Rd
Lyons, NJ 07939
Prepared By:
Acela Architects + Engineers, PC
2633 Moravian Avenue
Allentown, PA 18103
(610) 365-4023
SPECIFICATIONS
FOR: Widen Circle Drive 1
LOCATION: Veterans Health Administration New Jersey
Health Care System, Lyons NJ
NJ Healthcare System, Lyons NJ Contract #36C24220C0 156 Widen Circle Drive 1 Project #561A4-20-102
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 03-20 01 32 16.15 Project Schedules (Small Projects – Des ign/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16 02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
Not Used
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
Not Used
DIVISION 09 – FINISHES
00 01 10-2
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10-15
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
Not Used
DIVISION 13 - SPECIAL CONSTRUCTION
Not Used
DIVISION 14– CONVEYING EQUIPEMENT
Not Used
DIVISION 21- FIRE SUPPRESSION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
DIVISION 25 – INTEGRATED AUTOMATION
Not Used
DIVISION 26 – ELECTRICAL
Not Used
DIVISION 27 – COMMUNICATIONS
Not Used
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
Not Used
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16 31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improveme nts 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16 32 90 00 Planting 08-16
00 01 10-3
DIVISION 33 – UTILITIES
33 40 00 Storm Sewer Utilities 12-17
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
DIVISION 48 – Electrical Power Generation
NJ Healthcare System, Lyons NJ Contract #36C24220C0156
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
SITE PLANNING
GI001 Title Sheet
GI002 General Notes Sheet
CS101 Existing Features & Demolition Plan
CS102 Site Development Plan
CS103 Grading & Spotgrade Plan
CS104 Erosion & Sediment Pollution Control Plan
CS105 Construction Details
CS106 Construction Details
- - - END - - -
i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 RESIDENT ENGINEER'S FIELD OFFICE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY USE OF NEW ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.23 NEW TELEPHONE EQUIPMENT
1.24 TESTS
1.25 INSTRUCTIONS
ii
1.26 GOVERNMENT-FURNISHED PROPERTY
1.27 RELOCATED // EQUIPMENT // ITEMS //
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.29 CONSTRUCTION SIGN
1.30 SAFETY SIGN
1.31 PHOTOGRAPHIC DOCUMENTATION
1.32 FINAL ELEVATION Digital Images
1.33 HISTORIC PRESERVATION
1.34 VA TRIRIGA CPMS
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for bui lding operations, including demolition and removal of existing struct ures, and furnish labor and materials and perform work for the wideni ng of West Circle
Drive as required by drawings and specifications.
B. Visits to the site by Bidders may be made only b y appointment with the
Medical Center Engineering Officer.
C. Offices of Acela Architects + Engineers, PC., as Architect-Engineers, will render certain technical services during const ruction. Such services shall be considered as advisory to the Gov ernment and shall not be construed as expressing or implying a contra ctual act of the
Government without affirmations by Contracting Offi cer or his duly authorized representative.
D. Before placement and installation of work subjec t to tests by testing laboratory retained by Department of Veterans Affai rs, the Contractor shall notify the Contracting Officers Representativ e (COR) in sufficient time to enable testing laboratory person nel to be present at the site in time for proper taking and testing of s pecimens and field inspection. Such prior notice shall be not less tha n three work days unless otherwise designated by the Contracting Offi cers Representative
COR.
E. All employees of general contractor and subcontr actors shall comply with VA security management program and obtain perm ission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. BASE BID: GENERAL CONSTRUCTION: Contractor shall provide all tools, resources, materials, temporary fencing, signage, p ermits, supervision, 01 00 00 -2 etc. to widen the eastern side of West Circle Drive in front of
Building 9 to provide 17 new parking spaces and sid ewalk as indicated on the drawings and specifications along with all o ther work indicated on the drawings and specifications.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and admi nistrative security procedures that will remain effective for the entir e duration of the project.
2. The General Contractor is responsible for assuri ng that all sub-contractors working on the project and their employ ees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter t he project site without appropriate badge. They may also be subjec t to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shal l give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is sepa rate from any notices required for utility shutdown described lat er in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the pr emises in the event of a national emergency. The General Contrac tor may return to the site only with the written approval of the Cont racting Officer.
01 00 00 -3
C. Key Control:
1. The General Contractor shall provide duplicate k eys and lock combinations to the Contracting officers representa tive (COR) for the purpose of security inspections of every area o f project including tool boxes and parked machines and take a ny emergency action.
D. Document Control:
1. Before starting any work, the General Contractor /Sub Contractors shall submit an electronic security memorandum desc ribing the approach to following goals and maintaining confide ntiality of
“sensitive information”.
2. The General Contractor is responsible for safeke eping of all drawings, project manual and other project informat ion. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photograp hs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Re turn the information to the Contracting Officer upon request .
4. These security documents shall not be removed or transmitted from the project site without the written approval of Co ntracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Off icer immediately when there is a loss or compromise of “sensitive in formation”.
7. All electronic information shall be stored in sp ecified location following VA standards and procedures using an Engi neering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and track ed through the
EDMS system.
01 00 00 -4
b. “Sensitive information” including drawings and o ther documents may be attached to e-mail provided all VA encryptio n procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitt ed 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be is sued for General
Contractor and its employees for parking in designa ted areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (inc luding storage of materials) on Government premises to areas authoriz ed or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harml ess from liability of any nature occasioned by the Contractor's perfor mance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the appr oval of the
Contracting Officer and shall be built with labor a nd materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor a t its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandon ed and need not be removed.
C. The Contractor shall, under regulations prescrib ed by the Contracting
Officer, use only established roadways, or use temp orary roadways constructed by the Contractor when and as authorize d by the Contracting
Officer. When materials are transported in prosecut ing the work, vehicles shall not be loaded beyond the loading cap acity recommended by the manufacturer of the vehicle or prescribed by an y Federal, State, or local law or regulation. When it is necessary to cr oss curbs or sidewalks, the Contractor shall protect them from d amage. The
Contractor shall repair or pay for the repair of an y damaged curbs, sidewalks, or roads.
01 00 00 -5
(FAR 52.236-10)
D. Working space and space available for storing ma terials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center a pplicable to their conduct.
F. Execute work in such a manner as to interfere a s little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as pos sible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any e xisting equipment, and with work being done by others. Use of equipmen t and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during co nstruction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other th an assigned areas.
2. Provide unobstructed access to Medical Center ar eas required to remain in operation.
H. Utilities Services: Where necessary to cut exis ting pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone ), they shall be cut and capped at suitable places where shown; or, in a bsence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses i n operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim lif e safety measure to
01 00 00 -6 be used during the work, and a schedule defining th e duration of the work with milestone subtasks. The work to be outli ned shall include, but not be limited to:
To ensure such executions, Contractor shall furnis h the COR with a schedule of approximate dates on which the Contract or intends to accomplish work in each specific area of site, buil ding or portion thereof. In addition, Contractor shall notify the C OR two weeks in advance of the proposed date of starting work in ea ch specific area of site, building or portion thereof. Arrange such dat es to ensure accomplishment of this work in successive phases mu tually agreeable to the Medical Center Director, COR, and Contractor, a s follows:
Phase I: Widening of West Circle Drive, including p aving, curbing, and sidewalks, as shown on the construction drawings an d specifications.
All work shall be completed in one phase.
H. Building No. 9 will be occupied during perform ance of work.
1. Contractor shall take all measures and provide a ll material necessary for protecting existing equipment and pro perty in affected areas of construction against dust and debris, so t hat equipment and affected areas to be used in the Medical Centers op erations will not be hindered. Contractor shall permit access to Depa rtment of
Veterans Affairs personnel and patients through oth er construction areas which serve as routes of access to such affec ted areas and equipment. These routes whether access or egress s hall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and st aff access.
Coordinate alteration work in areas occupied by Dep artment of
Veterans Affairs so that Medical Center operations will continue during the construction period.
I. Construction Fence: Before construction operat ions begin, Contractor shall provide a chain link construction fence, 2.4m (eight feet) minimum height, around the construction area indica ted on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails wi th tie wires spaced
01 00 00 -7 at maximum 375mm (15 inches). Bottom of fences shal l extend to 25mm
(one inch) above grade. Remove the fence when direc ted by the COR.
J. When a construction site is turned over to Contr actor, Contractor shall accept entire responsibility including upkeep and m aintenance.
K. Utilities Services: Maintain existing utility se rvices for the Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uni nterrupted services.
Where necessary to cut existing water, steam, gases , sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (incl uding telephone), they shall be cut and capped at suitable places whe re shown; or, in absence of such indication, where directed by the C OR.
1. No utility service such as water, gas, steam, se wers or electricity, or fire protection systems and communications syste ms may be interrupted without prior approval of the COR. Elec trical work shall be accomplished with all affected circuits or equip ment de-energized. When an electrical outage cannot be acco mplished, work on any energized circuits or equipment shall not comme nce without a detailed work plan, the Medical Center Director’s p rior knowledge and written approval.
2. Contractor shall submit a request to interrupt a ny such services to the COR, in writing, 7 days in advance of proposed interruption.
Request shall state reason, date, exact time of, an d approximate duration of such interruption.
3. Contractor will be advised (in writing) of appro val of request, or of which other date and/or time such interruption w ill cause least inconvenience to operations of the Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be reques ted, in writing, at least 15 calendar days prior to the desired time an d shall be performed as directed by the COR.
01 00 00 -8
5. In case of a contract construction emergency, se rvice will be interrupted on approval of the COR. Such approval w ill be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the c onstruction project, for such items as water, sewer, electricit y, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires , cables, conduits, ducts, pipes and the like, and their hangers or sup ports, which are to be abandoned but are not required to be entirely re moved, shall be sealed, capped or plugged at the main, branch or pa nel they originate from. The lines shall not be capped in finished are as, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or par titions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activit ies with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to p arking and to occupied areas of buildings clear of construction m aterials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, alter ing and removal of existing roads, walks and entrances must be approve d by the COR.
N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes th e scheduling of traffic and the use of roadways, as specified in Ar ticle, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contract or shall make a thorough survey with the COR in which alterations o ccur and areas which are anticipated routes of access, and furnish a rep ort, signed by both, to the Contracting Officer. This report shall note any discrepancies between drawings and existing conditions at site.
01 00 00 -9
B. Any items required by drawings to be either reus ed or relocated or both, found during this survey to be nonexistent, o r in opinion of the
COR, to be in such condition that their use is impo ssible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed b y reason of this subparagraph B, the contract will be modified accor dingly, under provisions of clause entitled "DIFFERING SITE CONDI TIONS" (FAR 52.236-
2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial o r final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furn ish a report on conditions of surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caus ed by Contractor to such surfaces, despite protection measures; and, wi ll form basis for determining extent of repair work required of Contr actor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective mea sures:
1. Wherever a full height curb crossing is require d, adequate shoring is to be provided to ensure the curb is not require d to support the full weight of the crossing vehicle.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, ma terials handled, and equipment moved and/or relocated.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work remov ed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of t he Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be rem oved or dislodged
01 00 00 -10 from present locations in such a manner as to preve nt damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.
3.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all st ructures, equipment, and vegetation (such as trees, shrubs, and grass) o n or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contrac t. The Contractor shall only remove trees when specifically authorize d to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract per formance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and p aint the cut with a tree-pruning compound as directed by the Contractin g Officer.
B. The Contractor shall protect from damage all exi sting improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any dam age to those facilities, including those that are the property o f a third party, resulting from failure to comply with the requireme nts of this contract or failure to exercise reasonable care in performin g the work. If the
Contractor fails or refuses to repair the damage pr omptly, the
Contracting Officer may have the necessary work per formed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENT AL CONTROLS, for additional requirements on protecting vegetation, s oils and the environment. Refer to Articles, "Alterations", "Res toration", and
"Operations and Storage Areas" for additional instr uctions concerning repair of damage to structures and site improvement s.
01 00 00 -11
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair ex isting work as necessary to install new work. Except as otherwise shown or specified, do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be al tered or extended and that is found to be defective in any way, shall be reported to the
COR before it is disturbed. Materials and workmansh ip used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specifie d.
B. Upon completion of contract, deliver work comple te and undamaged.
Existing work (lawns, paving, roads, walks, etc.) d isturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, a nd refinished and left in as good condition as existed before commenc ing work.
C. At Contractor's own expense, Contractor shall im mediately restore to service and repair any damage caused by Contractor' s workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications sy stems (including telephone) which are not scheduled for discontinuan ce or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered b y adjustment to contract time and price in accordance with clause e ntitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to be low is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(FAR 52.236-4)
B. Subsurface conditions have been developed by Qua lity Level B scanning, which is defined by the Standard as providing the “ approximate horizontal position of subsurface utilities”. Scann ing was completed with electromagnetic (EM), magnetic, radio frequenc y (FR), and ground penetrating radar (GPR)scans. Approximate locations of existing utilities identified during the subsurface explorat ion are shown
01 00 00 -12 diagrammatically on the drawings. Quality level A s ervices (test holes via vacuum excavation) to determine the precise hor izontal and vertical location of underground utilities where not conduct ion. Contractors and users of these plans and specifications shall be re sponsible for verification and location of utilities prior to con struction work.
Acela Architects + Engineers, PC. and the governmen t assume no liability for damage to any existing utility during construction. The contractor shall be responsible to repair any damag e that may occur during construction.
C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical
Center, 151 Knollcroft Road, Lyons, NJ 07939 and sh all be considered part of the contract documents.
D. Government does not guarantee that other materia ls will not be encountered nor that proportions, conditions or cha racter of several materials will not vary from those indicated by exp lorations. Bidders are expected to examine site of work; and, after in vestigation, decide for themselves character of materials and make thei r bids accordingly.
Upon proper application to Department of Veterans A ffairs, bidders will be permitted to make subsurface explorations of the ir own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registe red civil engineer whose services are retained and paid for by the Con tractor shall perform services specified herein and in other spec ification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contrac tor, and that the land surveyor or civil engineer has no financial in terest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Gover nment established base lines and bench marks, indicated on the drawings, a nd shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expen se, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor sha ll be responsible for executing the work to the lines and grades that may be established
01 00 00 -13 or indicated by the Contracting Officer. The Contra ctor shall also be responsible for maintaining and preserving all stak es and other marks established by the Contracting Officer until author ized to remove them.
If such marks are destroyed by the Contractor or th rough Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the repl acement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark lines and grades that are reasonably necessary to properly assure that location, orienta tion, and elevations established for roads, parking lots, and sidewalks are in accordance with lines and elevations shown on contract drawing s.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficien t additional survey control points or system of points as may be necess ary to assure proper alignment, orientation, and grade of all major feat ures of work. Survey shall include, but not be limited to, location of l ines and grades of roads, parking lots, and sidewalks:
1. Such additional survey control points or system of points thus established shall be checked and certified by a reg istered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as roads, parking lot s, or sidewalks) is placed.
D. During progress of work, and particularly as wor k progresses, Contractor shall have line grades of all major form work checked and certified by a registered land surveyor or register ed civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, the Contractor shall furnish to the COR/ certificates from a registered land surveyor or registered civil engine er that the following work is complete in every respect as requ ired by contract drawings.
1. Lines and elevations of roads, parking lots, sid ewalks.
01 00 00 -14
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a re producible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to the COR.
F. The Contractor shall perform the surveying and l ayout work of this and other articles and specifications in accordance wit h the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of t he project, to include all contract changes, modifications and cla rifications.
B. All variations shall be shown in the same genera l detail as used in the contract drawings. To ensure compliance, as-built d rawings shall be made available for the COR review, as often as requ ested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all sho p drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty man agement plan which contains information relevant to FAR 52.246-21 Warr anty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include wi thin the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is e ntitled. The plan must be in narrative form and contain sufficient de tail to render it suitable for use by future maintenance and repair p ersonnel, whether tradesman, or of engineering background, not necess arily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was app roved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval p rior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction
01 00 00 -15 warranty period will begin on the date of the proje ct acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured fro m time of acceptance, by the Contactor and the Contracting Of ficer. Include in the warranty management plan, but not limited to, t he following:
1. Roles and responsibilities of all personnel associa ted with the warranty process, including points of contact and t elephone numbers within the company of the Contractor, subcontractor s, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and te lephone number of each of the guarantor’s representatives nearest pro ject location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC bal ancing, pumps, motors, transformers and for all commissioned syste ms such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature o f construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and supplie rs.
e. Name and phone numbers of manufacturers or supplier s.
f. Names, addresses and phone numbers of sources of sp are parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting da te of warranty of construction. Items which have extended warranti es must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to conti nue the warranty in force.
01 00 00 -16
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons t o call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment co vered by extended warranties.
7. Copies of instructions to be posted near selected p ieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must rema in effective throughout the construction period.
1. In the event the Contractor fails to commence and d iligently pursue any construction warranty work required, the Contra cting Officer will have the work performed by others, and after c ompletion of the work, will charge the remaining construction warran ty funds of expenses incurred by the Government while performin g the work, including, but not limited to administrative expens es.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Governm ent at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instr uctions. Failure to respond will be cause for the Contracting Office r to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract compl etion, and at a time designated by the Contracting Officer, the Contract or shall meet with the Contracting Officer to develop a mutual underst anding with respect
01 00 00 -17 to the requirements of this section. Communication procedures for
Contractor notification of construction warranty de fects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed neces sary by the
Contracting Officer for the execution of the constr uction warranty will be established/ reviewed at this meeting. In connec tion with these requirements and at the time of the Contractor’s qu ality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorize d to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the l ocal service area of the warranted construction, be continuously availab le and be responsive to Government inquiry on warranty work action and s tatus. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty S ervice Requirements:
Following oral or written notification by the Contr acting Officer, the
Contractor shall respond to construction warranty s ervice requirements in accordance with the “Construction Warranty Servi ce Priority List” and the three categories of priorities listed below . Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was co mpleted. If the
Contractor does not perform the construction warran ty within the timeframe specified, the Government will perform th e work and back charge the construction warranty payment item estab lished.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to comple tion or relief.
2. Second Priority Code 2. Perform onsite inspection t o evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to compl etion or relief.
3. Third Priority Code 3. All other work to be initiat ed within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” i s as follows:
01 00 00 -18
Code 1-Asphalt
a. Pavement failures.
Code 3
a. All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approve d by the Contracting
Officer. Attach each tag with a copper wire and spr ay with a silicone waterproof coating. Also submit two record copies o f the warranty tags showing the layout and design. The date of acceptan ce and the QC signature must remain blank until the project is ac cepted for beneficial occupancy. Show the following informatio n on the tag.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads a nd roads on Medical
Center property and, when authorized by the COR, su ch temporary roads which are necessary in the performance of contract work. Temporary
01 00 00 -19 roads shall be constructed and restoration performe d by the Contractor at Contractor's expense. When necessary to cross cu rbing, sidewalks, or similar construction, they must be protected by wel l-constructed bridges.
B. When new permanent roads are to be a part of thi s contract, Contractor may construct them immediately for use to facilitat e building operations. These roads may be used by all who have business thereon within zone of building operations.
1.17 RESIDENT ENGINEER'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical e quipment to provide heat, ventilation, plumbing, light and power will b e permitted subject to written approval and compliance with the followi ng provisions:
1. Permission to use each unit or system must be gi ven by the COR in writing. If the equipment is not installed and main tained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipme nt.
2. Electrical installations used by the equipment s hall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. tran sformers, relays, circuit breakers, fuses, conductors, motor controll ers and their overload elements shall be properly sized, coordina ted and adjusted.
Installation of temporary electrical equipment or d evices shall be in accordance with NFPA 70, National Electrical Cod e, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be corr ect and it shall be determined that motors are not overloaded. The e lectrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuu m cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, an d aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for prehea t coils shall function properly and all safety controls shall fun ction to prevent coil freeze-up damage.
01 00 00 -20
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elemen ts shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distributi on system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or part s used which show wear and tear beyond normal, shall be replaced with iden tical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear du e to prolonged use will be repaired replaced by the contractor at the contr actor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS (NOT USED)
1.20 TEMPORARY USE OF NEW ELEVATORS (NOT USED)
1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contract or's workers) ample temporary sanitary toilet accommodations with suita ble sewer and water connections; or, when approved by the COR, provide suitable dry closets where directed. Keep such places clean and free fro m flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfec tly clean.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably require d amounts of utilities available to the Contractor from existing outlets a nd supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevail ing rates charged to the Government. The Contractor shall carefully cons erve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Con tracting Officer, 01 00 00 -21 shall install and maintain all necessary temporary connections and distribution lines, and all meters required to meas ure the amount of electricity used for the purpose of determining cha rges. Before final acceptance of the work by the Government, the Contr actor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the inf rastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to preven t injury to work and materials through dampness and cold. Use of open sa lamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Mainta in minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heat ing distribution system.
E. Electricity (for Construction and Testing): Furn ish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisti ng devices, electrical welding devices and any electrical heati ng devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish te mporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no co st to the
Contractor.
2. Maintain connections, pipe, fittings and fixture s and conserve water-use so none is wasted. Failure to stop leakag e or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
01 00 00 -22
G. Fuel: Natural and LP gas and burner fuel oil req uired for boiler cleaning, normal initial boiler-burner setup and ad justing, and for performing the specified boiler tests will be furni shed by the
Government. Fuel required for prolonged boiler-burn er setup, adjustments, or modifications due to improper desig n or operation of boiler, burner, or control devices shall be furnish ed and paid by the
Contractor at Contractor's expense.
1.23 NEW TELEPHONE EQUIPMENT (NOT USED)
1.24 TESTS (NOT USED)
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operati ng manuals (hard copies and electronic) and verbal instructions when requir ed by the various sections of the specifications and as hereinafter s pecified.
B. Manuals: Maintenance and operating manuals and o ne compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidenta l with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipme nt. They shall include complete information necessary for starting , adjusting, maintaining in continuous operation for long period s of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrati ons. Illustrations shall include "exploded" views showing and identify ing each separate item. Emphasis shall be placed on the use of specia l tools and instruments. The function of each piece of equipmen t, component, accessory and control shall be clearly and thorough ly explained. All necessary precautions for the operation of the equi pment and the reason for each precaution shall be clearly set forth. Man uals must reference the exact model, style and size of the piece of equ ipment and system being furnished. Manuals referencing equipment simi lar to but of a different model, style, and size than that furnishe d will not be accepted.
C. Instructions: Contractor shall provide qualified , factory-trained manufacturers' representatives to give detailed tra ining to assigned
Department of Veterans Affairs personnel in the ope ration and complete
01 00 00 -23 maintenance for each piece of equipment. All such t raining will be at the job site. These requirements are more specifica lly detailed in the various technical sections. Instructions for differ ent items of equipment that are component parts of a complete sy stem, shall be given in an integrated, progressive manner. All instructo rs for every piece of component equipment in a system shall be availab le until instructions for all items included in the system h ave been completed.
This is to assure proper instruction in the operati on of inter-related systems. All instruction periods shall be at such t imes as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough covera ge. The contractor shall submit a course outline with associated mater ial to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the co ntractual requirements. The Department of Veterans Affairs r eserves the right to request the removal of, and substitution for, any i nstructor who, in the opinion of the COR, does not demonstrate suffic ient qualifications in accordance with requirements for instructors abo ve.
1.26 GOVERNMENT-FURNISHED PROPERTY (NOT USED)
1.27 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necess ary, remove and reinstall in new location, all existing equipment a nd items indicated on the drawings or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as ste am, condensate return, water, drain, gas, air, vacuum and/or electrical, a t the main whenever such lines are disconnected from equipment to be re located. Remove abandoned lines in finished areas and cap as specif ied herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service co nnections, fittings, fastenings and any other materials necessary for as sembly and installation of relocated equipment; and leave such equipment in proper operating condition.
01 00 00 -24
E. All service lines such as noted above for reloca ted equipment shall be in…