This solicitation package seeks design-build services for a project to replace fire pump controllers at the Lebanon VA Medical Center in Lebanon, Pennsylvania. The selected prime contractor will partner with an architecture/engineering firm to complete designs and construction for replacing the fire pump controllers. The project scope includes all labor, materials, tools and equipment, and design-build services to design and construct the replacement in accordance with VA guidelines, EPA requirements, and VA specifications. The design-build team must provide completed designs and perform construction of the finished work. The two-phase solicitation will evaluate Phase I offers to select firms for the Phase II request for proposal. Phase II will be conducted according to FAR Parts 36.3 and 15 and evaluated based on the stated evaluation factors. The total anticipated project cost is between $250,000 and $500,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S02 Records Management Language for Contracts.docx | DOCX document | |
| S02 EXHIBIT A - Project Example.docx | DOCX document | |
| 36C24421R0099_2.docx | DOCX document | |
| P01 SOW - Replace Fire Pump Controllers.doc | DOC document | |
| S02 Solicitation 36C24421R0099 8-05-21.docx | DOCX document | |
| S02 Wage Determination 7-23-21.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT B - CALCULATION OF SELF-PERFORMED WORK
EXHIBIT B - CALCULATION OF SELF-PERFORMED WORK
SUBMITTED IN RESPONSE TO Request For Proposal 36C24420R0099
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.
Explain in detail how you will perform the minimum percentage required (15% GC) with your own resources. Note: An offeror who has the capability to perform both as a General contractor and self-perform a major element of construction, for example, pre-fabricated concrete, may be afforded additional consideration in the evaluation. You should address your general self-performance capability.
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
Clearly describe the work to be self-performed:
Show Calculation of Self-Performed work:
B.1 Total Offer Price: $
B.2 If applying for consideration as a General Contractor subtract Specialty Trades (Unless being self performed)
B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc. ($)
B.4 Remainder is “Total amount of work to be performed under the Contract” = $
B.5 “Work to be self-performed”: = $ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
B.6 15 % Self-performed Work = Line B.5 / B.4 X 100% = %