This combined synopsis/solicitation seeks quotations for fire alarm, fire suppression, and fire sprinkler system testing, maintenance, and repairs at four Department of Veterans Affairs locations in Connecticut. Required services include portable fire extinguisher inspections, kitchen wet suppression system inspections, central station monitoring, fire pump churn testing, fire and smoke damper inspections, and fire barrier inspections. Quotes are due by January 31, 2022 and the contract will be a firm-fixed price award set aside for Service-Disabled Veteran Owned Small Businesses. The solicitation includes a performance work statement, price schedule, and templates for past performance references and quality control plans.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24122Q0187 0003.docx | DOCX document | |
| VACTHS-Suppression Inventory.pdf | ||
| VACTHS-Fire Alarm Inventories.pdf | ||
| 2022 IMT Contract RFI Questions with answers.docx | DOCX document | |
| 36C24122Q0187 0002.docx | DOCX document | |
| VACTHS-Sprinkler Inventory.pdf | ||
| 36C24122Q0187 0001.docx | DOCX document | |
| S02_Attachment 4_QASP_.docx | DOCX document | |
| P09_PWS_(Rev-5).docx | DOCX document | |
| P07_Wage Determination_15-4119(Rev-18)_Newington.pdf | ||
| P07_Wage Determination_15-4127(Rev-19)_West Haven_Orange.pdf | ||
| S02_Attachment 3_Past Performance Worksheet.xlsx | XLSX spreadsheet | |
| S02_Price Schedule_Attachment 2_Line Items_.xlsx | XLSX spreadsheet | |
| 36C24122Q0187.docx | DOCX document | |
| S02_Attachment 5_Limitation on Subcontracting.doc | DOC document |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SimplexGrinnell Testing and Inspection Schedule Matrix - VA - Newington CT | |||||||||||||
| Revised August 12, 2021 | |||||||||||||
| Standard | Devices | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | June | July | Aug | Sept |
| Sprinkler Systems | |||||||||||||
| EP1 | Supervisory Signal Devices | Q | Q | Q | Q | ||||||||
| EP2 | Valves tampers, Flows & PIV's (PIV's exercised annually) | SA | SA | ||||||||||
| EP9 | Main Drain | SA | SA | ||||||||||
| EP10 | Fire Department Equipment Connections | Q | Q | Q | Q | ||||||||
| EP10 | Fire Hydrants | A | |||||||||||
| EP11 | Fire Pump Flow Test | A | |||||||||||
| NFPA25 | Dry Sprinkler Systems | A | |||||||||||
| Stand Pipes - Water Supply Piping *** | FY2022 | ||||||||||||
| Fire Alarm Systems | |||||||||||||
| EP3 | Duct Detectors/HVAC Systems Shutdown | A | Vis | ||||||||||
| EP3 | Electromechanical Release Devices / Door Holders | A | Vis | ||||||||||
| EP3 | Heat Detectors | A | Vis | ||||||||||
| EP3 | Manual Fire Alarm Boxes / Pull Stations | A | Vis | ||||||||||
| EP3 | Smoke Detectors | A | Vis | ||||||||||
| EP4 | Occupant Alarm Notification - A/V Devices | A | Vis | ||||||||||
| EP20 | Rolling Fire Doors | A | Vis | ||||||||||
| NFPA72 | Fire Alarm Panel incl Batteries | SA | SA | ||||||||||
| NFPA101 | Elevator Recall Smoke Detectors (lobbies and shafts) | A | Vis | ||||||||||
| Suppression Systems | |||||||||||||
| EP13 | Kitchen Wet Suppression System / Dry Chem System | SA | SA | ||||||||||
| EP16 | Portable Fire Extinguishers | A | |||||||||||
| Monitoring | |||||||||||||
| EP5 | SimplexGrinnell Central Station Monitoring * | Tested Daily | |||||||||||
| Tested In-House | |||||||||||||
| EP6 | Fire Pump Churn Test | W | W | W | W | W | W | W | W | W | W | W | W |
| EP18 | Fire & Smoke Dampers ** | FY22 | |||||||||||
| Fire Barriers | A | ||||||||||||
| ** Tested every four years. | |||||||||||||
| *** Tested every five years. | |||||||||||||
| Contractor Performed | Performed In-House | ||||||||||||
| WORK IS NOT COMPLETE UNTIL REPORTS HAVE BEEN SUBMITTED | |||||||||||||
| SimplexGrinnell Testing and Inspection Schedule Matrix - VA - West Haven, CT | |||||||||||||
| Revised August 12, 2021 | |||||||||||||
| Standard | Devices | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | June | July | Aug | Sept |
| Sprinkler Systems | |||||||||||||
| EP1 | Supervisory Signal Devices | Q | Q | Q | Q | ||||||||
| EP2 | Valves tampers, Flows & PIV's (PIV's exercised annually) | SA | SA | ||||||||||
| EP9 | Main Drain | SA | SA | ||||||||||
| EP10 | Fire Department Equipment Connections | Q | Q | Q | Q | ||||||||
| EP10 | Fire Hydrants | A | |||||||||||
| EP11 | Fire Pump Flow Test | A | |||||||||||
| NFPA25 | Dry Sprinkler Systems | A | |||||||||||
| Stand Pipes - Water Supply Piping *** | FY2022 | ||||||||||||
| Fire Alarm Systems | |||||||||||||
| EP3 | Smoke Detectors | A | Vis | ||||||||||
| EP3 | Duct Detectors/HVAC Systems Shutdown | A | Vis | ||||||||||
| EP3 | Electromechanical Release Devices / Door Holders | A | Vis | ||||||||||
| EP3 | Heat Detectors | A | Vis | ||||||||||
| EP3 | Manual Fire Alarm Boxes / Pull Stations | A | Vis | ||||||||||
| EP4 | Occupant Alarm Notification - A/V Devices | A | Vis | ||||||||||
| EP20 | Rolling Fire Doors | A | Vis | ||||||||||
| NFPA72 | Fire Alarm Panel incl Batteries | SA | SA | ||||||||||
| NFPA101 | Elevator Recall Smoke Detectors (lobbies and shafts) | A | Vis | ||||||||||
| Suppression Systems | |||||||||||||
| EP13 | Portable Fire Extinguishers | M | M | M | M | M | A | M | M | M | M | M | M |
| EP16 | Kitchen Wet Suppression System | SA | SA | ||||||||||
| Monitoring | |||||||||||||
| EP5 | SimplexGrinnell Central Station Monitoring * | Tested Daily | |||||||||||
| Tested In-House | |||||||||||||
| EP6 | Fire Pump Churn Test | W | W | W | W | W | W | W | W | W | W | W | |
| EP18 | Fire & Smoke Dampers ** | FY22 | |||||||||||
| Fire Barriers | A | ||||||||||||
| ** Tested every four years. | |||||||||||||
| *** Tested every five years. | |||||||||||||
| Contractor Performed | Performed In-House |
| SimplexGrinnell Testing and Inspection Schedule Matrix - Orange Annex - Orange, CT | |||||||||||||
| EP13 | Suppression Systems | ||||||||||||
| EP16 | Devices | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | June | July | Aug | Sept |
| Portable Fire Extinguisher | M | M | M | M | M | A | M | M | M | M | M | M | |
| Kitchen Wet Suppression System | SA | SA |
| SimplexGrinnell Testing and Inspection Schedule Matrix - VA Errera Center - New Haven, CT | |||||||||||||
| EP13 | Suppression Systems | ||||||||||||
| EP16 | Devices | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | June | July | Aug | Sept |
| Portable Fire Extinguisher | M | M | M | M | M | A | M | M | M | M | M | M | |
| Kitchen Wet Suppression System | SA | SA |
| WORK IS NOT COMPLETE UNTIL REPORTS HAVE BEEN SUBMITTED |
| Notes: |
| A = Annual M = Monthly |
| SA = Semi-Annual |
| Q = Quarterly |
| W = Weekly |
| Vis = Visual Inspection Only |
| Fire Alarm Communicators (Dialers) are tested daily by Simplex Central Station Monitoring |