RFI_Site_Visit_RFQP02011600012.pdf

PDF 37 KB Posted

Attached to
Replace Vault Water Lines Federal contract opportunity
Solicitation number
RFQP02011600012
Issued by
Department of Justice Bureau of Prisons Federal Correctional Complex Allenwood

View the file

Other files for this federal contract opportunity

Other files attached to Replace Vault Water Lines, newest first.
File Type Posted
RFQP02011600012_Amendment_003.pdf PDF
RFQP02011600012_Amendment002.pdf PDF
Site_Visit_Meeting_Minutes_6132016.pdf PDF
RFQP02011600012_SF1442_Revised.pdf PDF
RFQP02011600012_Amendment001.pdf PDF
Attachment_FCC_Allenwood_Vault__3_Pictures.pdf PDF
RFQP02011600012_Statement_of_Work.pdf PDF
RFQP02011600012_Coverletter.pdf PDF
RFQP02011600012_SF1442.pdf PDF
NCIC_Background_Check_Form.pdf PDF
Attachment_LSCI_Allenwood_Vault__2_Picture.pdf PDF
Davis_Bacon_Act_WD_PA160093_Modification_4_5-6-16_PA93.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Vault Waterlines

RFQP02011600012

Project 2B6K Request for Information Response

Site Visit Response

1. Is it possible for the contractor to be provided with as-builts for the vaults themselves?

We have one print we can provide. Do not know if any updates were made and cannot guarantee print is accurate. Contact Scott Barrett (sxbarrett@bop.gov) or Nick Guzenski (nguzenski@bop.gov) for a copy of the print.

2. Would the COR consider as a benefit to the government installing 4’ Bilco doors on each of the vaults as a part of the project to both make the work proposed and future maintenance of the vaults substantially easier despite a possible increase in overall price?

Please provide quote as outlined in Statement of Work. You may quote the supply and installation of access doors as an option in a separate line item.

3. Will the equipment on site from the prison be assisting the contractor to lower heavier pieces of piping and fittings down into the vaults?

Contractor must provide equipment to lower heavier pieces of piping and fittings into vaults.