This document summarizes a request for quotes (RFQ) from the National Institute of Allergy and Infectious Diseases (NIAID) for an electronic common technical document (eCTD) and electronic document management system. NIAID seeks a commercial off-the-shelf solution to manage regulatory submissions and review processes. The RFQ will follow a two-phase advisory down select process to evaluate quoters based on experience and configuration, product demonstrations, technical submissions, and price. Phase I questions are due August 3rd and Phase II submissions will be requested within ten business days of advisory guidance. Demonstrations will take place August 23rd through 26th. The award will be a single firm-fixed price purchase order for a base period of twelve months and four additional option periods of twelve months each. The North American Industry Classification System code is 541512 and there is no total small business set-aside.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA_PHASE I_NIAID eCTD_RFQ2076690.pdf | ||
| Attachment 4_Pricing Sheet_RFQ2076690.xlsx | XLSX spreadsheet | |
| RFQ_NIAID eCTD_RFQ2076690.pdf | ||
| Attachment 1_SOW_NIAID eCTD_RFQ2076690.pdf | ||
| Attachment 2_HHS Subcontracting Plan Template_RFQ2076690.doc | DOC document | |
| Attachment 3_Full Text Provisions and Clauses_RFQ2076690.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Electronic Common Technical Documents (eCTD) Publishing and Reviewing
Software Solicitation ID: RFQ-2076690
8/4/2021
II. PHASE II QUESTIONS
Q1: I am having trouble figuring out what attachments are due when? Are the other questions Due after the Demo or Tomorrow? Also please let us know what day you would like to see the demo.
A1: Phase I submissions are due 8/3/2021 5 pm EST. Please reference the Volume Tab on page 47 of the RFQ for the information to be submitted for each phase. The next due date for questions is also 8/3/2021 5 pm EST. Once NIAID completes Phase I evaluations, NIAID will send participants an email with a recommendation as to the likelihood of their organization being selected for award. Once the email is received and the organization elects to continue, you will have 10 days to submit the Phase II documents. If NIAID decides to offer an additional open question period, it will be mentioned in the recommendation email. NIAID will coordinate demo times with each vendor after the emails are sent out.
Q2: [Implementation] What is expected RPO and RTO for disaster recovery?
A2: Tentative MTD, RTO, and RPO are as follows. These values may change during the Security Assessment and Accreditation process.
Mission/Business Process
MTD RTO RPO
eCTD 1 business day
1 business day
1 business day
The estimated downtime factors are as follows:
• Maximum Tolerable Downtime (MTD): The MTD represents the total amount of time the system owner/authorizing official is willing to accept for a mission/business process outage or disruption and includes all impact considerations.
• Recovery Time Objective (RTO): RTO defines the maximum amount of time that a system resource can remain unavailable before there is an unacceptable impact on other system resources, supported mission/business processes, and the MTD.
• Recovery Point Objective (RPO): The RPO represents the point in time, prior to a disruption or system outage, to which mission/business process data can be recovered (given the most recent backup copy of the data) after an outage.
Q3: [Administration] Can one product sequence/submission be worked on by multiple divisions?
A3: No.
Q4: [Administration] Typically will external contractors/vendors access documents across single/multiple divisions?
A4: Typically, external contractors will only need to access one division’s documents. However, it’s possible an external contractor may need to access documents from more than one division.
Q5: [Access] Does NIAID require that the application be accessible via public internet?
A5: NIAID is looking for quoter’s suggestions and best practices for how the system is accessed.
Q6: [Administration] Can a single user be a member of multiple divisions?
A6: Most users will belong to a single division, but some will need access to multiple divisions.
Q7: [Administration] Are there users within the eDMS that require access across all divisions?
A7: Yes, but only a few.
Q8: [Administration] Are there documents that are not specific to any division?
A8: Yes, but not many.
Q9: [Administration] Can a document be applicable to multiple divisions or only one?
A9: Only one.