Question and Responses.pdf

PDF 61 KB Posted

Attached to
GREENHOUSE EVAPORATIVE COOLING SYSTEM REPLACEMENT Federal contract opportunity
Solicitation number
RFQ-20-4329-RS002
Issued by
Department of Agriculture Agricultural Research Service

View the file

Other files for this federal contract opportunity

Other files attached to GREENHOUSE EVAPORATIVE COOLING SYSTEM REPLACEMENT, newest first.
File Type Posted
Statement of Work for Replacement of Evaporative Coolers.docx DOCX document
SF18 RFQ for Replacement of Greenhouse Evaporative Cooling System.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ-20-4329-RS002 GREENHOUSE EVAPORATIVE COOLING SYSTEM REPLACEMENT

QUESTIONS AND RESPONSES

1) Can a quote be submitted without conducting a site visit?

A quote can be submitted without conducting a site visit. However, this is not recommended because if the quote is not within reason of the government cost estimate it may end up not being considered.

2) The completion date in the project schedule states to be complete 15 days after award. Can the completion date be extended?

The completion date will be negotiated at time of award. Nevertheless, there is an urgency to have this project completed a quickly as possible. Also stated in the schedule “Due to product availability for this project, all submittals shall reference estimated time of delivery” which was meant for materials.