This is a Solicitation/Contract/Order for Commercial Products and Commercial Services (Standard Form 1449) issued by the Department of Veterans Affairs (VA) Network Contracting Office 4 for the procurement of ceiling-mounted examination lights.
The VA Philadelphia Medical Center (VAPHI) requires the replacement of 18 pre-existing Chromophare D300 exam lights or equivalent units currently in use at the Emergency Department. The scope includes de-installation of existing lights, verification of structural support, purchase and installation of new ceiling-mounted exam lights, collaboration with VA Facilities on electrical requirements, and provision of all necessary labor, structural, steel work, and electrical components. Technical specifications require lights to be ceiling-mounted weighing no more than 9kg (including power supply), with controls to adjust light intensity across a minimum of 5 levels, a maximum of 10 LED light bulbs, minimum light intensity of 80 klux at 1 meter distance, minimum 36-inch vertical adjustment capability, 100-240V AC power supply, dual arms (spring and horizontal) with a minimum 30-inch horizontal arm length, and compatibility with existing mounting plates. All equipment must carry a minimum one-year warranty covering parts and labor. Quotes are due by March 27, 2026, at 1:00 PM EST with delivery required 90 days after receipt of order (ARO) on an FOB Destination basis to VAPHI, 3900 Woodland Ave, Philadelphia, PA 19104. The solicitation is unrestricted (100% small business set-aside was not applied). Invoices will be submitted electronically and payment will be made via Electronic Funds Transfer following receipt, inspection, and acceptance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment A - List of ED Exam Lights .xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF 1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
642-26-2-315-0040
36C24426Q0360 03-09-2026
McDaniel Brayboy III 916-841-7834 03-27-2026
1:00 PM EST
36C244
Department of Veterans Affairs
Network Contracting Office 4
3900 Woodland Ave
Philadelphia PA 19104 x 100
339113
750 Employees
N/A
X
See delivery schedule.
36C244
Network Contracting Office 4
Philadelphia PA 19104
Austin Payment Center
PO Box 149971
Austin TX 78714-9971
(877) 353-9791 (512) 460-5429
See CONTINUATION Page
Ceiling Mounted Exam Lights
Please provide a quote in accordance with the Statement of need.
All quotes must include delivery lead time, Vendors UEI
#, Manufacturer Part and Stock Numbers.
PLEASE READ SOLICITATION IN ITS ENTIRETY, AND COMPLETE ALL
SECTIONS THAT ARE HIGHLIGHTED AND REQUIRE QUOTER INPUT.
Quotes must be submitted by email no later than Friday
March 27, 2026, by 1:00 PM Eastern Standard Time to mcdaniel.brayboy@va.gov
All questions must be submitted in writing by 11:00 AM
03/17/2026.
See CONTINUATION Page
X
X 1
Melvin Moore
Contracting Officer
36C24426Q0360
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
B.3 DELIVERY SCHEDULE
B.4 STATEMENT OF NEED
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (NOV 2023)
C.2 52.225-1 BUY AMERICAN—SUPPLIES (OCT 2022)
C.3 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
C.4 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
C.5 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)
C.6 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
C.7 VAAR 852.246-71 REJECTED GOODS (OCT 2018)
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (SEP 2023)
E.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
E.3 52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES—REPRESENTATION
(OCT 2020)
E.4 52.225-2 BUY AMERICAN CERTIFICATE (OCT 2022)
E.5 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY
NOTICE (FEB 2023)
E.6 52.212-2 EVALUATION—SIMPLIFIED ACQUISITION PROCEDURES
E.7 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION FEB 2025)
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
POC:
TEL:
EMAIL:
b. GOVERNMENT: Melvin Moore, Contracting Officer McDaniel Brayboy III, Contract Specialist
Department of Veterans Affairs Network Contracting Office 4 Philadelphia Va Medical Center 3900 Woodland Ave Philadelphia, PA 19104
TEL: 916-841-7834
EMAIL: mcdaniel.brayboy@va.gov
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
[X] 52.232-34, Payment by Electronic Funds Transfer—Other Than System For Award Management, or
[] 52.232-36, Payment by Third Party
3. INVOICES: Invoices shall be submitted in arrears:
a. Quarterly [ ]
b. Semi-Annually [ ]
c. Other [X] Upon receipt, inspection, and acceptance by the Government.
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of
Payment Requests.
Tungsten Network https://www.tungsten-network.com/ https://www.tungsten-network.com/
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
AMENDMENT NO DATE
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
18.00 EA __________________ __________________
SIRCA Ceiling Double Arm
PRINCIPAL NAICS CODE: 339113 - Surgical Appliance and Supplies Manufacturing PRODUCT/SERVICE CODE: 6530 - Hospital Furniture, Equipment, Utensils, and Supplies
MANUFACTURER PART NUMBER (MPN): FILL IN
FLANGE TUBE CPL
PRINCIPAL NAICS CODE: 339113 - Surgical Appliance and Supplies Manufacturing PRODUCT/SERVICE CODE: 6530 - Hospital Furniture, Equipment, SOFFIT F 300 446 X 120 MM TUBE
PRINCIPAL NAICS CODE: 339113 - Surgical Appliance and Supplies Manufacturing PRODUCT/SERVICE CODE: 6530 - Hospital Furniture, Equipment, POWER SWITCHING SUPPLY F300 90-132 VAC
PRINCIPAL NAICS CODE: 339113 - Surgical Appliance and Supplies Manufacturing PRODUCT/SERVICE CODE: 6530 - Hospital Furniture, Equipment,
1.00 EA __________________ __________________
INSTALLATION
PRINCIPAL NAICS CODE: 339113 - Surgical Appliance and Supplies Manufacturing PRODUCT/SERVICE CODE: 6530 - Hospital Furniture, Equipment, GRAND TOTAL __________________
B.3 DELIVERY SCHEDULE
ITEM
NUMBER SHIPPING INFORMATION QUANTITY DELIVERY DATE
0001 SHIP TO: CMCVAMC
3900 Woodland Ave Philadelphia, PA 19104
USA
18.00 90 DAYS ARO
FOB: DESTINATION
0002 SHIP TO: CMCVAMC
0003 SHIP TO: CMCVAMC
0004 SHIP TO: CMCVAMC
0005 SHIP TO: CMCVAMC
1.00 90 DAYS ARO
B.4 STATEMENT OF NEED
Statement of Need
VA Philadelphia Medical Center (VAPHI)
SCOPE OF WORK AND GENERAL SPECIFICATIONS FOR REPLACEMENT OF CEILING- MOUNTED
EXAMINATION LIGHTS
1. Background
Exam lights assist clinical staff during medical examinations by illuminating body surfaces and cavities. Their specialized lighting provides clinicians with an accurate view of the body reducing errors of diagnosis. There are several types of exam lights: ceiling-mounted, floor standing, and wall-mounted. Ceiling-mounted lights are designed to suspend from ceiling providing an increased range of motion, while also minimizing space concerns.
The current fleet of ceiling-mounted exam lights located within the Emergency Department
(ED) at the Philadelphia VA Medical Center (VAPHI) are approaching their end-of-life cycle due to degradation experienced from normal usage throughout their lifespan. The ED utilizes this equipment during patient examinations to assess a patient’s condition, perform diagnostics, and carry out treatment plans. To prevent further equipment failures and minimize impacts on patient care, these ceiling-mounted exam lights require replacement.
2. Project Scope
This procurement covers the replacement of the 18 pre-existing Chromophare D300 exam lights or Equal. The lights are in the ED exam rooms at VAPHI. This will include the de-installation of the current exam lights as well as the purchase and installation of new ceiling-mounted exam lights. The inventory and rooms of the existing ceiling lights is listed in
Attachment A. The current inventory includes 17 exam lights, as one unit has been turned in as of October 2025. The Emergency department still requires 18 exam lights to be installed.
The Contractor is responsible for the below minimum services:
• De-installation of existing ceiling-mounted exam lights
• Verification of structural support
• Provision of new Ceiling-mounted exam light replacement equipment
• Complete installation of procured replacement equipment
• Collaboration with VAPHI Facilities department for validation of electrical requirements
• Provision of any necessary labor, structural, steel work, and electrical components needed for the system to function safely
• Any cable pulling required for the equipment will be installed by certified technicians only
• Fulfillment of VHA Directive 7715, Safety and Health Drug Construction and VA recognized health care accreditation standards. This includes infection control efforts, pre-construction risk assessments (PCRA) and infection control risk assessments (ICRA).
Note: this does not include all requirements, but the basic requirements required for each installation of exam light.
Technical Requirements
The exam light should:
▪ be ceiling-mounted
▪ weigh no more than 9kg including power supply
▪ provide controls to adjust light intensity at a minimum of 5 different intensity levels
▪ have a maximum of 10 LED light bulbs
▪ have a minimum light intensity of 80 klux at a distance of 1m
▪ perform a minimum of 36in vertical adjustment
▪ power supply voltage 100 - 240 V (AC)
▪ have two arms to support increased range of motion: spring arm and horizontal arm
▪ minimum length of horizontal arm is 30in
• compatible with mounting plate for current existing exam lights. See figure 1 listed below for schematics of existing mounting plate:
Figure 1: Schematics of existing exam light mounting plate within Emergency Department at
VAPHI
3. Installation Requirements
Installation, testing, and Go-live will be completed by contractor. Upon contract award, the contractor must provide a project manager point of contact for kick-off. Contractor will work with Biomed and Facilities electrical representatives to validate electrical requirements. During installation, the Contractor must meet the occupational safety and health requirements as well as adhere to the VHA Directive 7715 for Safety and Health
During Construction. The contractor will work with Biomedical Engineering staff to provide any additional documentation required.
4. Labor
All necessary labor must be included with the procurement of each ceiling-mounted exam light. The Contractor shall have available both standard weekday business hours and weekend hours due to impacts to patient care. Scheduling will be discussed with the
Biomedical Engineering representative and coordinated with the Clinical end users. The flexibility of schedule is due to unpredictability of patient volume that can occur within the
Emergency Department. The contractor must be able to work during times agreed upon by
Biomedical and Clinical end users to minimize impacts on patient care.
5. Warranty
All equipment procured under this contract will have a minimum one-year warranty for all parts and associated fees (i.e., labor and shipping). Contractor may provide optional add-ons for extended coverage as desired.
6. Delivery Location
VA Philadelphia Medical Center
Prior to delivery, Contractor shall verify shipment with the VAPHI designated point of contact. Once confirmed, tracking information, quantity and estimated arrival shall be provided.
The Contractor must comply and provide all necessary verification and information to the VAMC. The Purchase Order information must be included on the shipment for proper receiving. Failure to include Purchase Order information may result in the delivery being turned away. The delivery may be refused and require redelivery at no additional cost to the government.
7. Delivery Coordination
Normal business hours for acceptance of deliveries are 8:00am-3:30pm, Monday through Friday excluding Federal Holidays. Deliveries must be coordinated in advance with POC once a ship date is established. The POC, Biomedical Engineering and/or
Logistics Representative shall be the only VA entity signing for freight received on this requirement. The VA-issued purchase order number must be included in the packing slip. All items included in the requirement shall be shipped and delivered to site at the same time. If deliveries must be broken into several shipments due to size, this must be coordinated in advance with the POC. Failure of the coordinate shipment with POC may result in failure to deliver on site and cause re-scheduling of delivery/freight at no charge to the government. The packing slip must include the VA-issued purchase order number.
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The
Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered;
and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31
U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the
Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the
Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by
Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and
Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the
Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt
Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-
5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting
Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the
Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The
Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the
Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the
Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain
Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws
Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service
(TOS), or similar legal instrument or agreement, that includes any clause requiring the
Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause)
ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES
Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
C.2 52.225-1 BUY AMERICAN—SUPPLIES (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—(1) Means any item of supply (including construction material) that is—
(i) A commercial product (as defined in paragraph (1) of the definition of ‘‘commercial product’’ at Federal Acquisition Regulation (FAR) 2.101;
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into an end product.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the end product.
Critical component means a component that is mined, produced, or manufactured in the
United States and deemed critical to the U.S. supply chain. The list of critical components is at
FAR 25.105.
Domestic end product means—
(1) For an end product that does not consist wholly or predominantly of iron or steel or a combination of both—
(i) An unmanufactured end product mined or produced in the United States;
(ii) An end product manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind as those that the agency determines are not mined, produced, or manufactured in sufficient and reasonably available commercial quantities of a satisfactory quality are treated as domestic. Components of unknown origin are treated as foreign. Scrap generated, collected, and prepared for processing in the United States is considered domestic; or
(B) The end product is a COTS item; or
(2) For an end product that consists wholly or predominantly of iron or steel or a combination of both, an end product manufactured in the United States, if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all the components used in the end product. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the end product and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the end product contains multiple components, the cost of all the materials used in such end product is calculated in accordance with the definition of ‘‘cost of components’’.
End product means those articles, materials, and supplies to be acquired under the contract for public use.
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign end product means an end product other than a domestic end product.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) 41 U.S.C. chapter 83, Buy American, provides a preference for domestic end products for supplies acquired for use in the United States. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for an end product that is a COTS item (see
12.505(a)(1)), except that for an end product that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the end product, excluding COTS fasteners.
(c) Offerors may obtain from the Contracting Officer a list of foreign articles that the
Contracting Officer will treat as domestic for this contract.
(d) The Contractor shall deliver only domestic end products except to the extent that it specified delivery of foreign end products in the provision of the solicitation entitled "Buy
American Certificate."
Alternate I (OCT 2022). As prescribed in 25.1101(a)(1)(ii) substitute the following sentence for the first sentence of paragraph (1)(ii)(A) of the definition of ‘‘domestic end product’’ in paragraph (a): (A) The cost of its components mined, produced, or manufactured in the United
States exceeds ___ percent of the cost of all its components. [Contracting officer to insert the percentage.]
(End of Clause)
C.3 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Clause)
FAR
Number
Title Date
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS NOV 2023
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS
DEC 2014
52.233-3 PROTEST AFTER AWARD AUG 1996
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM OCT 2004
C.4 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
The Contractor shall not make reference in its commercial advertising to Department of
Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.
C.5 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)
(a) Definitions. As used in this clause—
(1) Contract financing payment has the meaning given in FAR 32.001;
(2) Designated agency office means the office designated by the purchase order, agreement, or contract to first receive and review invoices. This office can be contractually designated as the receiving entity. This office may be different from the office issuing the payment;
(3) Electronic form means an automated system transmitting information electronically according to the accepted electronic data transmission methods and formats identified in paragraph (c) of this clause. Facsimile, email, and scanned documents are not acceptable electronic forms for submission of payment requests;
(4) Invoice payment has the meaning given in FAR 32.001; and
(5) Payment request means any request for contract financing payment or invoice payment submitted by the contractor under this contract.
(b) Electronic payment requests. Except as provided in paragraph (e) of this clause, the contractor shall submit payment requests in electronic form. Purchases paid with a
Government-wide commercial purchase card are considered to be an electronic transaction for purposes of this rule, and therefore no additional electronic invoice submission is required.
(c) Data transmission. A contractor must ensure that the data transmission method and format are through one of the following:
(1) VA’s Electronic Invoice Presentment and Payment System at the current website address provided in the contract.
(2) Any system that conforms to the X12 electronic data interchange (EDI) formats established by the Accredited Standards Center (ASC) and chartered by the American National
Standards Institute (ANSI).
(d) Invoice requirements. Invoices shall comply with FAR 32.905.
(e) Exceptions. If, based on one of the circumstances in this paragraph (e), the Contracting
Officer directs that payment requests be made by mail, the Contractor shall submit payment requests by mail through the United States Postal Service to the designated agency office.
Submission of payment requests by mail may be required for—
(1) Awards made to foreign vendors for work performed outside the United States;
(2) Classified contracts or purchases when electronic submission and processing of payment requests could compromise the safeguarding of classified or privacy information;
(3) Contracts awarded by contracting officers in the conduct of emergency operations, such as responses to national emergencies;
(4) Solicitations or contracts in which the designated agency office is a VA entity other than the VA Financial Services Center in Austin, Texas; or
(5) Solicitations or contracts in which the VA designated agency office does not have electronic invoicing capability as described above.
(End of Clause)
C.6 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
The Contracting Officer reserves the right to designate an Administrative Contracting Officer
(ACO) for the purpose of performing certain tasks/duties in the administration of the contract.
Such designation will be in writing through an ACO Letter of Delegation and will identify the responsibilities and limitations of the ACO. A copy of the ACO Letter of Delegation will be furnished to the Contractor.
(End of Clause)
C.7 VAAR 852.246-71 REJECTED GOODS (OCT 2018)
(a) Supplies and equipment. Rejected goods will be held subject to Contractor’s order for not more than 15 days, after which the rejected merchandise will be returned to the Contractor’s address at the Contractor’s risk and expense. Expenses incident to the examination and testing of materials or supplies that have been rejected will be charged to the Contractor.
(b) Perishable supplies. The Contractor shall remove rejected perishable supplies within 48 hours after notice of rejection. Supplies determined to be unfit for human consumption will not be removed without permission of the local health authorities. Supplies not removed within the allowed time may be destroyed. The Department of Veterans Affairs will not be responsible for, nor pay for, products rejected. The Contractor will be liable for costs incident to examination of rejected products.
(End of Addendum to 52.212-4)
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (SEP 2023)
(a) North American Industry Classification System (NAICS) code and small business size standard. The NAICS code(s) and small business size standard(s) for this acquisition appear elsewhere in the solicitation. However, the small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(1) Is set aside for small business and has a value above the simplified acquisition threshold;
(2) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(3) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b) Submission of offers. Submit signed and dated offers to the office specified in this solicitation at or before the exact time specified in this solicitation. Offers may be submitted on the SF 1449, letterhead stationery, or as otherwise specified in the solicitation. As a minimum, offers must show—
(1) The solicitation number;
(2) The time specified in the solicitation for receipt of offers;
(3) The name, address, and telephone number of the offeror;
(4) A technical description of the items being offered in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature, or other documents, if necessary;
(5) Terms of any express warranty;
(6) Price and any discount terms;
(7) "Remit to" address, if different than mailing address;
(8) A completed copy of the representations and certifications at Federal Acquisition
Regulation (FAR) 52.212-3 (see FAR 52.212-3(b) for those representations and certifications that the offeror shall complete electronically);
(9) Acknowledgment of Solicitation Amendments;
(10) Past performance information, when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information); and
(11) If the offer is not submitted on the SF 1449, include a statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation. Offers that fail to furnish required representations or information, or reject the terms and conditions of the solicitation may be excluded from consideration.
(c) Period for acceptance of offers. The offeror agrees to hold the prices in its offer firm for 30 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.
(d) Product samples. When required by the solicitation, product samples shall be submitted at or prior to the time specified for receipt of offers. Unless otherwise specified in this solicitation, these samples shall be submitted at no expense to the Government, and returned at the sender's request and expense, unless they are destroyed during preaward testing.
(e) Multiple offers. Offerors are encouraged to submit multiple offers presenting alternative terms and conditions, including alternative line items (provided that the alternative line items are consistent with FAR subpart 4.10), or alternative commercial products or commercial services for satisfying the requirements of this solicitation. Each offer submitted will be evaluated separately.
(f) Late submissions, modifications, revisions, and withdrawals of offers.
(1) Offerors are responsible for submitting offers, and any modifications, revisions, or withdrawals, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that offers or revisions are due.
(2)(i) Any offer, modification, revision, or withdrawal of an offer received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—
(A) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of offers; or
(B) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(C) If this solicitation is a request for proposals, it was the only proposal received.
(ii) However, a late modification of an otherwise successful offer, that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(3) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the offer wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of
Government personnel.
(4) If an emergency or unanticipated event interrupts normal Government processes so that offers cannot be received at the Government office designated for receipt of offers by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of offers will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(5) Offers may be withdrawn by written notice received at any time before the exact time set for receipt of offers. Oral offers in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile offers, offers may be withdrawn via facsimile received at any time before the exact time set for receipt of offers, subject to the conditions specified in the solicitation concerning facsimile offers. An offer may be withdrawn in person by an offeror or its authorized representative if, before the exact time set for receipt of offers, the identity of the person requesting withdrawal is established and the person signs a receipt for the offer.
(g) Contract award (not applicable to Invitation for Bids). The Government intends to evaluate offers and award a contract without discussions with offerors. Therefore, the offeror's initial offer should contain the offeror's best terms from a price and technical standpoint. However, the Government reserves the right to conduct discussions if later determined by the
Contracting Officer to be necessary. The Government may reject any or all offers if such action is in the public interest; accept other than the lowest offer; and waive informalities and minor irregularities in offers received.
(h) Multiple awards. The Government may accept any item or group of items of an offer, unless the offeror qualifies the offer by specific limitations. Unless otherwise provided in the
Schedule, offers may not be submitted for quantities less than those specified. The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit prices offered, unless the offeror specifies otherwise in the offer.
(i) Availability of requirements documents cited in the solicitation.
(1)(i) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and product descriptions can be downloaded from the ASSIST website at https://assist.dla.mil.
(ii) If the General Services Administration, Department of Agriculture, or Department of
Veterans Affairs issued this solicitation, a copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained from the address in paragraph
(i)(1)(i) of this provision.
(2) Most unclassified Defense specifications and standards may be downloaded from the
ASSIST website at https://assist.dla.mil.
(3) Defense documents not available from the ASSIST website may be requested from the
Defense Standardization Program Office by-
(i) Using the ASSIST feedback module (https://assist.dla.mil/feedback); or
(ii) Contacting the Defense Standardization Program Office by telephone at 571-767-6688 or email at assisthelp@dla.mil.
(4) Nongovernment…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .