RFIs 573-18-604 with responses 24 Aug 22.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Z2DA--Correct Tunnel Water Protection Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

This document contains responses to requests for information (RFIs) related to a federal contract opportunity for correct tunnel water protection work at a Veterans Affairs medical facility. The opportunity involves performing repairs and improvements to address water protection issues in the facility's tunnel. Work is to be completed in phases on weekends and weekday nights to maintain staff and patient access. An on-site area will be designated for materials storage and one construction trailer will be permitted. Temporary construction fencing and refinishing of existing pipe railings either in place or off site are required. The contract refinishing work involves using exterior high gloss acrylic latex over waterborne galvanized primer. Proposals for the opportunity are due by September 8, 2022.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Correct Tunnel Water Protection, newest first.
File Type Posted
Site Visit Sign in Sheet 573-18-604.pdf PDF
S02 - SF30 Amendment 36C24822R0156 0001.pdf PDF
29450 Final Report (Piezometers at Pedestrian Tunnel)_digi.pdf PDF
ACMPbSurveyReport.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Correct Tunnel Water Protection
PROJ: 573-18-604
RFI's/QuestionsGovernment Response
1Please provide test reports for any testing that may have been performed in relationship to this project such as soil borings, ground water and ACM.Piezometer Report is available see attachment.
2Please confirm the work hours for the work inside the tunnel.Refer to specification Section 01 00 00, 1.6.G.3 and 4 and Sheet G003. Phases IA, B, C and D are to be completed during weekends from Friday 10:pm to Monday morning 5:30 am or weekdays from 10 pm to 5:30 am. Staff and patient access must be maintained Monday through Friday from 6:30 am to 9:30 pm. The remaining tunnel phases can be performed during daytime hours.
3What permits are anticipated for this project? Have these permits been applied for? When are these permits scheduled to be issued?The activities to perform the repairs and improvements per bid documents are exempt of permits.
4Please clarify if a superintendent can be a triple hat to cover the requirements of SSHO and QA/QC?Specification require separate rolls. Refer to spcification Section 01 00 00, 1.7.C: The SSHO is a seperate qualified individual from the Prime Contractor's Superintendent or Quality Control Manager. Refer to specification Section 01 45 00, 3.1.A: the Superintendent is the highest level manager on site responible for construction activities inclusive of quality and production: 3.2.B.1, the CQC Systems Manager reports to the Superintendent.
5If no to the question above, will the SSHO need to be full-time for this project?Refer to specification Section 01 35 26, 1.7.D: The SSHO will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6, Superintendence by the Contractor.
6Please identify an area onsite where a lay down yard can be established for the duration of the project.The contractor will be authorized to place one-20' Conex inside the construction limit of site improvements. No other space will be available for the laydown area.
7Please clarify if temporary fencing will be required during exterior construction activities?Temporary construction fencing with fence fabric required. Refer to specification Section 01 00 00, 1.6.J.
8Please clarify if the site work is to be completed with a certain Phase or at any time during construction?Site work can be completed at anytime during construction. Schedule with COR.
9Please clarify if the roof work to be completed with a certain Phase or at any time during construction?Roof work can be completed at any time during construction. Schedule with COR.
10Please clarify if the refinishing of existing pipe rail system is to be done in place?Refinish in place or provided temporary barriers if removed for shop refinishing.
11Please specify product requested to refinish existing pipe rail.Refer to specification section 09 91 00, exterior high gloss acrylic latex over waterborne galvanized primer.
12Please confirm the limits of refinishing existing pipe rail shown as “TYPICAL."All existing pipe rail on the MRI buildng and the tunnel emergency exit stair are to be refinished.
13If the ACM survey will be sent out along with the RFI responses.ACM Report is available see attachment.