Amendment_No._0002_to_R17PS00302.pdf

PDF 122 KB Posted

Attached to
Synthetic Sheet Pile Field Trial Federal contract opportunity
Solicitation number
R17PS00302
Issued by
Department of the Interior Bureau of Reclamation

About this file

Amendment No. 0002 to R17PS00302

View the file

Other files for this federal contract opportunity

Other files attached to Synthetic Sheet Pile Field Trial, newest first.
File Type Posted
Amendment_No._0001_to_R17PS00302.pdf PDF
Solicitation_R17PS00302.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

R17PS00302

x x

2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815

R20

Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation

03/08/2017000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/08/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Legacy Doc #: BOR

The Solicitation cited in block 9A above, Synthetic Sheet Pile Field Trial is hereby amended.

Purpose: The purpose of this amendment is to incorporate the attached Questions and

Answers.

The date and time for receipt of offers is hereby UNCHANGED and remains March 10, 2017 at

2:00 p.m.

The offeror must acknowledge this amendment by submitting a signed copy of this SF30 along

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Rosana Yousefgoarji

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

R17PS00302/000002

with their proposal.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Amendment No. 0002 to Solicitation No. R17PS00302

SYNTHETIC SHEET PILE FIELD TRIAL

TRUCKEE CANAL, FERNLEY NEVADA

Questions and Answers

Question 1: Can the bid documents be revised to a day rate for sheet pile installation in lieu of the Square Footage Item shown? With the difficult soils conditions and being that this job is out of town there are a lot of fixed costs with mobilization, travel time, subsistence, and motels which cannot be divided into the square foot unit price. For an example, due to the soils stay even with predrilling we cannot advance a single sheet pile to the tip elevation in a days’ worth of work. How is the contractor to be paid for the work spent trying to install the sheets into cobble soils if there is no square footage in the ground?

Response 1: The Contractor shall provide cost estimates using the bid schedule provided in the solicitation.

The Contractor will be paid for the full quantity of sheet pile materials furnished to the site. Request for payment may be made upon delivering the materials to the site, but no sooner than October, 2017.

Regarding the "difficult installation site", installation will be attempted with the specified vibratory hammer and steel mandrel equipment. If traditional driving methods are unsuccessful, then pre-augering or spudding ahead of the sheet pile installation will be attempted. These methods will be attempted for no more than 2 days, or once shown that they are not viable/efficient. The quantity of sheet piling that is not installed at the "difficult installation site" will be installed at Site No. 1 by the Contractor.

Questions 2: If a per day cost does not work can you allow for a mobilization/fixed cost unit price item?

Response 2: No, the Contractor shall provide cost estimates using the bid schedule provided in the solicitation.

The Contractor may request payment for the specified quantity of installed sheet piling at Site No. 1 (2,250 sf) upon mobilization to the site. The remainder of the installed sheet piling will be paid once the work is complete.