Amendment_No._0002_to_R17PS00302.pdf
PDF 122 KB Posted
- Attached to
- Synthetic Sheet Pile Field Trial Federal contract opportunity
- Solicitation number
- R17PS00302
About this file
Amendment No. 0002 to R17PS00302
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No._0001_to_R17PS00302.pdf | ||
| Solicitation_R17PS00302.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
R17PS00302
x x
2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
03/08/2017000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/08/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Legacy Doc #: BOR
The Solicitation cited in block 9A above, Synthetic Sheet Pile Field Trial is hereby amended.
Purpose: The purpose of this amendment is to incorporate the attached Questions and
Answers.
The date and time for receipt of offers is hereby UNCHANGED and remains March 10, 2017 at
2:00 p.m.
The offeror must acknowledge this amendment by submitting a signed copy of this SF30 along
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Rosana Yousefgoarji
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
R17PS00302/000002
with their proposal.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment No. 0002 to Solicitation No. R17PS00302
SYNTHETIC SHEET PILE FIELD TRIAL
TRUCKEE CANAL, FERNLEY NEVADA
Questions and Answers
Question 1: Can the bid documents be revised to a day rate for sheet pile installation in lieu of the Square Footage Item shown? With the difficult soils conditions and being that this job is out of town there are a lot of fixed costs with mobilization, travel time, subsistence, and motels which cannot be divided into the square foot unit price. For an example, due to the soils stay even with predrilling we cannot advance a single sheet pile to the tip elevation in a days’ worth of work. How is the contractor to be paid for the work spent trying to install the sheets into cobble soils if there is no square footage in the ground?
Response 1: The Contractor shall provide cost estimates using the bid schedule provided in the solicitation.
The Contractor will be paid for the full quantity of sheet pile materials furnished to the site. Request for payment may be made upon delivering the materials to the site, but no sooner than October, 2017.
Regarding the "difficult installation site", installation will be attempted with the specified vibratory hammer and steel mandrel equipment. If traditional driving methods are unsuccessful, then pre-augering or spudding ahead of the sheet pile installation will be attempted. These methods will be attempted for no more than 2 days, or once shown that they are not viable/efficient. The quantity of sheet piling that is not installed at the "difficult installation site" will be installed at Site No. 1 by the Contractor.
Questions 2: If a per day cost does not work can you allow for a mobilization/fixed cost unit price item?
Response 2: No, the Contractor shall provide cost estimates using the bid schedule provided in the solicitation.
The Contractor may request payment for the specified quantity of installed sheet piling at Site No. 1 (2,250 sf) upon mobilization to the site. The remainder of the installed sheet piling will be paid once the work is complete.