Solicitation_R16PS01066.pdf
PDF 5 MB Posted
- Attached to
- Folsom Resource Building Federal contract opportunity
- Solicitation number
- R16PS01066
About this file
Solicitation No. R16PS01066
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No._0004_to_R16PS01066.pdf | ||
| Amendment_No._0003_to_R16PS01066.pdf | ||
| Amendment_No._0002_to_R16PS01066.pdf | ||
| Amendment_No._0001_to_R16PS01066.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. R16PS01066
Folsom Resource Building
American River Division Folsom Unit Central Valley Project – California
TABLE OF CONTENTS
SECTION A - Solicitation, Offer and Award Form (SF 1442)
SECTION B - Pricing Schedule
SECTION C - Specifications/Appendices
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
SECTION F - Deliveries or Performance
SECTION G - Contract Administration Data
SECTION H - Special Contract Requirements
SECTION I - Contract Clauses
SECTION J - List of Documents, Exhibits, and Other Attachments
SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION L - Instructions, Conditions and Notices to Offerors
SECTION M - Evaluation Factors for Award
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040268114
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Bureau of Reclamation
Mid-Pacific Regional Office 2800 Cottage Way, Rm. E-1815 Sacramento, California 95825-1898
Rosana Yousefgoarji 916-978-5004 xR16PS01066
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A. Title: Folsom Resource Building
B. Work Site Location: Work is located approximately 2 miles north of the City of
Folsom, California in Sacramento County.
C. Site Visit Information: Site visit information is located in the solicitation in
Section L, Clause 52.236-27.
D. Estimated Price Range: $100,000.00 to $500,000.00
E. Set-aside Information: This requirement is reserved for Service Disabled
Veteran Owned Small Business concerns, in accordance with Federal Acquisition
Regulation (FAR) Section 19.1405.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 180 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F
07/06/2016
NSN 7540-01-155-3212
x x x x
___1__________ copies to perform the work required are due at the place specified in Item 8 by ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Rosana Yousefgoarji
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R16PS01066
Legacy Doc #: BOR
Delivery Location Code: 0009909968
Bureau of Reclamation-MP-CCAO
Central California Area Office
7794 Folsom Dam Road-Receiving
Folsom CA 95630-1799 US
FOB: Destination
00010 Folsom Resource Building 1 AU
(Price Schedule CLIN 1 through 4)
See Following Continuation Page
Delivery: 180 Days After Notice to Proceed
00011
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
Folsom Resource Building
AMERICAN RIVER DIVISION
CENTRAL VALLEY PROJECT - CALIFORNIA
B.1 PRICE SCHEDULES
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(d) Definitions:
(1) CLIN – Contract Line Item Number.
CLIN Supplies or Services Quantity and Unit
Unit Price Amount
1 Mobilization and Preparatory Work For the lump sum of $
2 Building 109 Demolition/Removal For the lump sum of $
3 Building 012 Relocation For the lump sum of $
4 Security Fencing/Barrier For the lump sum of $
TOTAL FOR SCHEDULE $_________________
B-1
C-1
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
Statement of Work titled “Folsom Resource Building” is attached.
Folsom Resource Building (Modular Building Removal, Modular Building Relocation, and Fence Installation)
Folsom Unit, American River Division, Central Valley Project, California
1. BACKGROUD/PROJECT CONDITIONS
1.1. Background: The Bureau of Reclamation, Central California Area Office (CCAO), has a modular office building to be removed, a modular office building to be relocated, security fence to be removed, security fence to be installed, decorative fence to be installed, and a concrete block wall to be modified to meet Area Office facility utilization and security mission goals. The work is located at Folsom Dam on the American River approximately 2 miles north of Folsom, California, in Sacramento County.
1.2. Project Conditions: The work is located at Folsom Dam in three distinct security zones: an unsecured office complex, Security Zone 1 (Administration Area), and an adjacent part of Security Zone 2. The Contractor will work in each of the three Zones and employees will require Government issued security badges to conduct activities within security Zones 1 and 2. The modular office building to be removed is located on asphaltic concrete, while the modular office building to be relocated is located on compacted gravel surfacing.
1.2.1. Building 109 (Resource Building): The Modular Office Building to be removed is a 6 unit-wide office (72 feet W x 60 feet L) that is at the end of its useful life for Government activities and is located within Security Zone 1. The building has electric, telephone, data, water and sanitary sewer service. Utilities shall be disconnected to allow for reutilization when a newer 4 unit-wide modular office building (48 feet W x 60 feet L) is relocated to the site under this contract. There are two concrete stair landings to be removed. Appurtenant features include two access ramps and three sets of stairs with landings. The Offeror shall remove the modules from the facility along with appurtenant components that cannot be reused on site for the new modular office building. The Offeror shall remove seismic anchor straps to pavement surface and grind any sharp edges smooth that are not to be reutilized to anchor the new modular office building. Federal facilities regulations require the Government to reuse, recycle, or dispose of facilities at an appropriate or certified facility. The Offeror shall provide written certifications that the Modular Office Building materials are disposed of at certified facilities.
1.2.2. Building 012: The Modular Office Building to be relocated is a 4 unit-wide office (48 feet W x 60 feet L) with one set of access ramps with stairs and three sets of stairs. The building is located in an unsecure outside of Security Zone 1.
The building has electric, telephone, data, water and sanitary sewer service.
Utilities shall be disconnected and stubs sealed to protect from weather for potential reuse at a future time. The seismic anchor straps should be removed.
Installation should be done on Modular Office Building 012 at the former site of Modular Office Building 109 and reestablish utility service at the new location within Security Zone 1. Floors; ceiling; interior and exterior walls; roof;
skirting; and access stairs, ramps and landings should be reestablished. Stairs, ramps, and landings should be reutilized where possible. Install seismic anchoring in accordance with applicable codes and regulations.
1.2.3. Security Zone 1 Fence Removal: A portion of the security fence to be removed is located within Security Zone 2 and must be removed in phases to assure no secured areas will be left unsecured during non-work hours. Items to be removed in the first phase include a post and single wire barrier and sections of 6 foot high chain link fence with 3 strands of barbed wire. This work must be accomplished prior to the installation of the new Security Zone 2 fence, because these items are on the same alignment as the new fence installation. Items to be removed in the second phase include gates to be reused and 8 foot high chain-link fence with 3 strands of barbed wire and some razor wire that run between buildings and will no longer be required. This work can only be accomplished after the new Security Zone 2 fence has been installed.
1.2.4. Security Zone 2 Fence to Install: The security fence to install is 8 foot high chain-link fence with 3 strands of barbed wire. The fence will start at an existing vehicle fence and traverse to sides of a large parking area, reconnecting near the site of Building 109. Existing pedestrian and vehicle gates will be relocated to complete the fence perimeter.
1.2.5. Landscaping: Landscaping includes removal of existing bollards, installation of new decorative fence with decorative chain, modification of a concrete block (CMU) wall, and placement of new decorative rock.
1.2.6. A pre-bid tour of the project sites shall be conducted to ensure that all prospective bidders have an opportunity to visit each site to properly gage the scope of work required. Two of the sites are in secured areas and are not available to prospective bidders without a Government escort. The pre-bid tour will be adequately announced and will only occur on the prescribed date. No separate or individual site visits will be allowed.
2. SCOPE OF WORK
2.1. This Statement of Work provides the framework for which the disassembly/demolition, removal, disposition/disposal, relocation, and installation of modular buildings, fences, and other features shall be accomplished. This Statement of Work provides for the restoration of the project site by removal of all accumulated trash and debris around the sites and repair of paved surfaces. Upon completion of the project the site will be left in a clean condition.
3. ADMINISTRATIVE INFORMATION
3.1. This part covers the basics of day to day operations and normal hours of work.
3.2. Place of Performance: The work to be performed under this contract will be performed at 7794 Folsom Dam Road, Folsom, CA 95630.
3.3. Period of Performance: The performance period for this will shall be 180 days. Project duration includes submittal of necessary paper work, mobilization, demolition, removal, disposal, demobilization, and final cleanup.
3.4. Recognized Holidays: Contractor is not required to perform on holidays. Contractor shall notify Government 72 hours prior to holiday weekend or holiday if not on a weekend if the Contractor intends to perform on-site work on and holiday weekend or holiday.
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
3.5. Hours of Operations: The Contractor is responsible for conducting business, between the hours of 7:00 am-5:00 pm Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Offeror shall, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
3.6. Definitions: The follow acronyms, terms, and wording will be used throughout this Statement of work.
Building 012 – Modular Building, 4 unit-wide, still within useful life Building 109 – Folsom Resource Building – Modular Building, 6 unit-wide, to removed Caltrans – California Department of Transportation CCAO – Central California Area Office CE – Construction Engineer CO – Contracting Officer COR – Contracting Officers Representative
New Modules – Building 012 when disassembled (may be used interchangeably) Offeror – Prime Contractor
OGR – Onsite Government Representative RSHS – Reclamation Safety and Health Standards Security Zone 1 – Administration Area Security Zone 1 Fence – Mostly six foot tall fence with three wire stringers in the area of work Security Zone 2 – Zone requiring higher security, guests must be escorted Security Zone 2 Fence – Eight foot tall fence with three wire stringers may or may not have razor wire
3.7. Interruption of Services Requests: The Central California Area Office requires 72 hours’ notice prior to any Contractor requested utility Interruption of Service (outage).
Schedule and coordinate all outage requests with the OGR.
3.7.1. No specific request for an outage will be considered unless COR has reasonable assurances that materials and equipment required for work will be on site and Contractor will be prepared to perform the work on the start date and during the period of time requested for the specific outage.
3.7.2. Government reserves right to schedule outages for any period during 24-hour day, any day of the week.
3.8. Post Award Conference: A post award conference will be held prior to commencement of work. The Contractor shall meet with the designated Bureau of Reclamation Field Engineer, Safety Manager, and Contracting Officer's Representative. The post award conference will provide the contractor an opportunity to discuss and outline both the safety and work plans, ask any questions relative to the project and to review the proposed time schedule.
3.9. Security: The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
3.9.1. All vehicles entering the worksite may be subject to search by onsite security forces (Sacramento County Sheriff’s Department).
3.9.2. The Contractor shall maintain a current and updated list of authorized persons, including subcontractors, and provide a copy to the Onsite Government Representative.
3.9.2.1. Submit RSN-1: List of Staff
3.9.2.1.1. Country of birth.
3.9.2.1.2. Country of citizenship.
3.9.2.1.3. Duration and frequency on site.
3.9.2.1.4. Company affiliation.
3.9.3. The Government will issue a durable Zone 2 Escorted Access badge to a limited number of Contractor supervisory employees for the duration of the onsite work.
3.9.3.1. Return Escorted Access badges to OGR at completion of contract.
3.9.4. The Government will issue a temporary security badge daily to each person authorized to enter site.
3.9.5. A valid Photo ID is required from each employee for Government issued temporary security badge and Escorted Access badge.
4. REQUIREMENTS: The Contractor’s schedule and plan of work may differ from the order of items described below except where specified.
4.1. Permit To Work
4.1.1. Submit RSN-2: Central California Area Office (CCAO) Permit to Work form in accordance with Part 6 - Submittals, 28 days prior to any on-site work activities (excluding site visits). The Contractor shall apply for and must be issued a CCAO Permit to Work prior to mobilization. The Permit to Work process is the Area Offices methodology of ensuring work at the local site is communicated to impacted personnel and is in compliance with Reclamation policies and procedures.
4.1.2. Permit to work will not be issued until all of the following Contractor submittals, listed in Section 6, have been received and approved by the Government:
4.1.2.1. Safety Plan (RSN-9).
4.1.2.2. Project Schedule (RSN-8).
4.1.2.3. Use of Site Plan (RSN-7).
4.1.2.4. Traffic Control Plan (RSN-17).
4.1.2.5. Compliance with Security Procedures Clause 1452.237-80.
4.1.3. The Contractor shall coordinate with the OGR to identify availability and requirements for issuance of Government keys to Contractor personnel, for obtaining access to Building 109 and Building 012. The Contractor shall assure that only approved workers and Government personnel and construction vehicles and equipment will enter through gates and have access to the jobsite.
4.2. Survey for Regulated Materials: Conduct survey for regulated materials with qualified inspectors. Coordinate access and provide security requirements to OGR 72 hours prior to inspection.
4.2.1. Develop abatement plan to meet all applicable regulations as required.
4.2.2. Submit RSN-3:
4.2.2.1. Report detailing any finding of regulated materials or statement of non-detection.
4.2.2.2. Abatement Plan for each identified regulated material based on final disposition (reuse, recycle demolition).
4.3. Building 109 (Resource Building): Disconnect utilities and prepare for reuse; conduct select demolition; store items to be reused on site; remove Building 109 and appurtenant features from site; and prepare utilities and site to receive new replacement building.
4.3.1. Determine if modular building will be relocated and reused or recycled/demolished and conduct activities consistent with final disposition.
4.3.1.1. Submit Disposition Plan, RSN-4:
4.3.1.1.1. State whether modules will be reused or recycled and disposed of at appropriate facility.
4.3.1.1.2. If modules are to be reused state location or storage site.
4.3.1.1.3. If modules are to be recycled and disposed of at
appropriate facility provide list of reuse, recycling, and disposal facilities and certifications.
4.3.2. Stairs, Ramps and Landings:
4.3.2.1. Disassemble stairs and landing on southwest and northeast sides of building when no longer required for access and deliver to Government.
4.3.2.2. Disassemble ramp and landings that extend from southwest side of building to southeast side of building when no longer required for access and deliver to Government.
4.3.2.3. Disassemble ramp on northeast side of building and provide new to access door on northwest side of Building 012 when installed.
Ramp to meet accessibility requirements; to extend to landing at door; to provided adequate clearance from electrical panel for access; stairs to extend from land toward electrical panel for maintenance access; remove unused portion of ramp; and install rails in accordance with life safety and accessibility codes.
Contractor may reuse components of existing ramp or provide new.
4.3.2.4. Save components that will be reused on site and dispose of other components in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.3.3. Concrete Foundations for Stairs, Ramps and Landings:
4.3.3.1. Demolish and dispose of concrete foundations for stairs and landing on southwest side of building in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.3.3.2. Demolish and dispose of concrete foundation for stairs and landing on northeast side of building in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.3.3.2.1. Protect concrete foundation for ramp on northeast
side of building.
4.3.3.3. Demolish and dispose of concrete foundations for ramp and landings that extend from southwest side of building to southeast side of building in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.3.3.4. Backfill and compact with aggregate road base to base of adjacent asphaltic concrete when compacted.
4.3.3.4.1. Caltrans Standard Specifications, Section 26, Aggregate Bases, Class 2 with 3/4-inch maximum grading.
4.3.3.5. Cover with asphaltic concrete to match adjacent asphaltic concrete.
4.3.3.5.1. Aggregate: Caltrans Standard Specifications, Section
39, Type A, 3/4-inch, medium grading.
4.3.3.5.2. Asphalt binder, Caltrans Standard Specifications, Section 92 Viscosity Grade AR 4000.
4.3.3.5.3. Asphalt Concrete: 5 to 7 percent of asphaltic concrete by weight of dry aggregate.
4.3.4. Disconnect modules from metal roof structure covering adjacent walkway.
4.3.5. Disassemble and remove Building 109 from site.
4.3.5.1. Disconnect utilities (Power, water, and sanitary sewer) to facilitate removal of building 109 and installation of building 012.
Government to disconnect telephone and data, and coil wire back to closest stub.
4.3.5.1.1. Temporarily cap water and sewer lines. Secure
powerline to prevent electrical hazard.
4.3.5.2. Disconnect seismic anchors. Remove or grind flat any part of anchoring system that will not be reused.
4.3.5.3. Stack and reuse existing cribbing if needed for Building 012.
4.3.5.4. Prepare each module for transport.
4.3.5.5. Provide OGR 72 hours of notice prior to removing modules to arrange for security.
4.3.5.6. Remove buildings and appurtenant features that will not be reused from site for final disposition.
4.3.5.7. Conduct preparatory work to receive Building 012.
4.4. Remove and Salvage Security Zone 1 Fence: Remove fence shown on drawing 485- 218-3660. Fence is approximately 600 linear feet long, 6 foot and 8 foot high, with three strands of barbed wire (see Drawing 40-D-2201 for existing fence details.
Confirm conditions in field during site walk with OGR).
4.4.1. Barbed and razor wire.
4.4.1.1. Dispose of barbed and razor wire in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.4.2. Fence hardware.
4.4.2.1. Remove fence hardware and barbed wire arms and deliver to
Government in wood crates with hinged lids sufficiently sized to hold weight of contents. Compartmentalize crates to keep components organized. Manufactured from ¾ inch thick exterior grade plywood with block-pallet base.)
4.4.2.2. Clearly label contents of box on a long side and adjacent short side.
4.4.3. Remove fence wire mesh fabric.
4.4.3.1. Roll fence and center on pallet for transport by forklift.
4.4.3.2. Secure to pallet with steel strapping.
4.4.4. Fence posts.
4.4.4.1. Remove post and footing and backfill with aggregate base and compact.
4.4.4.1.1. Caltrans Standard Specifications, Section 26, Aggregate Bases, Class 2 with 3/4-inch maximum grading.
4.4.4.2. For posts in asphaltic concrete, remove post and footing and cap posthole with hot mix asphalt concrete.
4.4.4.2.1. Transport, spread, and compact HMA in accordance
with Caltrans Standard Specifications Section 39- 1.11.
4.4.4.3. Dispose of cut posts in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.4.4.4. Center top posts and intermittent rails on pallet for transport by forklift.
4.4.4.5. Secure posts in bundles with steel strapping.
4.4.4.6. Secure to pallet with steel strapping.
4.4.4.7. Gates.
4.4.4.8. Remove and reuse gates at locations shown on drawing 485-218-
3660. Deliver unused gates to Government.
4.5. Remove Wood Post and One Strand Pipe Barrier:
4.5.1. Remove and dispose of pipe in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.5.2. Remove and dispose of posts in accordance with Part 5.2, Reuse, Recycle, and Demolition.
4.5.3. Backfill and compact post holes with suitable fill approved by OGR.
4.6. Install Security Zone 2 Fence: Install approximately 600 linear feet of 8 foot high wire mesh, topped with 3 strands of barbed wire, Security Zone 2 Fence in accordance with fence details on Drawing 859-208-2201 along alignment depicted on drawing 485-218- 3661.
4.6.1. Section Includes:
4.6.1.1. Fence framework, fabric, and accessories.
4.6.1.2. Excavation for post bases; concrete foundation for posts.
4.6.1.3. Manual gates and related hardware.
4.6.1.4. Barbed wire.
4.6.2. Overall Fence Height: 9 feet total.
4.6.2.1. Fabric height, 8 feet with 12 inches of three strands of barbed wire installed on a barb arm.
4.6.2.2. Barbed wire top: 3 strands of twisted 12.5 gauge galvanized steel for strand wire. 14 gauge galvanized steel for barbs. Barbs shall be 4 inch ± on centers.
4.6.3. Line Post-Spacing: At intervals not exceeding 10 feet.
4.6.4. Fence Post and Rail Strength: Posts will be Schedule 40 steel. Diameter as described further in these specifications and on drawings.
4.6.5. Post Footings: Depth and width as described further in these specifications and on drawings.
4.6.6. Qualifications:
4.6.6.1. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years’ experience.
4.6.6.2. Installer: Company specializing in performing work of this section with minimum three years’ experience.
4.6.7. Delivery, Storage And Handling:
4.6.7.1. Deliver fence fabric and accessories in packed cartons or firmly tied rolls.
4.6.7.2. Identify each package with manufacturer's name.
4.6.7.3. Store fence fabric and accessories in secure and dry place as recommended by the manufacturer.
4.6.8. Manufacturers:
4.6.8.1. Anchor Fence Inc. or approved equal, specializing in manufacturing the products with the minimum salient characteristics specified in the sections below.
4.6.8.2. Cyclone Inc. or approved equal, specializing in manufacturing the products with the minimum salient characteristics specified in the sections below.
4.6.9. Materials:
4.6.9.1. Submit RSN-5:
4.6.9.1.1. Product data for fabric, posts, accessories, fittings, and hardware in accordance with Section 6 – Submittals.
4.6.9.2. Framing (Steel): Schedule 40.
4.6.9.3. Fabric Wire (Steel): ASTM A392 zinc coated wire fabric.
4.6.9.4. Barbed Wire: ASTM A121 galvanized steel; 12.5 gauge, 0.80 oz./ft2 zinc coating for strand wires; 14 gauge, 0.65 oz./ft2 zinc coating for barbs; 3 strands; barbs shall be 4 points and spaced at 4 inch ± on centers.
4.6.9.5. Concrete: ASTM C94/C94M, Type II Portland Cement, minimum 5 sacks of cement per cubic yard of concrete yielding a minimum of 2,500 psi strength at 28 days, 3 inch slump ± one inch, minimum ½ inch nominal sized coarse aggregate.
4.6.10. Components:
4.6.10.1. Intermediate Posts (Line Posts): 2.375 inches (60 mm) Outside
Diameter (O.D.) Schedule 40, 11 feet long with hardware to attach barbed wire (3 strands).
4.6.10.2. Terminal Posts (Corner Posts, End Posts, and Pull Posts): 2.875 inches (73 min) O.D. Schedule 40, 12 feet long with hardware to attach barbed wire (3 strands).
4.6.10.2.1. For pull posts, install pull posts at the end of each run, at maximum intervals of 500 feet, and at horizontal and vertical changes in alignment greater than 30 degrees.
4.6.10.3. Gate Posts:
4.6.10.3.1. Gate posts shall be schedule 40 galvanized steel pipe per ASTM F1083-08, Regular Grade. Gate Post Outside Diameters (O.D.) and lengths are as follows:
4.6.10.3.1.1. For 42-inch wide walk-through gate:
2.875 inches (73 mm) O.D., 12 feet long with hardware to attach barbed wire (3 strands).
4.6.10.3.1.2. For 16-foot wide and for 20-foot wide
double swing gates: 4.000 inches (102
mm) O.D., 12 feet long with hardware to attach barbed wire (3 strands).
4.6.10.4. Brace Rail: 1.625 inch O.D. steel pipe, plain end, sleeve coupled.
4.6.10.5. Gate Frame: 1.90 inch O.D. Schedule 40 steel pipe, welded fabrication.
4.6.10.5.1. Fabric Size: 8 foot high, 2 inch diamond woven wire mesh, 9 gauge thick, top selvage twisted tight (barb), bottom selvage knuckle end closed.
4.6.10.6. Truss Rod: Minimum 3/8 inch diameter.
4.6.10.7. Tension Wire: 6 gauge thick steel, single strand.
4.6.10.8. Tension Band: Minimum 1/8 inch x 3/4 inch, 12 inch maximum spacing and within 4 inches from top and bottom of fence fabric.
4.6.10.9. Tension Strap: Minimum 1/4 inch x 3/4 inch steel flat bar.
4.6.10.10. Tie Wire: As specified on drawings, 9 gauge, 18 inch maximum spacing on gates and 14 gauge, 14 inch maximum spacing on fence.
4.6.11. Accessories:
4.6.11.1. Caps: Cast steel galvanized; sized to post diameter, set screw retainer.
4.6.11.2. Fittings: Sleeves, bands, clips, rail ends, tension bars, fasteners and fittings; galvanized steel.
4.6.11.3. Extension Arms (Barb Arms): Cast steel galvanized, to accommodate 3 strands of barbed wire; single sloped to 45 degrees, or vertical arm.
4.6.11.4. Gate Hardware: Fork latch with gravity drop; center gate stop and drop rod; mechanical keepers; two 180 degree gate hinges for each leaf and hardware for padlock.
4.6.12. Gates:
4.6.12.1. Gate Types, Opening Widths and Directions of Operation: As directed by COR or as indicated in specifications or on drawings.
4.6.12.2. Reuse gates salvaged from Zone 1 fence demolition.
4.6.12.3. Swing Gates:
4.6.12.3.1. Fabricate gates to permit 180 degree swing.
4.6.13. Finishes:
4.6.13.1. Components, Hardware and Fabric: Galvanized to ASTM
Al23/A123M-09 for components; ASTM A153/AIS3M for hardware; ASTM A392 for fabric; 2.0 oz./ft2 coating.
4.6.13.2. Accessories: Same finish as framing.
4.6.14. Installation:
4.6.14.1. Install framework, fabric, accessories and gates in accordance with ASTM F567, as specified on drawings, and as specified by COR.
4.6.14.2. Set intermediate, terminal, and gate posts plumb, in concrete footings with top of footing 2 inches above finish grade. Slope top of concrete for water runoff.
4.6.14.3. Line Post Footing Depth Below Finish Grade: as specified on drawings.
4.6.14.4. Corner, Gate and Terminal Post Footing Depth Below Finish Grade: as specified on drawings.
4.6.14.5. For fencing installed in soil, loose rock, or concrete, brace each gate, corner, end, and pull post to adjacent line post with horizontal brace rail and diagonal truss rods. Install brace rail and truss rod one bay from gate, corner, end, and pull posts as shown on drawing 859-208-2201.
4.6.14.6. Install top tension wire through line post top stretched taut between terminal posts.
4.6.14.7. Install brace rail on corner gate leaves, for fencing installed in soil, loose rock, or concrete.
4.6.14.8. Place fabric on outside of posts and rails as directed by COR.
4.6.14.9. Stretch fabric between terminal posts or at intervals of 100 feet maximum, whichever is less.
4.6.14.10. Position bottom of fabric 2 inches above finished grade.
4.6.14.11. Fasten fabric to top tension wire, line posts, braces, and bottom tension wire with tie wire at maximum 15 inches on centers.
4.6.14.12. Attach fabric to end, corner, gate, and pull posts with tension bars and tension bar clips.
4.6.14.13. Install bottom tension wire stretched taut between terminal posts.
4.6.14.14. Install barbed wire support arms and attach barbed wire.
4.6.14.15. Support gates from gate posts. Do not attach hinged side of gate from building wall.
4.6.14.16. Install gate with fabric and barbed wire overhang to match fence.
Install three hinges on each gate leaf, latch, catches, drop bolt, foot bolts and sockets, torsion spring retainer, and or retainer and locking clamp (to be specified by COR).
4.6.14.17. Provide concrete center drop to footing depth and drop rod retainers at center of double gate openings when called for by
COR.
4.6.14.18. Connect to existing fence at existing terminal post, new terminal post or existing line post converted to terminal post by installation of brace rails and brace rods.
4.6.14.19. Install posts with 4 inches maximum clear opening from end posts to buildings, fences and other structures.
4.6.14.20. Excavate holes for posts to diameter and spacing indicated on drawings without disturbing adjacent materials.
4.6.14.21. Center and align posts. Place concrete around posts, and vibrate or tamp for consolidation. Verify vertical and top alignment of posts and make necessary corrections.
4.6.14.22. Extend concrete footings 2 inches above grade, and trowel, forming crown to shed water.
4.6.14.23. Allow footings to cure minimum 7 days before installing fabric and other materials attached to posts.
4.6.15. Erection Tolerances:
4.6.15.1. Maximum Variation From Plumb: 1/8 inch.
4.6.15.2. Maximum Offset From Indicated Position: 1 inch.
4.6.16. In lieu of top rail shown on Standard Drawing 40-D-7017, Contractor shall furnish and install top tension wire instead, in accordance with the requirements of these specifications. Additionally, although not shown on Standard Drawing 40-D-7017, for fencing installed in concrete, Contractor shall brace each gate, corner, end, and pull post to adjacent line post with horizontal brace rail and diagonal truss rods, in accordance with drawing 859-208-2201.
4.6.17. Install posts in concrete per Standard Drawing 40-D-7017.
4.6.18. Reuse posts installed around motorized road gate and extend posts to accommodate new 8 foot chain link fabric and barbed wire arms.
4.6.19. Install opening for single pedestrian gate currently located near Building 110.
Location on drawing 485-218-3660 is approximate. Confirm gate and new location in field with OGR.
4.6.20. Install opening for single half of double swing gate currently located near Building 110 over in ground utility vault. Location on drawing 485-218-3660 is approximate. Confirm existing gate and new location in field with OGR. Intent is to be able to open gate when maintenance is required in utility box.
4.6.21. Install opening for single half of double swing gate currently located near Building 110 near drainage basin. Location on drawing 485-218-3660 is approximate. Confirm existing gate and new location in field with OGR. Intent is to be able to open gate when maintenance is required at drainage basin.
4.6.22. When fence is installed from road gate to tie in point at Building 206 and gate sites are ready to receive gates, notify OGR of request for inspection.
4.6.22.1. Provide OGR with 72 hour notice to coordinate Fence Acceptance Inspection with CCAO Security and to coordinate security for the relocations of the gates.
4.6.22.2. Make any corrective actions determined as required during Fence Acceptance Inspection before relocation of gates.
4.6.22.3. Have OGR inspect and accept changes.
4.6.23. Dispose of earth materials generated from construction work off site or at onsite location within 1 mile of fence work as approved by OGR.
4.6.24. Fence materials specified may be non-standard and may not be readily available in California. Additional time has been added to the contract duration to account for the fence material lead time. Fence material lead times shall not impact modular disassembly, removal and relocation, which is to be conducted promptly upon approval of required submittals.
4.7. Security Zone 2 Gate Relocations: Upon preliminary acceptance of the Security Zone 2 fence and after coordination with security, relocate the gates from existing Security Zone 2 fence to new Security Zone Fence 2 at locations describe above.
4.7.1. Plan work so all activities associated with gate relocation can be completed in one shift.
4.7.2. Openings in fence will require continuous monitoring until new fence installation is complete.
4.7.3. Government to provide locks to secure all gates.
4.7.4. Notify OGR upon completion for Acceptance Inspection.
4.7.5. Make any corrective actions determined as required during Acceptance
Inspection before end of shift to assure perimeter security of Security Zone 2 is maintained.
4.8. Remove and Salvage Zone 2 Fence: Repeat process described above in Part 4.4 above for fence identified Drawing 485-218-3660.
4.8.1. Be cognizant that buildings adjacent to fence removal work are occupied office buildings. Attempt to reduce noise when practical.
4.9. Modify CMU Block Wall: Demolish approximately 80 linear feet of 7 foot high CMU block wall with barbed wire after final acceptance of Security Zone 2 fence.
4.9.1. Protect bottom three rows of block wall for 40 foot length as shown on drawing
485-218-3660. Coordinate removal layout with OGR in field.
4.9.2. Demolish and dispose of wall in accordance with Section 5.2, Reuse, Recycle, and Demolition.
4.9.3. Backfill and compact with aggregate road base to base of adjacent asphaltic concrete when compacted.
4.9.3.1. Caltrans Standard Specifications, Section 26, Aggregate Bases, Class 2 with 3/4-inch maximum grading.
4.9.4. Cover with asphaltic concrete to match adjacent asphaltic concrete.
4.9.4.1. Aggregate: Caltrans Standard Specifications, Section 39, Type A, 3/4-inch, medium grading.
4.9.4.2. Asphalt binder, Caltrans Standard Specifications, Section 92 Viscosity Grade AR 4000.
4.9.4.3. Asphalt Concrete: 5 to 7 percent of asphaltic concrete by weight of dry aggregate.
4.9.5. Construct new section of CMU block wall along alignment shown on drawing 485-218-3661. Coordinate installation layout with OGR in field.
4.9.5.1. Field fit and finish ends of wall with Government furnished CMU blocks.
4.9.5.2. Construct minimum 12 inch W x 12 inch D reinforced concrete footing for new section.
4.9.5.2.1. Concrete: ASTM C94/C94M, Type II Portland
Cement, minimum 5 sacks of cement per cubic yard of concrete yielding a minimum of 2,500 psi strength at 28 days, 3 inch slump ± one inch, minimum 1/2 inch nominal sized coarse aggregate.
4.9.5.2.2. Reinforcement: One #4 reinforcing steel bar, centered.
4.9.5.2.3. Match height to existing wall remaining.
4.9.5.2.4. Fill CMU block cells with grout.
4.9.5.2.5. Contractor to provide and install 10 inch decorative cap to close match existing block color.
4.9.5.2.6. Submit RSN-6:
4.9.5.2.6.1. Submit a minimum of two examples of
decorative block wall cap manufacturer’s data with photograph or detailed drawing.
4.10. Decorative Fence: Install decorative fence posts on 6 foot centers as shown on drawing 485-218-3661.
4.10.1. Embed fence posts in concrete, in ground, in accordance with Note 4 for corner fence posts as shown on drawing 859-208-2201.
4.10.1.1. Dispose of earth materials generated for digging post holes off site or at onsite location within 1 mile of fence work as approved by
OGR.
4.10.2. Install Decorative Chain.
4.10.2.1. 3/16” stainless steel with mounting eyes.
4.10.3. Submit RSN-6:
4.10.3.1. Proposals for decorative fence and chain.
4.10.3.1.1. Submit a minimum of two examples of decorative
fence and chain manufacturer’s data with photograph or detailed drawing.
4.11. Building 012 (Resource Building Replacement): Disconnect utilities, remove electrical service to closest safe point of termination, cap water line, cap sewer line; disassemble modules and disconnect utilities between modules; store items to be reused on site;
relocate to former site of Building 109; reconnect utilities; install stairs, ramps and landings; connect building to walkway cover; install skirting; repair roof and exterior wall seems; repair interior floor, wall and ceiling; repair damage caused by move; test utilities; and dispose of excess materials and waste in accordance with Section 5.2, Reuse, Recycle, and Demolition.
4.11.1. Disassemble stairs, ramps, landings, and store items to be used at new location contractors use area for reuse, dispose of excess materials and waste in accordance with Section 5.2, Reuse, Recycle, and Demolition.
4.11.2. Remove building skirting and fascia boards and store items to be used at new location at contractors use area for reuse, dispose of excess materials and waste in accordance with Section 5.2, Reuse, Recycle, and Demolition.
4.11.3. Disconnect utilities (power, water, and sanitary sewer) to facilitate relocation of Building 012. Government to disconnect telephone and data, and coil wire back to closest stub.
4.11.3.1. Cap water and sewer lines minimum 18 inches above ground and attach to new 4 inch x 4 inch wood post marker to allow for future connections.
4.11.3.2. Disconnect power at breakers in box adjacent to building and secure openings to box prevent electrical hazard.
4.11.3.3. Disconnect seismic anchors; salvage parts for reuse where practical; and dispose of excess materials and waste in accordance with Section 5.2, Reuse, Recycle, and Demolition.
4.11.4. Disassemble Building 012 modules. Attempt to preserve as much of each module intact as possible. All water and sewer are located in one module.
Drawings show power, telephone, and data connect between modules via plugs. Exercise care during disassembly until conditions are confirmed.
4.11.5. Protect interior of modules when disassembled from rain, dust, and other environmental factors.
4.11.6. Prepare each module for transport.
4.11.7. Provide OGR 72 hours of notice prior to moving modules.
4.11.8. Relocate modules and appurtenant features to be reused to new site. Remove items that will not be reused from site for final disposition.
4.11.9. Carefully move first module into place against electrical service box and covered walkway to the best extend possible.
4.11.10. Reconnect inner wall utility connections and perform continuity tests on all electric outlets, telephone outlets, and data ports while reconnecting remaining modules, and appurtenant features and supports.
4.11.10.1. Connect modules to metal roof structure covering adjacent walkway.
4.11.11. Install seismic anchoring.
4.11.12. Re-establish utilities.
4.11.13. Repair roof.
4.11.14. Place wall fascia. Replace if not reusable.
4.11.15. Repair interior walls, floors, and ceilings. Repair and tape sheetrock wall as required to repair damage from disassembly. Finish wall texture to match existing. Match existing floor and ceiling tiles. Repaint walls to match existing interior color or as approved by OGR.
4.11.16. Install skirting.
4.11.17. Install new underfloor access hatches.
4.11.17.1. Quantity, size, and spacing per International Building Code.
4.11.18. Install stairs, main ramp, and landing. Install reconfigured ramp and stairs adjacent to covered walkway.
4.11.19. Notify OGR upon completion for Acceptance Inspection.
4.11.19.1. Make any corrective actions determined as required during Acceptance Inspection.
4.11.19.2. Notify OGR upon completion of repairs for Acceptance Inspection.
4.12. Landscaping:
4.12.1. Provide and install 3 inch minus decorative river rock, 12 inches thick in landscaped area of new CMU block wall.
4.12.1.1. Provide three different physical samples to COR for approval.
4.12.2. Provide and install 140N non-woven geotextile, manufactured by Mirafi, www.tencate.com, or equal with the following essential characteristics:
4.12.2.1. Grab Tensile Strength (ASTM D 4632): 120 lbs.
4.12.2.2. Elongation (ASTM D 4632): 50%
4.12.2.3. Puncture Strength (ASTM D 6241): 328 lbs.
4.12.2.4. Apparent Opening Size (ASTM D 4751): 70 US Sieve size
4.13. Site Cleanup:
4.13.1. Vacuum sweep all Contractor Use Areas and haul roads and wash paved work areas with water truck.
4.14. Final Acceptance Inspection of All Items: Provide OGR 72 hours of notification upon completion of all activities for Final Acceptance Inspection.
4.14.1. Make any corrective actions determined as required during Final Acceptance
Inspection.
4.14.2. Final Inspection may uncover items not discovered during previous inspections.
Contractor shall make repairs to all pertinent items upon discovery.
4.14.3. Notify OGR upon completion of repairs for Punch List Acceptance Inspection.
5. GENERAL REQUIREMENTS
5.1. Work shall be performed within the authorities of the Reclamation Act of 1902 (32 Stat. 388, 43 USC 391), National Environment Policy Act of 1969 (PL91-90), as amended; and other applicable agency and Department of the Interior policies. Policies and regulations will be provided to the contractor by the Bureau of Reclamation upon request. The Contractor shall conduct work in accordance with all local, state and Federal regulations relative to this project.
5.2. Reuse, Recycle, and Demolition: The Contractor is strongly encouraged to reuse the modules or part of the modules first then, to the maximum extent practicable, recycle all metal, building materials, concrete and any other debris before disposal at a certified land fill.
http://www.tencate.com/
5.3. Landscape Preservation: The Contractor shall exercise care to preserve the natural landscape and shall conduct the operation so as to prevent any unnecessary destruction, scarring, or defacing of the surroundings in the vicinity of the work site. Demolish and remove from the site all vegetation and any other enhancements or improvements associated with the buildings required for this work.
5.3.1. The Contractor is responsible for injuries to vegetation caused by Contractor operations, personnel, or equipment. Repair or treat injured vegetation as directed by the COR.
5.4. Cleanup and Disposal of Waste Material: The Contractor shall be responsible for all waste materials or rubbish generated by their work. Debris shall be removed from the work site and taken to an authorized disposal site. The disposal of waste materials and rubbish shall be in accordance with this paragraph and all applicable Federal, State, and local regulations, standards, codes and laws. Also, the requirements contained in the Reclamation Safety and Health Standards (RSHS) are applicable to clean up and to dispose of waste materials and rubbish. In the event that there is a conflict between the requirements contained in this paragraph, the RSHS, and other Federal, State, or local regulations, standards, codes, and laws, the more stringent requirements having jurisdiction shall prevail.
5.5. Use of Site:
5.5.1. Government land as shown on drawings may be used for required construction facilities.
5.5.2. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
5.5.3. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
5.5.4. Housing for construction personnel will not be permitted on Government land.
5.6. Construction Program:
5.6.1. Develop, maintain, and use approved Construction Schedule to plan, monitor, and evaluate accomplishment of work.
5.6.2. Failure to include any element of the work will not release Contractor from completing all required work under the contract.
5.6.3. Construction Schedule shall include:
5.6.3.1. Progress chart of suitable scale to indicate percentage of work scheduled for completion by any date.
5.6.3.2. Prepare schedule based on required sequence and interdependence of activities.
5.6.3.3. Include work of subcontractors, Government interfaces, and contract milestones.
5.6.3.4. Include contract title, contract number, and Contractor's name on each sheet.
5.6.4. Baseline Schedule Requirement:
5.6.4.1. Represents Contractor’s as-planned approach to accomplishing the work.
5.6.4.2. Include planned start and completion dates for features of work.
5.6.5. Updated Schedule:
5.6.5.1. Use actual dates.
5.6.5.2. Enter actual progress.
5.6.6. If in the opinion of the CO, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO.
5.6.7. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contacting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
5.6.8. Costs for actions required to improve progress will the responsibility of the Contractor.
5.6.9. The Contractor shall be required to submit a time impact evaluation within 30 days of any change order or delay, showing effects…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .