Solicitation_No._R16PS00663.pdf
PDF 6 MB Posted
- Attached to
- Lake Woolomes Recreation Area Asphalt Replacement Federal contract opportunity
- Solicitation number
- R16PS00663
About this file
Solicitation No. R16PS00663 - Lake Woolomes Recreation Area Asphalt Replacement
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| R16PS00663_-_Amendment_No._003.pdf | ||
| R16PS00663_-_Amendment_No._002.pdf | ||
| R16PS00663_-_Amendment_No._001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado FEBRUARY 2016
Solicitation No. R16PS00663
Lake Woolomes Recreation Area Asphalt Replacement
Central Valley Project, California
R16PS00663 – Lake Woolomes Recreation Area Asphalt Replacement
TABLE OF CONTENTS
SECTION A - Solicitation, Offer and Award Form (SF 1442)
SECTION B - Pricing Schedule
SECTION C - Specifications/Appendices
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
SECTION F - Deliveries or Performance
SECTION G - Contract Administration Data
SECTION H - Special Contract Requirements
SECTION I - Contract Clauses
SECTION J - List of Documents, Exhibits, and Other Attachments
SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION L - Instructions, Conditions and Notices to Offerors
SECTION M - Evaluation Factors for Award
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Bureau of Reclamation - MP Regional Office
Attn: Matthew T. Byrne, Contracting Officer 2800 Cottage Way, Rm. E-1815, Federal Bldg.
Sacramento, California 95825-1898
Matthew Byrne 916-978-5126 x
05/16/2016
R16PS00663
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A. Title: Lake Woolomes Recreation Area Asphalt Replacement
B. Work Site Location: Work is located approximately 2 miles west of Jasmin, CA in
Kern County.
C. Site Visit Information: See Section L, FAR 52.236-27, Site Visit (Construction) -
Alt. 1
D. Estimated Price Range: The estimated cost of this project is between $100,000.00 and $250,000.00
E. Set-Aside Information: This requirement is restricted to Total Small Business concerns using NAICS 237310 and applicable size standard of $36.5 million. FAR
Clause 52.219-06, "Notice of Total Small Business Set Aside" applies to this requirement.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 120 calendar days and complete it within ________________ ________________ calendar days after receiving
06/28/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Matthew T. Byrne
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R16PS00663
Legacy Doc #: BOR
FOB: Destination
Section B - Supplies or Services and Prices
"AU" - Activity Unit is used solely for the purposes of allowing progress payments under the
Department of Interior's Financial & Business
Management System (FBMS).
00010 R16PS00663 - Lake Woolomes Recreaction Area 1 AU
Asphalt Replacement
Price Schedule - CLINs 1-3
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
MADERA CANAL HEADWORKS LOW-FLOW CONVEYANCE
CENTRAL VALLEY PROJECT
FRIANT DIVISION
B.1 PRICE SCHEDULES
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number.
SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 WBR
1452.232
-81
Mobilization and Preparatory Work
For the lump sum of $
2 32 01 13 Screenings 570 Ton $ $
3 32 01 13 Excavation 70 Ton $ $
TOTAL FOR PRICE SCHEDULE $______________________________________________
END OF SUPPLIES OR SERVICES AND PRICES/COSTS
Price Schedule
B - 2
This page intentionally left blank.
Lake Woollomes Recreation Area Asphalt Replacement Central Valley Project, California Solicitation No.
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 31 19 Project Management and Coordination 01 32 10 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 13 Double Seal Coat
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
Table of Contents
00 01 10 - 2
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located approximately 2 miles west of Jasmin, California, in Kern County.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Preparation for and placing Double Seal Coat:
1. Includes:
a. Removing and stockpiling concrete wheel stops onsite.
b. Sweeping and vacuuming existing concrete asphalt surface to receive double seal coat.
c. Place double seal coat.
d. Resetting concrete wheel stops.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CE: Construction Engineer
2. CO: Contracting Officer.
3. COR: Contracting Officer’s Representative.
4. OGR: Onsite Government Representative
Summary of Work
01 11 00 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. Reclamation Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220- 07-05) 2012 Edition Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use area on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and access trails.
3) Areas for processing, storing, and disposing of waste materials from construction operations.
4) Utilities including air, power, and water lines; fire hydrants; and compressor station.
5) First-aid facilities.
6) Temporary fences.
b. Describe methods to preserve, protect, and repair if damaged trees, shrubs, grass, and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with the work required under
01 14 10 - 2 this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to be used to prevent introduction of noxious weeds and invasive species.
d. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
e. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of land made during construction after use of land is in operation.
1.04 PROJECT CONDITIONS
A. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
B. Construction limits are three feet from edge of excavation or backfill unless otherwise indicated on drawings or approved by OGR.
C. Approximate limits and location of Contractor Use Areas are shown on the drawings.
D. Location, construction, operation, maintenance, and removal of construction facilities on Government-controlled land will be subject to approval of OGR.
E. Existing access roads may be used in accordance with Section 01 55 00 - Vehicular Access and Parking.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction Equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.
01 14 10 - 3
3. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.
3.02 RESTORATION
A. Perform final grading, restoration and other conditions for areas used for disposal of excess excavated materials in accordance with Section 01 74 00 - Clean and Waste Management.
B. Restore Contractor use areas to pre-construction condition.
01 14 10 - 4
Project Management and Coordination
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html.
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals.
B. RSN 01 31 19-1, Pre-Construction Meeting Notification:
1. Provide confirmation to COR regarding requested date and time of meeting and indicate who will be attending and affiliations.
C. RSN 01 31 19-2, Construction Progress Review Meetings Notification:
1. Provide confirmation to COR regarding requested date and time of meeting and indicate who will be attending and affiliations.
1.04 PROJECT COORDINATION
A. Contractor Safety Program Review: See RSHS Section 3 for requirements.
B. This meeting will take place in conjunction with the pre-construction meeting.
1. Pre-Construction Meeting:
a. Date: No later than 45 days after receipt of Notice to Proceed and prior to performing work on the required RSNs.
b. Location: To be Determined by COR.
c. Provide following preliminary information at meeting:
1) Proposed schedule.
2. Construction Progress Review Meetings:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
Project Management and Coordination
01 31 19 - 2
a. Required if deemed necessary by COR. Location to be determined by
COR.
1) Contractor and subcontractor representatives not onsite may participate in meeting via telephone conference.
b. Purpose:
1) Review with Government personnel construction progress.
2) Schedule, Progress, and Coordination:
a) Review safety, progress made, schedule, project issues, submittals, Request for Information (RFI), and resolution necessary to meet specifications requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Construction Program
01 32 20 - 1
SECTION 01 32 20
CONSTRUCTION PROGRAM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Developing Baseline Schedule: Include in lump sum price offered in the Price Schedule for mobilization and preparatory work.
2. Updating and Using Construction Program: Include as an element of Contractor’s overhead.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 32 20-1, Baseline Schedule:
1. Bar chart for project using actual Notice to Proceed date.
2. May be prepared using Microsoft Excel.
C. RSN 01 32 20-2, Updated Schedule:
1. Bar chart for project.
2. Submit with each request for payment.
1.03 SCHEDULE
A. Develop, maintain, and use approved Construction Schedule to plan, monitor, and evaluate accomplishment of work.
B. Failure to include any element of the work will not release Contractor from completing all required work under the Contract.
C. Construction Schedule:
1. Progress chart of suitable scale to indicate percentage of work scheduled for completion by any date.
2. Prepare schedule based on required sequence and interdependence of activities.
3. Include work of subcontractors, Government interfaces, and contract milestones.
4. Include contract title, contract number, and Contractor's name on each sheet.
D. Baseline Schedule:
01 32 20 - 2
1. Represents Contractor’s as-planned approach to accomplishing the work.
2. Include planned start and completion dates for features of work.
E. Updated Schedule:
1. Use actual dates.
2. Enter actual progress.
F. If in the opinion of the CO, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO.
1. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contacting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
2. Costs for actions required to improve progress will the responsibility of the Contractor.
G. The Contractor shall be required to submit a time impact evaluation within 30 days of any change order or delay, showing affects of the change order or delay on the progress schedule.
H. Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.
I. Float is not for the exclusive use by or benefit of either the Government or the Contractor.
1.04 FAILURE TO COMPLY
A. Failure to comply with the requirements of this section shall be grounds for a determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time. The CO may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 32 20 - 3
01 32 20 - 4
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work except as provided.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-2005(2012) Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-2011 United States National CAD Standards, Version 5
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Administrative Notice to Proceed: Issued to allow Contractor to Proceed with RSN preparation and submittal, see the clause at FAR 52.211-10, Commencement, Prosecution, and Completion of Work and Section H.10 Intermediate Milestones and Limitations.
D. Notice to Proceed: Issued to allow start of onsite construction work, see the clause at FAR 52.211-10, Commencement, Prosecution, and Completion of Work and Section H.10 Intermediate Milestones and Limitations.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
01 33 00 - 2
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Print Size: D size (22 inches by 34 inches).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.
5. Government Format Drawings:
a. Prepare drawings designated as “Government Format” in the specifications as follows:
1) Title block and sheet format:
a) As shown on standard drawing 40-D-7102.
b) Government will provide specific title block information to be used.
2) Drawing format:
a) AutoCAD, Version 2012.
b) In accordance with NIBS NCS.
3) Size: D-size (22-inch by 34-inch) as defined by ASME Y14.1.
4) Government will provide an electronic AutoCAD template.
6. Final Drawings:
a. Drawing format: AutoCAD, Version 2012.
b. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
c. Electronic files: On CD or DVD discs.
d. Original plots: D size (22 inches by 34 inches).
e. Government will provide an electronic AutoCAD template.
D. Product Data:
01 33 00 - 3
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by a State of California registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe .pdf on CD or DVD discs.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.
D. Include the following information in transmittal letters.
01 33 00 - 4
1. Bureau of Reclamation contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved.
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.
1.06 GOVERNMENT REVIEW OF SUBMITTALS
A. Time Required:
1. Government will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval/acceptance was required under the contract, and
01 33 00 - 5
b. Requests for approval/acceptance were properly and timely submitted and were approved/accepted.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Return of Submittals:
1. With the exception of the following submittals: RSNs RSN 01 32 10-1, RSN 01 32 10-2, and RSN 01 35 20-1 the submittals will be returned, approved, conditionally approved, or not approved.
2. RSNs RSN 01 32 10-3, RSN 01 32 10-3, and RSN 01 35 20-1 will be returned, accepted, conditionally accepted, or not accepted.
3. One set of submittals required for action will be returned either approved, approved subject to identified changes, not approved, accepted, conditionally accepted, not accepted, or incomplete.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.
c.
1.07 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Construction Engineer, Bureau of Reclamation, MP Construction Office, Attn:
MPCO-100, P.O. Box 988, Willows, CA 95988-2615;
a. Express Mail: 1140 West Wood Street, Willows, CA 95988-2615.
2. Onsite Government Representative, address to be provided after Notice to Proceed.
3. Technical Service Center, Bureau of Reclamation, Attn: 86-68510, P.O. Box 25007, Denver, CO 80225-0007;
a. Express Mail: Sixth and Kipling, Building 67, Room 152, Denver, CO 80225-0007.
4. Project Manager, Bureau of Reclamation, Mid-Pacific Regional Office, Attn:
MP-200, 2800 Cottage Way, Sacramento, CA 95825.
Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A – List of Submittals.
01 33 00 - 6
B. Send copy of transmittal letter with appropriate number of sets to offices that are not the responsible code, but show “No. of sets to be sent to” in Table 01 33 00A – List of Submittals.
C. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.
D. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to CE, unless otherwise specified.
E. Facsimile and electronic transmissions of RSN’s are not acceptable, unless specifically approved by COR.
PART 2 PRODUCTS
Not Used
Table 01 33 00A - List of Submittals *R-Code indicates Responsible Code ** CE indicates Construction Engineer, OGR indicates Onsite Government Representative, and TSC indicates Technical Service Center.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
R- Code*
No. of sets to be sent to:**
CE OGR TSC
01 14 10-1 Use of Site Land Use and
Landscape Rehabilitation Plan
Within 21 days after receipt of Notice to Proceed
CE 4 1 0
01 31 19-1 Project Management and Coordination
Pre-Construction Meeting Notification
At least 14 days prior to meeting date
CE 2
1 0
01 31 19-2 Project Management and Coordination
Construction Progress Review Meeting Notification
At least 14 days prior to meeting date
CE 2 1 0
01 33 00 - 7
Table 01 33 00A - List of Submittals *R-Code indicates Responsible Code ** CE indicates Construction Engineer, OGR indicates Onsite Government Representative, and TSC indicates Technical Service Center.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
R- Code*
No. of sets to be sent to:**
CE OGR TSC
01 32 10-1 Construction
Program Baseline Schedule
1. Blackline prints
2. Reports
3. Data on CD-
ROM
Within 21 days after receipt of Notice to Proceed
CE
01 32 10-2 Construction Program
Updated Schedule
1. Blackline prints
2. Reports
3. Data on CD-
ROM
With monthly requests for progress payments.
CE
01 35 10-1 Safety Data Sheets
Complete LHM and SDS
At least 14 days before jobsite delivery of hazardous material
CE 2 1 0
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
CE 2 1 0
01 35 20-1 Safety and Health
Safety Program Within 21 days after receipt of Notice to Proceed
CE 4 1 0
01 35 20-2 Safety and Health
Monthly Accident Safety Reports
Monthly CE 4 1 0
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
Within 21 days after receipt of Notice to Proceed
CE 2 1 0
01 46 20-2 Testing Agency Services
Contractor Quality Testing Results
Within 7 days of completion of related testing
CE 2 1 0
01 55 00-1 Vehicle Access and Parking
Initial Digital Recording
At least 3 days prior to mobilization
CE 2 1 0
01 55 00-2 Vehicle Access and Parking
Post Construction Digital Recording
Within 7 days of completion of related construction
CE 2 1 0
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
Within 21 days after receipt of Notice to Proceed
CE 2 1 0
01 33 00 - 8
Table 01 33 00A - List of Submittals *R-Code indicates Responsible Code ** CE indicates Construction Engineer, OGR indicates Onsite Government Representative, and TSC indicates Technical Service Center.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
R- Code*
No. of sets to be sent to:**
CE OGR TSC
01 57 30-1 Water Pollution
Control Spill Prevention, Control, and Countermeasure (SPCC) Plan
Within 21 days after receipt of Notice to Proceed
CE 2 1 0
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Within 21 days after receipt of Notice to Proceed
CE 2 1 0
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of hazardous waste disposal
CE 2 1 0
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
Submitted and approved before start of associated onsite work
CE 1 1 0
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 28 days of completion of work
CE 2 1 0
32 01 13-1 Double Seal Coat
Certifications Within 21 days after receipt of Notice to Proceed
CE 2 1 2
Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials.
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.
1.03 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:
1. Materials delivered to Government.
2. Materials incorporated into work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.
Safety Data Sheets
01 35 10 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Prices Schedules for other items of work.
1.02 REFERENCES STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910 OSHA General Industry Standards
2. 29 CFR Part 1926 OSHA Construction Industry Regulations
3. Available online at: https://www.osha.gov/
C. Applicable State Safety and Health Regulations – CAL/OSHA
1. California Code of Regulations (CCR) Title 8
2. Available online at: https://www.dir.ca.gov/title8/index/T8index.asp
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 20-1, Safety Program:
1. Written Safety Program in accordance with Section 3 of the RSHS.
2. Cover all aspects of on site and applicable off site operations and activities associated with this contract.
3. Program must follow the format of the outline in Appendix B of Reclamation RSHS (included at end of this section).
4. Will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B, a narrative for each applicable item in the outline.
https://www.osha.gov/ https://www.dir.ca.gov/title8/index/T8index.asp
01 35 20 - 2
a. For items in the outline that do not apply to this contract write “Not Applicable to Contract” next to the number/letter.
5. Provide a list of Job Hazard Analyses (JHA) for all major or distinct phases of work that will be submitted throughout the project.
6. A generic Company Safety Plan is not acceptable. The Safety Program must be site specific for this contract.
7. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing on site work.
C. RSN 01 35 20-2, Monthly Accident Summary Report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
1.04 SAFETY AND HEALTH
A. Do not allow Contractor employees (including subcontractors), Government personnel, or the Public to be exposed to, or work under, conditions which are unsanitary, physically hazardous, or a potential exposure danger to their health or safety during performance of the contract.
B. Under no circumstances will onsite work, including mobilization, be permitted until the Safety Program has been accepted by the COR.
C. Fully participate in a Contractor Safety Program Review meeting, according to RSHS Section 3.4.1, prior to mobilization. If applicable, include subcontractor management representatives.
D. The minimum work crew at any time on the construction site shall consist of no less than two people and shall be in accordance with other contractual obligations.
E. Develop Job Hazard Analysis for each distinct phase of work under the contract.
1. Work shall not begin on the phase of work until a JHA is acceptable to OGR and shared with all construction employees.
2. Activities involving hazardous materials shall have the appropriate Safety Data Sheet(s) attached to the JHA.
F. In addition to requirements of the clause at FAR 52.236-13, Accident Prevention, fully comply with RSHS.
1. One copy of RSHS, in digital format, will be provided at no charge for use in connection with the specifications.
2. Construction Safety and Health Standards promulgated by the Secretary of Labor may be obtained from any regional or area office of the Occupational Safety and Health Administration of the U.S. Department of Labor.
01 35 20 - 3
G. Be cognizant of and ensure compliance with requirements set forth in paragraphs above.
1. Contractor’s responsibility applies to all operations, including those of the Contractor’s Subcontractors.
2. When violations of safety and health requirements contained in these specifications or referenced standards are called to the Contractor’s attention by the CO, COR or the OGR, immediately correct the condition to which attention has been directed.
3. Either oral or written notice shall be deemed sufficient.
H. When the Contractor fails or refuses to promptly correct a compliance directive, the CO or the COR may issue an order to stop all or any part of the work.
1. When satisfactory corrective action is taken, an order to resume work will be issued.
2. The Contractor shall not be entitled to extension of time, nor to claim for damage or to additional compensation by reason of either the directive or the stop order.
3. Failure of the CO, COR or the OGR to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
I. Maintain an accurate record of, and report to the COR in the manner prescribed by the CO for all near misses, accidents or incidents, occupational diseases, traumatic injury, cases of death to Contractor employees (including subcontractors), Government personnel, or the Public, and property damage occurring during the performance of work under this contract.
J. The rights and remedies of the Government provided in this section are in addition to any other rights and remedies provided by law or under this contract.
1. In the event there is a conflict between requirements contained in RSHS, specification paragraphs, Contractor’s approved Safety Program, referenced safety and health codes, and standards, or the U.S. Department of Labor Construction Safety and Health Standards, promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.), as amended, the more protective requirement having jurisdiction shall prevail.
PART 2 PRODUCTS
Not Used
01 35 20 - 4
Reference Standards
01 42 10 - 1
SECTION 01 42 10
REFERENCE STANDARDS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.
B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.
1.03 JOBSITE REFERENCE STANDARDS
A. Maintain at fabrication site, a copy of referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the Government.
B. Maintain onsite, a copy of referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.
1.04 AVAILABILITY
A. Code of Federal Regulation (CFR):
1. Available online, authorized by the National Archives and Records Administration (NARA) and the Government Printing Office (GPO), at www.gpoaccess.gov/cfr/index.html.
B. Federal Specifications, Standards, and Commercial Item Descriptions; and Military Specifications:
1. Copies of Federal Specifications, Standards, and Commercial Item Descriptions may be obtained from GSA Federal Supply Service, see the provision at FAR 52.211-1, Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.
2. Copies of Military Specifications may be obtained from Department of Defense, see the provision at FAR 52.211-2, Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST).
01 42 10 - 2
C. Bureau of Reclamation Documents:
1. Reclamation Safety and Health Standards (RSHS), 2009 edition, may be downloaded at http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:
United States Department of Commerce National Technical Information Service 5285 Port Royal Road Springfield, VA 22161 Telephone: 703-487-4650 or 1-800-553-6847
D. Industrial and Governmental Documents:
1. When a reference has a joint designation (e.g., ANSI/IEEE) these specifications generally cite the proponent organization (e.g., IEEE).
2. Addresses for obtaining industrial and governmental (other than Federal and Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in table 01 42 10A - Addresses for Specifications, Standards, and Codes.
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
AGC Associated General Contractors of America 333 John Carlyle Street, Suite 200 Alexandria, VA 22314 www.agc.org
202-293-8020
ASME American Society of Mechanical Engineers 3 Park Avenue New York, NY 10016-5990 www.asme.org
800-843-2763
ASTM ASTM International P.O. Box C700 100 Barr Harbor Drive West Conshohocken, PA 19428-2959 www.astm.org
610-832-9585
01 42 10 - 3
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
IEEE Institute of Electrical and Electronics Engineers 3 Park Avenue, 17th Floor New York, NY 10016-5997 www.ieee.org
212-419-7900
NIBS National Institute of Building Sciences 1090 Vermont Avenue, NW., Suite 700 Washington, D.C. 20005-4905 www.nibs.org
202-289-7800
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 42 10 - 4
Quality Procedures
01 46 00 - 1
SECTION 01 46 00
QUALITY PROCEDURES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 DEFINITIONS
A. Government Contract Quality Assurance: (from FAR 46.101) Various functions, including inspection, performed by the Government to determine whether a contractor has fulfilled the contract obligations pertaining to quality and quantity.
B. Contractor Quality Assurance / Quality Control (QA/QC): Activities performed by the Contractor to ensure work conforms to contract requirements.
1. The clause at FAR 52.246-12, Inspection of Construction, requires the Contractor to establish an inspection system to ensure quality.
2. Contractor QA/QC includes activities in addition to specified Contractor Quality Testing to ensure work conforms to contract requirements.
C. Contractor Quality Testing: Specified tests shall be performed by the Contractor.
1. The Government will evaluate results of these tests when determining acceptability of work.
2. The Contractor may use the test results as part of Contractor QA/QC.
a. The Government anticipates that these tests will be part of the Contractor’s QA/QC program; however, the tests do not relieve the Contractor of maintaining adequate quality system in accordance with the clause at FAR 52.246-12 - Inspection of Construction.
PART 2 PRODUCTS
Not Used
Quality Procedures
01 46 00 - 2
Testing Agency Services
01 46 20 - 1
SECTION 01 46 20
TESTING AGENCY SERVICES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for items of work requiring applicable testing agency services.
1.02 REFERENCE STANDARDS
A. ASTM International (ASTM)
1. ASTM D3666-13 Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 46 20-1, Testing Agency Services Plan:
1. Include:
a. Names of agencies to perform sampling and testing.
b. Agency accreditation to perform specified testing or agency qualifications to perform specified testing.
c. Resumes of personnel performing tests.
d. Samples of report forms.
2. No change in the approved plan may be made without written concurrence by the
COR.
C. RSN 01 46 20-2, Contractor Quality Testing Results.
1.04 QUALIFICATIONS
A. Testing Agency Organization:
1. Agencies Testing Bituminous Paving Materials: Meet requirements of ASTM D3666.
B. Equipment:
Testing Agency Services
01 46 20 - 2
1. Calibrate measuring devices, laboratory equipment, and instruments at established intervals.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CONTRACTOR QUALITY TESTING
A. Employ accredited independent agency to perform sampling, and testing.
3.02 GOVERNMENT CONTRACT QUALITY ASSURANCE
A. During the course of the work, the Government may perform quality assurance tests.
Tests performed by the Government will be used to ensure compliance with contract requirements and not as replacement for specified Contractor quality testing.
1. Upon request, make measuring and testing devices available for use by the Government for verification tests.
Temporary Utilities
01 51 00 - 1
SECTION 01 51 00
TEMPORARY UTILITIES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE C2-12 National Electrical Safety Code (NESC)
1.03 TEMPORARY ELECTRICITY
A. Provide electric power required for construction.]
B. Provide generators, transmission lines, distribution circuits, transformers, and other electrical equipment and facilities required for obtaining power and distributing power to points of use.
C. Comply with IEEE C2 clearances and spacing for temporary communications and supply lines.
1.04 TEMPORARY WATER
1.05 TEMPORARY WATER
A. Provide water required for construction purposes.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 REMOVAL
A. Remove temporary equipment and facilities upon completion of work under this contract.
Temporary Utilities
01 51 00 - 2
Vehicular Access and Parking
01 55 00 - 1
SECTION 01 55 00
VEHICULAR ACCESS AND PARKING
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REGULATORY REQUIREMENTS
A. Meet requirements established by jurisdictional authority for use of existing roadways and access trails; including seasonal or other limitations or restrictions.
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 55 00-1, Initial Digital Recording.
C. RSN 01 55 00-2, Post Construction Digital Recording.
1.04 SITE CONDITIONS
PART 2 PRODUCTS
2.01 MATERIALS
A. Materials to maintain and repair existing roadways and parking areas: In accordance with requirements of jurisdictional authority.
PART 3 EXECUTION
3.01 EXAMINATION
A. Investigate condition of available public or private roads for clearances, restrictions, bridge-load limits, bond requirements, and other limitations that affect or may affect access and transportation operations to and from the jobsite.
3.02 RECORDS
A. Make preconstruction video of surface conditions of roads that will be using during construction for haul routes, disposal areas, parking areas, and other uses.
1. DVD format with a minimum 720 pixel resolution.
Vehicular Access and Parking
01 55 00 - 2
2. Label:
a. Contract number and title.
b. Contractor’s name.
c. Date recording is made.
d. Preface video with this information.
3. OGR will be present during recording. Notify OGR at least 3 days prior to recording.
3.03 HAUL ROUTES
A. Perform work on rights-of-way established by Government as necessary to construct and maintain any roads, bridges, or drainage structures required for establishment and use of haul routes for construction operations.
B. Use existing available public highways, roads, or bridges as haul routes subject to applicable local regulations.
C. Minimize interference with or congestion of local traffic.
D. Provide barricades, flaggers, and other necessary precautions for safety of public where haul routes cross public highways or roads.
3.04 MAINTENANCE
A. Maintain roadways, parking areas and haul routes in a sound, reasonably smooth condition.
A. Maintain surfacing of gravel-surfaced and paved roads and parking areas in a smooth condition until completion and acceptance of all work under this contract.
3.05 REPAIR
A. Promptly repair any damage to access travelways.
3.06 REMOVAL
A. Remove materials used to construct temporary roadways, parking areas, and haul routes prior to contract completion. Recycle salvageable materials as approved by OGR.
Traffic Control
01 55 20 - 1
SECTION 01 55 20
TRAFFIC CONTROL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
B. California Manual on Uniform Traffic Control Devices
1. MUTCD, Rev 1, Part 6
2. Traffic Control, Manual on Uniform Traffic Control Devices, 2014 Edition http://www.dot.ca.gov/hq/traffops/engineering/mutcd/pdf/camutcd2014/ CAMUTCD2014.pdf
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 MAINTAINING TRAFFIC
A. Public access to the park will be closed during Seal Coat operations. Contractor shall submit a traffic control plan to the COR for approval 30 days prior to beginning Seal Coat Operations. Notification signs shall be posted 500 feet from the park entrance in both directions along Woollomes Avenue. Signs must be posted at least 7 days prior to Seal Coat operations and must include dates when the park will be closed and then reopened. All traffic control devices and signs shall meet the requirements set forth in the latest edition of the Manual on Uniform Traffic Control Devices.
3.02 TRAFFIC CONTROL
A. Meet requirements of RSHS, Section 9 and 20, and MUTCD, 2014 Edition.
http://www.dot.ca.gov/hq/traffops/engineering/mutcd/pdf/camutcd2014/CAMUTCD2014.pdf http://www.dot.ca.gov/hq/traffops/engineering/mutcd/pdf/camutcd2014/CAMUTCD2014.pdf
Traf…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .